Search results for: substation

1947 results

A list of search results

16 April 2019 Grid Connection, Wind Farm Update

Poland’s Mostostal Pomorze has loaded out the substation topside built for the Northwester 2 offshore wind farm in Gdansk. The load-out operations were performed on 13 and 14 of April. The topside is currently travelling to Aalborg in Denmark where Bladt Industries will continue working on it. In June 2018, Mostostal Pomorze signed a contract for prefabrication of […]

4 April 2019 Grid Connection, Wind Farm Update

Heavy lift vessel Seaway Strashnov has installed the jacket foundation and the substation topside on the 269MW Deutsche Bucht offshore wind farm in the German North Sea. “With the installation of the offshore substation completed, we have once more accomplished another milestone on schedule,” said Jens Poulsen, Project Director at Northland Deutsche Bucht GmbH. “In […]

25 March 2019 Grid Connection, Wind Farm Update

The topside for the Deutsche Bucht substation was shipped out from the Damen Shiprepair yard in Vlissingen, the Netherlands, to the installation site in the German North Sea on 19 March. The 269MW Deutsche Bucht offshore wind farm will comprise of 33 MHI Vestas 8.4MW wind turbines installed on 31 monopile foundations and two mono […]

13 March 2019 Grid Connection, Ports & Logistics, Wind Farm Update

The topside for the offshore substation of the Northland Power’s Deutsche Bucht offshore wind farm has been loaded on the pontoon at the Damen Shiprepair yard in Vlissingen, the Netherlands. The topside was loaded out on Sunday 24 February, Smulders said. The accompanying jacket was loaded on the pontoon earlier that week. The topside will […]

21 February 2019 Wind Farm Update

Smulders has loaded out the jacket foundation for the Northland Power’s Deutsche Bucht offshore substation in Vlissingen, the Netherlands. The jacket, weighing more than 1,700 tons, will be transported to the German North Sea at the beginning of March, weather permitting, Smulders said. The substation topside, which was assembled at the Damen Shiprepair Vlissingen yard, […]

6 December 2018 Grid Connection, Wind Farm Update

ScottishPower Renewables has announced Grove Wood, Friston, as the most appropriate location for development of the onshore substations required for its East Anglia Two and East Anglia One North offshore wind farms.

14 November 2018 Contracts & Tenders, Grid Connection, Operations & Maintenance, Technology, Wind Farm Update

Siemens has selected Sollatek to provide stabilisers for the Beatrice offshore wind farm’s onshore substation.

6 November 2018 Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

Ørsted has awarded an engineering, procurement, and construction (EPC) contract to Taiwan Cogeneration Corporation (TCC) to build two onshore substations, cable corridors, landfalls and transition joint bays for the first 900MW Greater Changhua projects.

26 October 2018 Grid Connection, Ports & Logistics, Wind Farm Update

Smulders, acting for and on behalf of the JV Iemants-Eiffage, has rolled out the substation topside for the Deutsche Bucht offshore wind farm at the yard of Damen Shiprepair Vlissingen. The milestone was achieved 10 months after starting the final assembly in January 2018. The topside was driven outside for further outfitting on 21 October. Offshore […]

24 September 2018 Contracts & Tenders, Grid Connection, Jobs & Recruitment, Vessels, Wind Farm Update

World Marine Offshore (WMO) has, through its daughter company, recently signed a contract with Navantia Shipyards to provide the onshore and offshore logistics services for the commissioning of the offshore substation on the East Anglia One wind farm.

31 August 2018 Grid Connection, Vessels, Wind Farm Update

The heavy-lift vessel Oleg Strashnov has installed the offshore substation for the East Anglia ONE wind farm in the southern North Sea, some 59 km from the coast of Lowestoft.

30 August 2018 Contracts & Tenders, Grid Connection, Wind Farm Update

Huadong Engineering Corporation, which plans to set up a 1.1GW wind farm off China’s Jiangsu Province, has contracted DNV GL to support feasibility studies for the project’s HVDC offshore substation, first of its kind in China.

22 August 2018 Wind Farm Update

The offshore high-voltage station (OHVS) for the Norther offshore wind farm arrived at the project site off Belgium today, 22 August, the developer informed via social media. 

16 August 2018 Grid Connection, Ports & Logistics, Wind Farm Update

The Norther Offshore High Voltage Station (OHVS) built at the Hoboken yard of ENGIE Fabricom by the consortium partners ENGIE Fabricom, Smulders and CG, has set sail towards its destination in the Belgian North Sea.

10 August 2018 Contracts & Tenders, Grid Connection, Wind Farm Update

The UK founded infrastructure group Balfour Beatty has secured a contract to build the onshore substation for Ørsted’s Hornsea Project Two offshore wind project on the East coast of England.

6 August 2018 Grid Connection, Wind Farm Update

All three offshore substations and the world’s first Reactive Compensation Substation (RCS) have been installed at Hornsea Project One, Ørsted, the owner and developer of the 1.2GW wind farm, said.

6 August 2018 Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

The Andalucía II offshore substation topside built for the 714MW East Anglia One offshore wind farm left Navantia’s Puerto Real shipyard in the Spanish province of Cádiz on Saturday, 4 August, Iberdrola said.

6 August 2018 Grid Connection, Wind Farm Update

Norther NV and Van Oord have loaded out the offshore substation topside destined for the 370MW Norther offshore wind farm.

30 July 2018 Grid Connection, Wind Farm Update

Bladt Industries has sent off the last two offshore substation topsides for Ørsted’s Hornsea Project One offshore wind farm from its site in Aalborg, Denmark.

4 July 2018 Wind Farm Update

Navantia has completed the construction of the East Anglia ONE offshore substation (topside), which is scheduled to set sail from the shipyard at Puerto Real in Spain in early August and arrive at the UK construction site in early September. 

28 June 2018 Grid Connection, Wind Farm Update

Heerema’s vessel Thialf has installed the offshore substation topside at the EnBW Hohe See offshore wind farm in the German North Sea.

19 June 2018 Grid Connection, Ports & Logistics, Wind Farm Update

The EnBW Hohe See substation topside has left ENGIE Fabricom’s yard in Hoboken, Belgium, and is now sailing towards the installation site in the German North Sea.

12 June 2018 Grid Connection, Ports & Logistics, Wind Farm Update

ENGIE Fabricom has loaded out the EnBW Hohe See substation topside at its yard in Hoboken, Belgium. The topside is expected to leave the yard and head to the installation site in the German North Sea soon. The substation’s jacket foundation was installed earlier this month. The substation, built by a consortium of ENGIE Fabricom, Iemants […]

11 June 2018 Operations & Maintenance, Technology, Wind Farm Update

B.offshore GmbH has completed maintenance work on the offshore substation of the Alpha Ventus offshore wind farm in Germany.

28 May 2018 Grid Connection, Ports & Logistics, Wind Farm Update

HSM Offshore has started the load-out of the offshore substation topside built for the Borkum Riffgrund 2 offshore wind farm at its yard in Schiedam, the Netherlands.

25 May 2018 Grid Connection, Ports & Logistics, Wind Farm Update

The jacket foundation for the Hohe See offshore substation has been loaded out at Smulders’ yard in Vlissingen, the Netherlands.