  • 15 March 2013
    Business & Finance, Grid Connection

    Elia Asset nv is looking for contractors who will undertake the design, engineering, supply, construction, installation and commissioning of an Offshore High Voltage Substation with jacket substructure and top structure (Alpha and/or Beta OHVS) and/or a topside modular construction of an OHVS (Alpha OHVS for an artificial island) for the project Belgian Offshore Grid (BOG). […]

  • 9 June 2020
    Grid Connection

    ENGIE Fabricom and Iemants have started engineering work on the Hollandse Kust Noord (HKN) offshore transformer station, with construction work for the topside and the jacket scheduled to start in October. As previously reported, TenneT TSO selected the ENGIE Fabricom – Iemants joint venture to construct the offshore substation for the Hollandse Kust Noord wind […]

  • 15 September 2015
    Grid Connection

    The European transmission system operator, TenneT, is inviting candidates for the qualification system Grid-At-Sea.nl Platforms and Transport & Installation (T&I). In order to inform all candidates in general about Offshore Grid NL (Wind op Zee) and specifically about this Qualification System, an information meeting will be organized by TenneT on 18 September 2015. The presentation […]

  • 23 January 2018
    Grid Connection, Wind Farm Update

    HSM Offshore, the EPC contractor for the Borkum Riffgrund 2 offshore substation, installed the two transformers that make the topside structure on 13 January. The topside left the construction hall for the installation of the transformers and was brought back into the covered construction area after the lifting operation was completed. 

  • 23 July 2020
    Contracts & Tenders, Operations & Maintenance

    Norther has issued two calls for tenders for service and maintenance of the Offshore High Voltage Substation (OHVS) at the Belgian Norther offshore wind farm. One contract will be awarded for service and maintenance of the OHVS topside with its electrical components, and one for mechanical services also including the platform’s foundation. The deadline for […]

  • 4 April 2016
    Grid Connection, Vessels, Wind Farm Update

    A 1,888 tonne topside built for the high voltage substation of the 400 MW Horns Rev 3 offshore wind farm left Schiedam last weekend and is en route to Esbjerg, Denmark. The transportation of the topside is being carried out by Royal Wagenborg, using the company’s largest tug, Waterland, and the largest barge, Wagenborg Barge 9.  A specialized team of Wagenborg ballast engineers assisted […]

  • 24 January 2018
    Grid Connection, Operations & Maintenance, Wind Farm Update

    The installation of the offshore transformer substation topside for the 309MW Rentel offshore wind farm in the Belgian North Sea has been postponed, DEME Group told Offshore WIND.

  • 26 April 2016
    Grid Connection, Vessels, Wind Farm Update

    Seaway Heavy Lifting has shared this photo of the heavy-lifting vessel Stanislav Yudin setting the topside of the Horns Rev C substation down onto the jacket construction. The topside was transported from the Port of Esbjerg to the installation site some 20 kilometers off the Danish North Sea coast on board Royal Wagenborg’s largest barge, Wagenborg Barge 9. The 1,888 […]

  • 18 May 2016

    DONG Energy has ordered three substation topsides for its Hornsea Project One offshore wind farm from Bladt Industries. Bladt and its partner Semco Maritime deemed the order as historical, since this is the first time that a contract has been signed for three topsides at the same time. Bladt Industries is responsible for fabricating the steel structures of the substation […]

  • 10 December 2013

    DolWin Beta’s topside was placed onto the substructure yesterday. The jacking up of DolWin Beta’s topsides started on December 5. Drydocks World lifted the 10,000-tonne topside of the platform structure to a height of 52.8 metres from the dock bottom. On Saturday, the substructure was moved in position under the topside. Aibel is designing and […]

  • 11 June 2020
    Grid Connection, Wind Farm Update

    The topside for the Triton Knoll Offshore Substation Platform (OSP) East has left Vlissingen in the Netherlands and is en route to the installation site off Lincolnshire, UK. Once there, the topside will be lowered onto its monopile foundation by Seaway 7’s installation vessel Seaway Strashnov. Seaway Strashnov installed the Triton Knoll OSP West topside […]

  • 13 March 2019
    Grid Connection, Ports & Logistics, Wind Farm Update

    The topside for the offshore substation of the Northland Power’s Deutsche Bucht offshore wind farm has been loaded on the pontoon at the Damen Shiprepair yard in Vlissingen, the Netherlands. The topside was loaded out on Sunday 24 February, Smulders said. The accompanying jacket was loaded on the pontoon earlier that week. The topside will […]

  • 9 June 2014
    Grid Connection, Technology

    Heerema has successfully loaded the HVDC topside of Siemens’ HelWin beta platform onto a seagoing barge. On Saturday, the HelWin beta topside was loaded onto the H-542 barge, operated by Heerema Marine Contractors, a sister division of Heerema Fabrication Group, which built the platform. In October 2012, Heerema started the construction of the 10,200-ton HVDC […]

