Search results for: works

3051 results

A list of search results

29 March 2019 Industry Contribution

By Susanne den Hoed, HR Department at Temporary Works Design Temporary Works Design (TWD) is an ambitious and innovative engineering firm, working with major on- and offshore contractors to assist them with practical solutions for their wide variety of constructions and installation challenges. Specialized in the structural and mechanical design of custom installation equipment, TWD’s […]

1 March 2019 Wind Farm Update

Fugro plans to commence geotechnical survey operations at the Hollandse Kust (west) site in April, the company informed after recently winning the contract for the works with the Netherlands Enterprise Agency (RVO.nl). As the agreement is expected to be finalised soon, Fugro has already started preparing to carry out the project that will run until […]

1 November 2018 Wind Farm Update

104 out of 174 turbine monopile foundations and 66 out of 174 inter-array cables have been installed on the 1,218MW Hornsea Project One wind farm, Ørsted said.

13 September 2018 Training & Education

The Offshore Renewable Energy (ORE) Catapult is holding a workshop together with Narec Distributed Energy on the topic of connecting renewable energy and battery technologies to the electricity grid.

11 September 2018 Technology, Vessels

nCentric will provide internet access and wireless communication on Van Oord's Nessie onshore cable trencher which is set to be deployed for the Norther offshore wind farm.

10 September 2018 Grid Connection, Wind Farm Update

Triton Knoll onshore construction officially started in Lincolnshire on Monday, 10 September, as the project commenced work on the electrical system to transport power from the 860MW offshore wind farm to UK homes.

1 August 2018 Business & Finance, Contracts & Tenders

RanaWorks – a joint venture company set up between Italian RANA Diving SpA and Dutch Workships Contractors BV in January 2018 – has been awarded its first contract that will see the company working on an offshore wind project in Germany.

13 July 2018 Operations & Maintenance, Vessels

M.C. Construction (Cleveland) has completed the fabrication and mobilisation of steelwork for MPI Adventure ahead of the vessel's upcoming works on the removal, upgrade and re-installation of turbine blades at the London Array offshore wind farm.

10 July 2018 Contracts & Tenders, Wind Farm Update

Jan De Nul will commence works on the Northwester 2 offshore wind farm in Belgium in June 2019, the EPCI contractor informed as it announced the signing of a contract with Parkwind, the developer of the Belgian 219MW offshore wind farm.

10 July 2018 Vessels, Wind Farm Update

Van Oord's installation vessel Aeolus has wrapped up sea trials off the North Holland coast, marking the completion of the modification campaign that commenced in 2017. Now, the vessel is ready to start working on the Norther offshore wind farm. 

6 July 2018 Vessels

Van Oord has ordered lifting slings from Cortland, a global ropes and slings specialist, for the installation of monopiles and transition pieces at the Norther offshore wind farm in Belgium and Deutsche Bucht offshore wind farm in Germany.

6 July 2018 Wind Farm Update

Fugro has commenced marine site characterisation work at the Hornsea Project Two offshore wind farm site under a contract with Ørsted for geotechnical site investigation, which follows earlier contracts for geophysical investigation services at the site.

3 July 2018 Business & Finance, Operations & Maintenance, Vessels

Seacat Services has been awarded a new charter agreement for the Beatrice offshore wind farm, following two previously signed contracts under which two of its vessels are already supporting the works at the project site off Scotland.

2 July 2018 Grid Connection, Vessels, Wind Farm Update

Jack-Up Barge's vessel JB-115 has been deployed at the Kriegers Flak site off Denmark to accommodate the crew working on the hook up and commissioning of the substation that will be the heart of the Kriegers Flak Combined Grid Solution (CGS).

31 May 2018 Authorities, Wind Farm Update

New Jersey Governor Phil Murphy opened a new window of opportunity for the Atlantic City offshore wind farm to be built by signing the S1217 bill into law on 30 May, after two similar bills introduced in 2016 did not pass at the former Governor Chris Christie's desk.

31 May 2018

Triton Knoll Offshore Wind Farm Ltd will hold a series of public information days in June to inform local residents in Lincolnshire, UK, about the wind farm's onshore works before the initial activity begins in the coming weeks.

23 May 2018 Authorities, Business & Finance

Delaware’s Offshore Wind Working Group is hosting two public workshops in May to gather input for Governor John Carney on its draft recommendations regarding the development of offshore wind in the state.

17 May 2018 Grid Connection, Vessels, Wind Farm Update

Nexans has completed all export cable installation and burial works at the Beatrice site, where Siemens Transmission and Distribution team has started commissioning works on the recently installed second Offshore Transformer Module (OTM) in preparation for the energisation of the system. 

15 May 2018 Technology, Vessels

Belgium-based nCentric has installed its wireless communication systems onboard A2Sea's jack-up vessel Sea Installer for offshore installation works at the Rentel wind farm.

15 May 2018 Grid Connection, Operations & Maintenance

EDS HV Group has completed the onshore installation, termination and testing work of the platform cable on the EnBW Hohe See offshore wind project.

3 May 2018 Ports & Logistics, Vessels, Wind Farm Update

Belgian offshore wind developer Norther NV has announced the start of offshore construction works on the 370MW Norther offshore wind farm.

26 April 2018 Technology, Vessels

UK marine engineering company MAATS Tech has announced that it received a patent for its latest product, the Vessel Enabler, a modular chute that enables high-tension horizontal cable lay in deep waters and thus eliminates the need for a vertical lay tower or vertical lay system.

23 April 2018 Contracts & Tenders, Operations & Maintenance, Wind Farm Update

US Wind has selected two Baltimore-based companies for a range of specialized services related to the fabrication and installation of a meteorological tower necessary for environment activity monitoring at its proposed offshore wind farm in Maryland, US.

11 April 2018 Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm's onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

9 April 2018 Operations & Maintenance, Vessels, Wind Farm Update

Vroon's subsea-support walk-to-work (W2W) vessel VOS Stone has commenced operations at the 385MW Arkona offshore wind farm in the German Baltic Sea.

4 April 2018 Grid Connection, Wind Farm Update

Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.