  • 6 March 2013
    Wind Farm Update

    The beginning of the month of March has seen the crane vessel, Stanislav Yudin, launch the transportation of tripods from the offshore terminal in Bremerhaven BLG to the Trianel Wind Farm Borkum. The vessel has been transporting two by two of these up to 900 ton and 60 meter high tripods to the construction site […]

  • 6 November 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s crane vessel Stanislav Yudin has installed 84 out of the 86 sets of piles for jacket foundations on the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

  • 28 August 2017
    Vessels, Wind Farm Update

    Heavy lift vessel Stanislav Yudin has installed more than three quarters of the foundation piles on the 588MW Beatrice wind farm off Scotland, Beatrice Offshore Windfarm Ltd (BOWL), reports.

  • 3 April 2012

    GWYNT Y MÔR Offshore Wind Farm Limited has secured a major contract to begin the next stage of offshore construction off the North Wales coast. In a £multi-million deal with Seaway Heavy Lifting Limited of Cyprus, the heavy lift vessel, ‘Stanislav Yudin’ will operate in Liverpool Bay between April and December, 2012, to install major […]

  • 31 July 2018
    Vessels, Wind Farm Update

    Eight out of 32 monopile foundations have been installed on the Trianel Windpark Borkum II in the German North Sea, the project’s developers said.

  • 11 March 2013
    Business & Finance

    Seaway Heavy Lifting (SHL) has won a new contract with Gwynt y Môr Offshore Wind Farm Limited to begin the second half of foundation installation off the North Wales coast. SHL’s crane vessel ‘Stanislav Yudin’ will go to Liverpool Bay in May this year to install the last 80 of the 160 monopile foundations and […]

  • 30 October 2013
    Operations & Maintenance, Wind Farm Update

    Seaway Heavy Lifting’s vessel, Stanislav Yudin, has successfully completed a record run of foundation installation works at Gwynt y Mor Offshore Wind Farm. The vessel, operating over eight miles off the North Wales coast, installed 80 monopiles and 32 transition pieces in 77 days, ensuring all 160 wind turbine locations have a foundation in place.The […]

  • 4 October 2017
    Vessels, Wind Farm Update

    The installation of jacket foundations at the Beatrice offshore wind farm is now suspended as Seaway Heavy Lifting’s vessel Oleg Strashnov left the site on 2 October and Stanislav Yudin’s re-mobilisation for the work is awaited.

  • 4 December 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) has installed the 86th and final four-pile set at the Beatrice offshore wind farm site. SHL carried out the piling work with the heavy-lift vessel Stanislav Yudin, which will now re-mobilise for jacket foundation installation.

  • 26 September 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessels Stanislav Yudin and Oleg Strashnov are working full-steam at the Beatrice offshore wind farm site and have installed 78 pile sets and 24 jacket foundations so far, according to the project’s latest Notice to Mariners.

  • 9 October 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessel Stanislav Yudin has installed 80 out of 86 sets of foundation piles for the 588MW Beatrice offshore wind farm off Scotland.

  • 4 September 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessels Stanislav Yudin and Oleg Strashnov have installed 69 pile clusters and 12 jacket foundations in the Outer Moray Firth off Scotland for the 588 Beatrice offshore wind farm project.

  • 14 November 2016
    Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) has appointed GAC UK to provide shipping services support during the construction and installation of foundations, inter-array cables and offshore substations at the 588MW Beatrice offshore wind farm. SHL, the engineering, procurement, construction and installation (EPCI) contractor, will design, supply and install the piled foundations, jacket substructures and inter-array cables for the […]

  • 10 April 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s Stanislav Yudin has installed the second set of piles for jacket foundations at the 580MW Beatrice offshore wind farm in Outer Moray Firth, Beatrice Offshore Windfarm Ltd (BOWL) said.

  • 9 August 2013
    Wind Farm Update

    AWJ Marine issued a notice on construction progress at Gwynt y Môr on August 5, according to which there are only 8 monopiles left to install at the offshore wind project. The following is a summary on construction progress issued by AWJ: Wind Farm Construction Status Progress with construction is illustrated in a map here, and […]

  • 21 July 2017
    Wind Farm Update

    Half of the wind turbine foundation piles have been installed at the Beatrice offshore wind site, the developer informed via social media. The piling is being carried out by Seaway Heavy Lifting (SHL) with their heavy lift vessel Stanislav Yudin.

  • 3 April 2018
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has been deployed on the jacket installation at the Beatrice offshore wind farm as the heavy lift vessel Oleg Strashnov left the site to handle the substation installation at the Arkona offshore wind farm in the German part of the Baltic Sea.

  • 11 December 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Oleg Strashnov – which left the Beatrice site after installing the 24th jacket foundation in late September and returned to the job in November – has put the 25th jacket in place and thus officially resumed the works after more than two months of suspension. 

  • 19 December 2017
    Operations & Maintenance, Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Oleg Strashnov has installed one third of the jacket foundations at the 588MW Beatrice offshore wind farm located in the Outer Moray Firth off Scotland.

  • 9 March 2017
    Vessels, Wind Farm Update

    Monday 6 March saw the delivery of the purpose built 700 tonne Pile Installation Frame (PIF) to the Rhenus Logistics Facility in Rotterdam, ahead of deployment to the 588MW Beatrice offshore wind farm site in Outer Moray Firth, Scotland.

  • 12 June 2016
    Business & Finance, Grid Connection, Operations & Maintenance, R&D, Technology, Vessels, Wind Farm Update

    TenneT Presents ‘Hub and Spoke’ Offshore Wind Concept (VIDEO) TenneT has presented a ‘hub and spoke’ concept to set up a large European offshore electricity system that incorporates building of an island in the middle of the North Sea. Van Oord, Highland Group Team Up for Deutsche Bucht OWF Van Oord and Highland Group Holdings […]

  • 10 March 2013

    Germany: Crane Vessel Stanislav Yudin Transports Tripods to Trianel Wind Farm Borkum The beginning of the month of March has seen the crane vessel, Stanislav Yudin, launch the transportation of tripods from the offshore terminal in Bremerhaven BLG to the Trianel Wind Farm Borkum.   Main Reasons Why U.S. Still Doesn’t See Offshore Wind Turbines […]

  • 3 November 2013

    Stanislav Yudin Installs 80 Gwynt y Mor Foundations in Record Time (UK)  Seaway Heavy Lifting’s vessel, Stanislav Yudin, has successfully completed a record run of foundation installation works at Gwynt y Mor Offshore Wind Farm. UK: St. Jude Storm Could Halt London Array  The world’s largest offshore wind farm, the London Array could be affected […]

  • 4 April 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) installed the first cluster of foundation piles at the Beatrice offshore wind farm site on 2 April, according to the Beatrice Offshore Wind Limited’s (BOWL) social media pages.

  • 28 September 2017

    Dutch company Ridderflex delivered 4,150 dampening pads to Seaway Heavy Lifting (SHL) in March, with SHL now installing them in the jacket pile grippers as part of foundation installation works currently ongoing at the Beatrice offshore wind farm.

  • 21 February 2019
    Vessels

    Seaway Heavy Lifting has renamed its vessels Stanislav Yudin and Oleg Strashnov to Seaway Yudin and Seaway Strashnov. All renaming and rebranding activities for the vessels were completed last week, Seaway Heavy Lifting said. The vessels, together with Seaway Moxie and Seaway Aimery, have been fitted with appropriate logos and are now part of the Seaway […]