Search results for: eew spc

14783 results

A list of search results

  • 23 February 2016

    Bladt Industries upended the first transition piece for the Veja Mate offshore wind farm, weighing 293.5 tonnes. As announced last summer, a joint venture between Bladt industries and EEW SPC won the contract for building foundations for the Veja Mate Offshore Wind Farm. Bladt’s scope in the project is to build 67 transition pieces which […]

  • 26 April 2019
    Wind Farm Update

    DEME Offshore installed the final of the 174 monopile foundations on the 1.2GW Hornsea Project One offshore wind farm on Thursday, 25 April. The first monopile was installed at the site some 120 kilometres off the Yorkshire coast in the UK in January 2018. According to DEME, four of the company’s jack-ups has since worked at […]

  • 17 August 2017
    Wind Farm Update

    The first set of transition pieces built by Bladt Industries for the 385MW Arkona offshore wind farm has arrived to the Mukran Port on Germany’s Rügen island.

  • 24 June 2019
    Wind Farm Update

    The installation of foundations has kicked off at the Formosa 1 Phase 2 offshore wind project in Taiwan. The installation began in early June, a spokesperson from COWI, who designed all the steelwork for the 20 monopiles and transition pieces, told Offshore WIND. Seaway Yudin is installing the foundations, which comprise monopiles produced by Germany’s EEW SPC and transition pieces manufactured by […]

  • 25 October 2018
    Business & Finance, Contracts & Tenders, Grid Connection, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Ørsted has added Bladt Industries, Nexans and Cordeel to the list of suppliers and contractors for the 752MW Borssele 1 and 2 wind farm in the Dutch North Sea, according to Henrik Egholm, EPC director Borssele 1 and 2.

  • 15 May 2020
    Wind Farm Update

    The first foundation at the Kriegers Flak offshore wind farm is now in place. Van Oord’s heavy lift vessel Svanen arrived at the project site off Denmark a few days ago to begin the installation work. The vessel will install a total of 72 monopile foundations, with the work expected to be completed in the […]

  • 26 October 2017
    Wind Farm Update

    Bladt Industries has shipped the remaining five transition pieces (TPs) for the Arkona offshore wind farm from the Port of Aalborg to Sassnitz, Germany.

  • 4 May 2017
    Wind Farm Update

    Offshore Structures Britain (OSB) has shipped out the last six transition pieces built for DONG Energy’s Walney Extension offshore wind farm.

  • 23 January 2018
    Ports & Logistics, Vessels, Wind Farm Update

    GeoSea’s jack-up Innovation has loaded the first set of monopile foundations in Vlissingen, the Netherlands, and is now en route to install them on Orsted’s 1.2GW Hornsea Project One wind farm off the UK, DEME said.

  • 11 September 2019
    Contracts & Tenders, Wind Farm Update

    Offshore foundations manufacturer EEW has signed a contract with Denmark’s ProCon Wind Energy for the electrical construction of 30 transition pieces for the Hornsea Project Two offshore wind farm. The electrical construction work will take place at EEW Offshore Structures (Britain) Ltd.’s site in the United Kingdom in the first half of 2020. ”We are extremely […]

  • 28 September 2017
    Wind Farm Update

    DONG Energy has appointed Con4Mare as the marine warranty surveyor for the transport and installation of the transition pieces and monopile foundations at the 1.2GW Hornsea Project ONE offshore wind farm.

  • 1 April 2016
    Business & Finance, Grid Connection, Vessels, Wind Farm Update

    EEW SPC Rolls Out World’s Heaviest Monopile The heaviest monopile ever produced for an offshore wind project left the production site of EEW Special Pipe Constructions GmbH in Rostock on 2 March, and will be ready to be installed at the 402MW Veja Mate offshore wind farm within the next few months. A2SEA Cuts to […]

  • 24 November 2017
    Wind Farm Update

    Offshore Structures Britain (OSB) has installed the first external platform on one of the transition pieces being built for the Hornsea Project One offshore wind farm in the UK part of North Sea.

