Search results for: onshore

3575 results

A list of search results

2 April 2019 Contracts & Tenders

Ørsted has contracted AMS Trenchless Specialists to conduct part of the onshore cable works for the Hornsea Project Two offshore wind farm in the UK. AMS Trenchless Specialists will conduct Horizontal Directional Drilling (HDD) at the landfall site in Horseshoe Point where the offshore cables meet the onshore cables under the more than GBP 1 million worth contract. Using […]

22 March 2019 Grid Connection, Wind Farm Update

The first onshore electrical cables destined for the Triton Knoll offshore wind farm have rolled out from production and are heading towards the Port of Boston, the UK. The High Voltage Alternating Current (HVAC) cables will make up the onshore cable network, connecting power from the 860MW offshore wind farm to the new onshore substation […]

25 February 2019 Authorities, Grid Connection, Wind Farm Update

The Scottish Government has approved the onshore planning application for the Inch Cape offshore wind project. Inch Cape Offshore Ltd (ICOL) submitted the planning application in principle to East Lothian Council in March last year proposing the former Cockenzie Power Station site as the new location for the project's onshore substation. The application and supporting Environmental Impact […]

8 February 2019 Business & Finance, Grid Connection, Wind Farm Update

The TFKable Group has produced the first part of the 220kV onshore high-voltage cable for the Moray East offshore wind farm in the UK. According to the company, the 220kV cable is now ready to be delivered from its Bydgoszcz plant in Poland for the 950MW offshore wind project. TFKable and VolkerInfra won the contract to […]

18 January 2019 Business & Finance

Ørsted is holding a series of community information events about the onshore cable route for the Hornsea Project Two offshore wind project in the UK. According to the Danish company, the aim of the events is that local people in North East Lincolnshire and East Lindsey find our more about the onshore cabling works for the […]

6 December 2018 Grid Connection, Wind Farm Update

ScottishPower Renewables has announced Grove Wood, Friston, as the most appropriate location for development of the onshore substations required for its East Anglia Two and East Anglia One North offshore wind farms.

14 November 2018 Contracts & Tenders, Grid Connection, Operations & Maintenance, Technology, Wind Farm Update

Siemens has selected Sollatek to provide stabilisers for the Beatrice offshore wind farm's onshore substation.

6 November 2018 Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

Ørsted has awarded an engineering, procurement, and construction (EPC) contract to Taiwan Cogeneration Corporation (TCC) to build two onshore substations, cable corridors, landfalls and transition joint bays for the first 900MW Greater Changhua projects.

1 October 2018 Business & Finance, Grid Connection, Wind Farm Update

Ørsted has awarded the South Korean LS Cable & System with a contract to supply the onshore cable for the Hornsea Project Two offshore wind farm.

10 September 2018 Grid Connection, Wind Farm Update

Triton Knoll onshore construction officially started in Lincolnshire on Monday, 10 September, as the project commenced work on the electrical system to transport power from the 860MW offshore wind farm to UK homes.

10 August 2018 Contracts & Tenders, Grid Connection, Wind Farm Update

The UK founded infrastructure group Balfour Beatty has secured a contract to build the onshore substation for Ørsted’s Hornsea Project Two offshore wind project on the East coast of England.

31 May 2018

Triton Knoll Offshore Wind Farm Ltd will hold a series of public information days in June to inform local residents in Lincolnshire, UK, about the wind farm's onshore works before the initial activity begins in the coming weeks.

15 May 2018 Grid Connection, Operations & Maintenance

EDS HV Group has completed the onshore installation, termination and testing work of the platform cable on the EnBW Hohe See offshore wind project.

13 April 2018 Authorities, Environment, Grid Connection, Wind Farm Update

The Scottish government has called-in Inch Cape Offshore Limited’s application for planning permission in principle for onshore components of the wind farm development.

11 April 2018 Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm's onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

4 April 2018 Grid Connection, Wind Farm Update

Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.

2 April 2018 Grid Connection, Wind Farm Update

Ørsted's Greater Changhua offshore wind projects in Taiwan are in the contracting process of TWD 3 billion (approximately EUR 83.6 million) onshore substation EPC (engineering, procurement, and construction) contract, the Danish company said.

28 March 2018 Grid Connection, Wind Farm Update

Triton Knoll Offshore Wind Farm Limited has reduced the number of onshore cable circuits required for electricity transport from the offshore wind farm to the national grid. According to the project team, this will help reduce the overall construction footprint of the project and realise planned reductions in costs.

15 March 2018 Authorities, Environment, Grid Connection, Wind Farm Update

UK's Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved an increase in the total works area for the Hornsea Project Two onshore substation site.

12 March 2018 Grid Connection, Wind Farm Update

After the Inch Cape Offshore team had spent the last year consulting on a new location for its onshore infrastructure, based on the feedback received on the initial application, the developer has now submitted a new application to East Lothian Council for planning permission in principle, proposing the former Cockenzie Power Station site as the new location for Inch Cape offshore wind farm's onshore substation.

14 February 2018 Environment, Grid Connection, Wind Farm Update

Pre-construction works are set to start around the onshore Triton Knoll electrical system, as innogy's 860MW offshore wind project gears up for the start of construction this summer.

6 December 2017 Environment, Operations & Maintenance, R&D, Wind Farm Update

Allen Archaeology is undertaking a series of geoarchaeological investigations during this and next week as part of onshore survey works on the Triton Knoll offshore wind farm.

13 November 2017 Wind Farm Update

As announced earlier, Vattenfall has now started holding public consultation to discuss its preliminary environmental information report (PEIR) for the Norfolk Vanguard offshore wind farm. On 11 November, a session which saw a record turnout was held in Happisburgh, where some of the residents voiced their concerns over the onshore infrastructure.

7 November 2017 Business & Finance

From April to September 2017, Siemens Gamesa marked strong performance in its offshore business with an increase of 16% in revenues. This contrasts the company's overall results for the period, as Siemens Gamesa reports a 12.3% fall in revenues.

27 October 2017 Environment, Grid Connection, Wind Farm Update

Lincolnshire-based company Allen Archaeology is currently carrying out a series of rapid walkover surveys at selected locations along the route of the Triton Knoll onshore cable corridor.

26 October 2017 R&D

APEM has produced detailed 3D maps of the 55km Hornsea Project Three onshore cable route, showing the heights, terrain and surface features.