  • 8 December 2016
    Wind Farm Update

    STX France has started fabrication works for the offshore substation that will be installed at the Rentel offshore wind farm site in Belgium. The first steel cutting for the substation took place yesterday at STX France’s yard in Saint-Nazaire. Design of both the foundation and the topside has been carried out by STX France. The substation will comprise a 1,600t monopile foundation […]

  • 2 June 2016
    Wind Farm Update

    Engie Fabricom and Iemants completed the load-out of the topside for the 258MW Burbo Bank Extension offshore wind farm at the ENGIE Fabricom’s Hoboken yard on 30 May. The 1180-tonne topside was placed next to the 985-tonne offshore substation jacket on the pontoon. The jacket was loaded onto the pontoon on 11 May. The topside […]

  • 19 March 2013

    KCI completed the engineering work for German Offshore wind project Riffgat in March 2013. In April 2010, KCI was awarded an engineering contract for structural, utility systems and 3D interfacing design for both the jacket and the topside. Just before sail away in February this year, KCI engineers carried out a final inspection of the […]

  • 10 June 2020
    Grid Connection, Wind Farm Update

    The second Triton Knoll offshore substation platform (OSP) topside has been loaded onto a barge and fastened in Vlissingen, the Netherlands. The Triton Knoll OSP East topside was seafastened onto the Greenbarge 3 at Damen Shiprepair Vlissingen. The Greenbarge 3 and the topside will be towed offshore the UK to be installed on the accompanying […]

  • 21 July 2017
    Wind Farm Update

    The jacket foundation for the Borkum Riffgrund 2 offshore substation was installed at the offshore construction site on 19 July.

  • 7 July 2016
    Grid Connection

    Trelleborg’s engineered products operation has been awarded a contract by Petrofac for its first floatover installation of an offshore converter platform – BorWin3 (BorWin Gamma) wind farm project. A consortium between Siemens and Petrofac has been contracted by TenneT to design, build and install the 900MW Offshore HVDC converter platform BorWin gamma. The platform will be […]

  • 10 March 2017
    Grid Connection, Wind Farm Update

    The load-out of the first of two substations built by the Engie Fabricom-Iemants consortium for DONG Energy’s 660MW Walney Extension offshore wind farm took place in Hoboken, Belgium, on Thursday, 9 March. The topside was removed from its base on the production site and put on the pontoon. The topside was loaded next to the jacket foundation which […]

  • 28 May 2020
    Grid Connection

    Dubai-based Drydocks World has held a steel-cutting ceremony for the Hollandse Kust Zuid Beta offshore substation topside. This is the third topside that Drydocks World will be constructing for Petrofac and end-client TenneT, and the second project for the Hollandse Kust Zuid zone. The 700 MW High Voltage Alternating Current (HVAC) platform will, together with […]

  • 15 December 2013
    Grid Connection, Technology

    At Heerema Zwijndrecht, one of the manufacturing yards of Heerema Fabrication Group (HFG), fabrication of the HelWin bèta topsides for Siemens, yesterday reached the phase during which the transformer equipment will be installed outside. In October 2012, Heerema Zwijndrecht started the construction of the 10,200 tons weighing HVDC (High Voltage Direct Current) topsides, after contract […]

  • 26 October 2018
    Grid Connection, Ports & Logistics, Wind Farm Update

    Smulders, acting for and on behalf of the JV Iemants-Eiffage, has rolled out the substation topside for the Deutsche Bucht offshore wind farm at the yard of Damen Shiprepair Vlissingen. The milestone was achieved 10 months after starting the final assembly in January 2018. The topside was driven outside for further outfitting on 21 October. Offshore […]

  • 5 April 2019
    Grid Connection

    The topside of Elia’s Offshore SwitchYard (OSY) platform has left Heerema Fabrication Group’s construction site in Zwijndrecht, the Netherlands, and was loaded onto a barge. According to Elia, the topside left the construction site this morning, which represents the first step in the journey towards its final destination in the Belgian North Sea. The topside will […]

  • 7 April 2016
    Grid Connection

    The jacket construction and the topside built for the Horns Rev C offshore substation have reached the Port of Esbjerg, from where the pieces will be shipped to the installation site some 20 kilometers off the Danish North Sea coast by the end of this week, weather permitting. The installation of the two pieces is expected to start […]

  • 19 April 2017
    Vessels, Wind Farm Update

    Scaldis has installed the 2000-tonne offshore substation topside on the 400MW Rampion offshore wind farm some 14 kilometres off the Sussex coast.