  • 27 February 2017
    Wind Farm Update

    Poland’s Energomontaż-Północ Gdynia (EPG) has loaded and shipped out 26 out of 30 external platforms ordered by Bladt Industries for the 385MW Arkona offshore wind farm.  Ten platforms with a total weight 240 tonnes were loaded onto Rix Pacific from EPG’s premises in Gdynia as part of the latest shipment. The load-out of the last four platforms is planned for […]

  • 6 March 2016

    EEW SPC Rolls Out World’s Heaviest Monopile The heaviest monopile ever produced for an offshore wind project left the production site of EEW Special Pipe Constructions GmbH in Rostock on 2 March, and will be ready to be installed at the 402MW Veja Mate offshore wind farm within the next few months. Fred. Olsen Windcarrier […]

  • 13 May 2019
    Ports & Logistics, Vessels, Wind Farm Update

    Transition pieces and monopiles for the Formosa 1 Phase 2 offshore wind farm have started arriving at the Taichung Port in Taiwan. And so have the vessels that will install the 20 monopile foundations and the wind turbines at the site in the Taiwan Strait, Ørsted, one of the owners of the 120MW wind farm, said. Seaway […]

  • 20 November 2019
    Contracts & Tenders

    EEW Group has contracted Hutchinson Engineering Ltd for the fabrication and on-site assembly of Suspended Internal Platforms (SIPs) for the Hornsea Two offshore wind project. The Cheshire-based company is in charge of providing 30 SIPs, each weighing 10t and towering 12m high, that will be suspended inside the transition pieces. In June, Ørsted, the developer […]

  • 12 December 2016
    Wind Farm Update

    Smulders has completed the first jacket foundation section for the Beatrice offshore wind farm, for which the company is building a total of 28 jackets. according to Beatrice project’s social media pages.  Smulders Projects was awarded the contract for 28 Beatrice jacket foundations by Seaway Heavy Lifting, which is in charge of the engineering, procurement, construction, transport and […]

  • 20 August 2019
    Wind Farm Update

    Jan De Nul has completed the installation of all 20 turbine foundations at the Formosa 1 Phase 2 offshore wind farm in Taiwan. Seaway Yudin began installing the foundations at the beginning of June at the project site some 6km off the west coast of the Miaoli district in the Taiwan Strait. Germany’s EEW SPC produced the monopiles and Thailand’s CUEL Limited manufactured […]

  • 18 May 2020
    Wind Farm Update

    EEW’s manufacturing facilities in Asia have produced half of the total of 188 pin piles for Taiwan’s Formosa 2 offshore wind farm. Formosa 2 will comprise 47 jacket foundations, with each jacket secured to the seabed with four pin piles. Each pile is approximately 65 metres long, has a diameter of 2.4 metres and weighs 240 […]

  • 10 April 2020
    Wind Farm Update

    DEME has installed half of the 94 monopile foundations at the Borssele 1+2 offshore wind farm site.

  • 22 October 2019
    Wind Farm Update

    EEW Offshore Structures Britain (OSB) has completed the load-out of the first six transition pieces built for the Borssele 1+2 offshore wind farm in the Dutch North Sea. The Teesside-based company will manufacture and deliver a total of 35 transition pieces for Ørsted’s 752MW wind farm. ALE Heavy Lift is providing the transportation services. Denmark’s Bladt […]

  • 24 March 2017
    Vessels, Wind Farm Update

    The installation vessel Aeolus has arrived at Belfast Harbour ahead of the foundation installation works at the Walney Extension offshore wind farm in the UK.

  • 20 August 2018
    Contracts & Tenders, Operations & Maintenance

    The Thailand-based oil & gas company CUEL Limited has secured a contract with Jan De Nul for the fabrication and supply of 20 transition pieces for the Formosa 1 Phase 2 project in Taiwan, marking its first offshore wind contract.

  • 31 May 2018
    Contracts & Tenders, Operations & Maintenance

    UK-based Mech-Tool Engineering Ltd (MTE) has won a contract by EEW OSB to fabricate 20 suspended internal support structures (SIPS) for the Hornsea Project One offshore wind farm, which marks the company’s second contract for Ørsted’s project.

  • 2 June 2017
    Wind Farm Update

    Beatrice Offshore Windfarm Ltd (BOWL) has shared a photo of the teams at Burntisland Fabrications’ (BiFab) facility in Methil preparing to upend one of the jacket foundations built for the 588MW Beatrice offshore wind farm.