  • 18 May 2020
    Wind Farm Update

    The 32nd and final wind turbine at the Trianel Windpark Borkum II (TWBII) site was installed on Sunday, 17 May. “The last big components were installed Saturday, and final bolt and nut Sunday early morning”, Fred. Olsen Windcarrier informed on 18 May. Fred. Olsen Windcarrier was contracted in February to install eleven turbines on the […]

  • 16 March 2020
    Contracts & Tenders

    Trianel Windkraftwerk Borkum II GmbH & Co. has issued a tender seeking transport services of personnel and material for the Trianel Windpark Borkum II (TWBII) in Germany. The contractor will be in charge of providing the transport of personnel and material between the harbor of Eemshaven in the Netherlands and the project construction site some 40km […]

  • 14 May 2020
    Wind Farm Update

    The Blue Tern installation vessel is currently at the Trianel Windpark Borkum II (TWBII) project site with the last two turbines to be installed. OffshoreWIND.biz contacted Fred. Olsen Windcarrier after Buss Energy Group, which has been providing port logistics for wind turbine installation, reported it had completed its project for Trianel wind farm Borkum II. […]

  • 24 July 2019
    Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent has begun loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII offshore wind farm will comprise 32 Senvion 6.2M152 turbines installed at the project site some 40km north of the island of Borkum in Germany. Taillevent loaded the first three towers, blades […]

  • 4 February 2020
    Wind Farm Update

    Twenty-one of the 32 Senvion 6.2M152 turbines have been installed on the Trianel Windpark Borkum II (TWBII) offshore wind project in Germany.

  • 4 December 2018
    Contracts & Tenders, Wind Farm Update

    Jan De Nul Group has awarded Global Wind Service (GWS) with the installation and completion scope for the 200MW Trianel Windpark Borkum II (TWBII) offshore wind farm in the German North Sea.

  • 4 March 2020
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Blue Tern is on its way to the Trianel Windpark Borkum II (TWBII) offshore wind farm loaded with the first batch of turbine components. Blue Tern was contracted to finish installing the remaining 11 Senvion turbines on the project offshore Germany, replacing Jan De Nul’s Taillevent which is reportedly on its way to start a […]

  • 15 August 2019
    Wind Farm Update

    Jan De Nul’s vessel Taillevent has installed the first turbine at the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 turbines installed on monopile foundations at the site some 40km north of the island of Borkum in the German North Sea. Taillevent is loading the turbine components in sets […]

  • 15 July 2019
    Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent is en route to Eemshaven in the Netherlands to start loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. Located in the German North Sea, the 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 wind turbines installed at the site some 40 […]

  • 10 May 2017
    Business & Finance, Wind Farm Update

    The 200MW Trianel Windpark Borkum II (TWBII) offshore wind farm project in the German North Sea has reached financial close, Green Giraffe said. Green Giraffe was the sole financial advisor to TWBII, initially owned by EWE and Trianel. Green Giraffe helped arrange the sale of a minority stake to ewz, the Swiss utility, and compatriot […]

  • 13 November 2019
    Wind Farm Update

    Senvion has delivered the last turbine for the Trianel Windpark Borkum II (TWBII) offshore wind project in Germany. According to Senvion, all components for the 200MW wind farm have been finished and shipped to Eemshaven. Trianel Windpark Borkum II comprises 32 Senvion 6.2M152 turbines installed on monopile foundations at the site some 40km north of the […]

  • 17 September 2019
    Operations & Maintenance

    C-bed’s accommodation vessel Wind Innovation is servicing the installation and commissioning phases of the Trianel Windpark Borkum II (TWBII) project in Germany. The DP2 walk-to-work vessel began its deployment at the project site some 45km off the coast of the Borkum island at the end of July. C-bed is using Eemshaven as the base port for crew change and […]

  • 9 November 2018
    Wind Farm Update

    27 out of the 32 monopile foundations have been installed on the 200MW Trianel Windpark Borkum II (TWB II) offshore wind farm in the German North Sea.

  • 3 December 2018
    Wind Farm Update

    All 32 turbine foundations for the 200MW Trianel Windpark Borkum II offshore wind farm have been installed at the construction site some 45 kilometers north of the island of Borkum in the German North Sea. “We are right on schedule with the construction of the offshore wind farm. We were able to compensate for the […]

  • 29 June 2018
    Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has installed the first monopile at the Trianel Windpark Borkum II (TWB II) in Germany. 

  • 5 December 2019
    Wind Farm Update

    The Trianel Windpark Borkum II (TWBII) offshore wind project has reached the halfway turbine installation point as 16 out of 32 units have been erected. Jan De Nul’s jack-up vessel Taillevent installed the 16 Senvion 6.2M152 turbines in the northeastern part of the project site offshore Germany, with the installation of the remaining 16 units […]

  • 2 August 2019
    Wind Farm Update

    Jan De Nul’s jack-up Taillevent has started installing the first wind turbine on the 200MW Trianel Windpark Borkum II (TWBII) wind farm offshore Germany. Taillevent loaded the first three sets of turbine components at Buss Terminal Eemshaven prior to transporting them to the site some 40 kilometres north of the island of Borkum in the German North Sea. […]

  • 2 August 2019
    Vessels, Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent has left Eemshaven with a first load of turbine components to be installed on the Trianel Windpark Borkum II (TWBII) offshore wind farm in the German North Sea. Taillevent is loading the turbine components at the Buss Terminal Eemshaven in sets of three and transporting them to the installation […]

  • 14 November 2019
    Wind Farm Update

    13 of the 32 Senvion 6.2M152 wind turbines have been installed on the 200MW Trianel Windpark Borkum II (TWBII) offshore wind farm in the German North Sea, Trianel GmbH said. Eleven out of the thirteen turbines installed have been commissioned, according to Trianel. The wind turbines are being loaded by Jan De Nul’s jack-up Taillevent at Buss […]

  • 25 February 2020
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Blue Tern has been contracted to finish installing the remaining eleven Senvion 6.2M152 turbines on the Trianel Windpark Borkum II (TWB II) in the German North Sea. Blue Tern will replace Jan De Nul’s Taillevent on TWB II as this jack-up is reportedly on its way to start a project […]

  • 10 November 2017
    Business & Finance

    Senvion posted an increase in revenues at its offshore segment for the first nine months of 2017, however, the third quarter itself saw a decline compared to Q3 2016. The offshore revenues are driven by the completion of wind turbine installation at Nordsee One, which especially reflected on the results for the first half of the year and only to some extent on those for the third quarter.