Search results for: installs

386 results

A list of search results

18 July 2019 Wind Farm Update

Van Oord has installed the last jacket foundation on the East Anglia ONE offshore wind farm and delivered it to client ScottishPower Renewables. This marks the marine contractor's completion of its work for this 714MW UK wind project. As the main contractor, Van Oord transported and installed all 102 foundations. This is the largest number […]

28 June 2019 Vessels, Wind Farm Update

Fred. Olsen Windcarrier's jack-up vessel Bold Tern has completed the installation of 53 turbines at the Hornsea Project One offshore wind farm in the UK. Bold Tern is in charge of installing 88 out of the project's total 174 turbines, with A2SEA's Sea Challenger responsible for installing the remaining 86 units. According to Fred. Olsen Windcarrier, the […]

27 June 2019 Grid Connection, Wind Farm Update

TFKable has installed the first sections of the 220kV onshore high-voltage cable system at the Moray East offshore wind farm in Scotland. Each of the sections includes three circuits of ducted cable, the company said, adding that the next phase of production is in progress. At the beginning of the year, TFKable and VolkerInfra won […]

3 May 2019 Wind Farm Update

Fred. Olsen Windcarrier's jack-up Bold Tern has completed the installation of 28 turbines at the Hornsea Project One offshore wind farm in the UK. The vessel, which is in charge of installing half of the project's 174 turbines, has picked up the 8th batch of the Siemens Gamesa units in the Port of Hull and […]

16 April 2019 Vessels

Huadian Wenqiang, the Chinese self-elevating jack-up vessel, has installed its first turbine at an offshore wind project. According to Hengtong Group, the vessel installed the turbine at the project site offshore Zhanjiang in the Guangdong Province on 9 April. The company said the construction site is located in a typhoon-prone area with complex geological sea conditions, extreme working […]

26 December 2018 Business & Finance, Grid Connection

Nexans has completed the installation of the first four cables of the NordLink high voltage direct current (HVDC) subsea interconnector between Norway and Germany.

26 November 2018 Business & Finance

Fred. Olsen Windcarrier has marked a milestone in offshore wind turbine installation as it installed the 400th unit.

1 October 2018 Technology, Wind Farm Update

Heerema Marine Contractors' vessel Aegir has installed the Delft Offshore Turbine (DOT) at the Princess Amalia offshore wind farm (Prinses Amaliawindpark) in the Netherlands.

3 September 2018 Wind Farm Update

A2Sea’s jack-up vessel Sea Installer has completed the installation of all 42 turbines at the Rentel offshore wind farm in Belgium.

7 August 2018 Grid Connection

Seaway Heavy Lifting's vessel Oleg Strashnov has installed the jacket foundation for TenneT's Borssele Alpha offshore transformer station in the Dutch North Sea.

16 July 2018 Vessels

Swire Blue Ocean's jack-up vessel Pacific Orca has installed the first of the total of 84 Siemens Gamesa 7MW wind turbines at the Beatrice offshore wind farm site in the Outer Moray Firth, Scotland. 

7 June 2018 Wind Farm Update

Heerema’s vessel Thialf has installed the jacket foundation for the EnBW Hohe See offshore substation (OSS) at the project site in the German North Sea.

20 April 2018 Ports & Logistics, Vessels, Wind Farm Update

GeoSea has installed all of the transition pieces at the 396MW Merkur offshore wind farm in the German North Sea using A2SEA’s jack-up vessel Sea Challenger.

20 March 2018 Vessels

Marine Designs has installed a new pontoon in Barrow, which will serve for the berthing of crew transfer vessels (CTVs) working on Ørsted's offshore wind farms.

6 March 2018 Vessels, Wind Farm Update

Jan De Nul's offshore installation vessel Vole au vent has installed the first monopile on Ørsted's 450MW Borkum Riffgrund 2 offshore wind farm in the German North Sea.

19 February 2018 Grid Connection, Wind Farm Update

Jan De Nul has installed the first of the two gravity-based foundations that will support the offshore substations on the 605MW Kriegers Flak offshore wind farm in the Danish Baltic Sea.

22 December 2017 Technology, Wind Farm Update

Chinese wind turbine manufacturer and offshore wind farm developer, CSIC (China Shipbuilding Industry Corporation) HaiZhuang Windpower, informed on 21 December that two of its H128-5MW wind turbines are now installed off in Fujian Province and connected to the grid.

18 December 2017 R&D, Vessels, Wind Farm Update

A2SEA’s jack-up vessel Sea Installer has installed the last turbine at Ørsted’s 573MW Race Bank offshore wind farm located off the North Norfolk coast in the UK.

8 December 2017 Grid Connection, Ports & Logistics, R&D, Vessels, Wind Farm Update

Nexans' cable laying vessel Nexans Skagerrak has completed the laying and burial of the first 70-kilometer 220kV export cable which will connect the 588MW Beatrice offshore wind farm to the Scottish grid.

4 December 2017 Vessels, Wind Farm Update

Seaway Heavy Lifting (SHL) has installed the 86th and final four-pile set at the Beatrice offshore wind farm site. SHL carried out the piling work with the heavy-lift vessel Stanislav Yudin, which will now re-mobilise for jacket foundation installation.

27 September 2017 Grid Connection, Vessels, Wind Farm Update

The foundation for the offshore substation (OSS) at Belgian Rentel offshore wind farm was installed at the project site last week, STX Europe Offshore Energy reported yesterday, 26 September. 

20 September 2017 Wind Farm Update

The last of 116 wind turbines at the Rampion offshore wind farm was installed today. 

6 September 2017 Wind Farm Update

Jan De Nul Group has completed the installation and burial of the export cables for DONG Energy’s Race Bank offshore wind farm in the United Kingdom.

15 August 2017 Wind Farm Update

Dutch offshore construction specialist Van Oord has installed all 87 foundations at DONG Energy's 659MW Walney Extension wind farm in the Irish Sea.

14 August 2017 Vessels, Wind Farm Update

Seaway Heavy Lifting's vessel Oleg Strashnow has installed the first of 86 jacket foundations on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

27 July 2017 Wind Farm Update

France-based offshore services provider Bourbon has completed the installation of the mooring system for the Floatgen wind turbine – first of its kind in France – at the SEM-REV site off Brittany. The turbine will be installed by the end of the year.