Search results for: eew spc

112 results

A list of search results

27 February 2018 Operations & Maintenance, Wind Farm Update

EEW Offshore Structures (Britain) Ltd has produced its 100th transition piece, which is due to set sail to Ørsted’s Hornsea Project One offshore wind farm.

28 November 2017 Business & Finance, Contracts & Tenders, Wind Farm Update

Danish offshore wind developer Ørsted has contracted the Teesside-based EEW OSB (formerly OSB) and Denmark’s Bladt Industries to manufacture 30 and 28 transition pieces respectively for the 174-turbine Hornsea Project One.

14 September 2015

[…]

21 November 2014 Business & Finance

[…]

11 September 2019 Contracts & Tenders, Wind Farm Update

[…]

27 August 2019 Ports & Logistics, Wind Farm Update

[…]

20 August 2019 Wind Farm Update

[…]

24 June 2019 Wind Farm Update

[…]

13 May 2019 Ports & Logistics, Vessels, Wind Farm Update

[…]

26 April 2019 Wind Farm Update

[…]

9 April 2019 Wind Farm Update

[…]

15 February 2019 Wind Farm Update

[…]

21 December 2018 Contracts & Tenders, Wind Farm Update

Vattenfall has contracted Bladt Industries to deliver 72 transition pieces for the Danish Kriegers Flak offshore wind farm.

25 October 2018 Business & Finance, Contracts & Tenders, Grid Connection, Operations & Maintenance, Ports & Logistics, Wind Farm Update

Ørsted has added Bladt Industries, Nexans and Cordeel to the list of suppliers and contractors for the 752MW Borssele 1 and 2 wind farm in the Dutch North Sea, according to Henrik Egholm, EPC director Borssele 1 and 2.

3 October 2018 Wind Farm Update

GeoSea has installed half of the monopile foundations at the Hornsea Project One offshore wind farm in the UK.

20 August 2018 Contracts & Tenders, Operations & Maintenance

The Thailand-based oil & gas company CUEL Limited has secured a contract with Jan De Nul for the fabrication and supply of 20 transition pieces for the Formosa 1 Phase 2 project in Taiwan, marking its first offshore wind contract.

31 May 2018 Contracts & Tenders, Operations & Maintenance

UK-based Mech-Tool Engineering Ltd (MTE) has won a contract by EEW OSB to fabricate 20 suspended internal support structures (SIPS) for the Hornsea Project One offshore wind farm, which marks the company’s second contract for Ørsted’s project.

3 April 2018 Business & Finance, Contracts & Tenders, Ports & Logistics, Technology

Bay State Wind, the US-based 50-50 partnership between Ørsted and Eversource developing an offshore wind project in Massachusetts, has entered into an agreement with the steel pipe manufacturing specialist EEW to open and staff a Massachusetts facility to manufacture offshore wind turbine foundations.

16 March 2018 Business & Finance, Contracts & Tenders, Grid Connection

Belgian transmission system operator Elia is on track to complete the Modular Offshore Grid by September 2019 after awarding all the main contracts for the project.

8 March 2018

Cathie Associates have performed a study which enabled the reduction of noise in the water column created by monopile driving at the Arkona offshore wind farm site in Germany, the company informed after all the 60 foundations were installed.

8 February 2018 Ports & Logistics, Vessels, Wind Farm Update

SAL Heavy Lift’s crane vessel Svenja has delivered 12 monopile foundations for the Hornsea Project One wind farm to the Able Seaton Port on the River Tees.

23 January 2018 Ports & Logistics, Vessels, Wind Farm Update

GeoSea’s jack-up Innovation has loaded the first set of monopile foundations in Vlissingen, the Netherlands, and is now en route to install them on Orsted’s 1.2GW Hornsea Project One wind farm off the UK, DEME said.

24 November 2017 Wind Farm Update

Offshore Structures Britain (OSB) has installed the first external platform on one of the transition pieces being built for the Hornsea Project One offshore wind farm in the UK part of North Sea.

9 November 2017 Wind Farm Update

The installation of monopiles at the Arkona offshore wind farm site has been completed ahead of schedule with the last of the total of 60 monopiles now in place, allowing for an early start of the installation of the transition pieces.