  • 29 September 2017

    The Mukran Port in Sassnitz on the island of Rügen has published a photo of the transition pieces for the 385MW Arkona offshore wind farm.

  • 8 September 2017
    Wind Farm Update

    DEME Group has loaded out the last two out of the 42 transition pieces built for the 309MW Rentel offshore wind farm at the Smulders fabrication yard in Hoboken, Belgium.

  • 17 August 2017
    Wind Farm Update

    The first set of transition pieces built by Bladt Industries for the 385MW Arkona offshore wind farm has arrived to the Mukran Port on Germany’s Rügen island.

  • 8 August 2017
    Wind Farm Update

    Bladt Industries carried out the final load-out of Walney 4 transition pieces in Aalborg on 31 July.

  • 21 June 2017
    Wind Farm Update

    Bladt Industries has completed the stacking of the upper 3D structure to the lower 3D structure on the first of 30 jacket foundations built for the 588MW Beatrice Offshore Windfarm Ltd (BOWL) project.

  • 4 May 2017
    Wind Farm Update

    Offshore Structures Britain (OSB) has shipped out the last six transition pieces built for DONG Energy’s Walney Extension offshore wind farm.

  • 11 April 2017
    Technology, Wind Farm Update

    Bilbao-based Navacel has loaded out five transition pieces built for Statoil’s 30MW Hywind Scotland Pilot Park, the world’s first floating offshore wind farm.

  • 7 February 2017
    Business & Finance, Wind Farm Update

    DONG Energy has hired Germany’s Steelwind Nordenham and Teesside-based Wilton Engineering Services Limited to supply the 1.2GW Hornsea Project One offshore wind farm with 20 transition pieces. The multi-million pound contract was signed in Port Clarence in Middlesbrough on Monday, 6 February. Wilton Engineering Services Limited will provide a significant part of the work scope including outfitting, […]

  • 5 January 2017
    Wind Farm Update

    DONG Energy has signed a contract with Bladt Industries for 96 transition pieces for its 1.2GW Hornsea Project ONE offshore wind farm. 56 transition pieces will be manufactured at the Offshore Structures Britain (OSB) facility in Haverton Hill near Billingham, Teesside. The remaining 40 transition pieces will be manufactured at the Bladt Aalborg facility in […]

  • 17 October 2016
    Wind Farm Update

    The final six transition pieces for the 402MW Veja Mate offshore wind farm were delivered to Offshore Windforce M V.O.F. from Bladt Industries’ production facilities in Aalborg at the end of the third quarter of 2016. The six transition pieces were the last of a total of 67 units which were all finished within 14 months from contract commencement, Bladt […]

  • 13 July 2016
    Ports & Logistics, Vessels, Wind Farm Update

    The last 10 foundation components for the Nobelwind project arrived onboard the vessel Drago J to the port of Ostend on 7 July. The REBO terminal at Energy Port Oostende has been in full operation for a few months now. As of March, foundation components have been arriving on the REBO site every 2 to 3 weeks for final assembly. […]

  • 5 August 2014
    Business & Finance

    On July 3, Smulders Projects was awarded the contract for the supply of 67 Transition Pieces for the Dudgeon Offshore Wind Farm.  The Dudgeon Offshore Windfarm will be constructed on the coast of Norfolk, South East England. The wind farm comprises 67 monopile foundations on which 6 MW turbines will be placed. This large capacity […]

  • 20 December 2013
    Business & Finance, Wind Farm Update

    Ballast Nedam Offshore (BNO) is executing the foundation EPCI works for wind farm operator OWP Butendiek.  As part of this, BNO has subcontracted Jumbo for the offshore transport and installation of 80 transition pieces (TPs). The TPs are fabricated in Esbjerg and will be installed with the Dynamically Positioned HLV Jumbo Javelin. During the summer […]

  • 25 June 2013

    Since 3 June 2013, AMBAU GmbH has been constructing 41 transition pieces to be used for the jackets at the “EnBW Baltic 2” wind farm on commission from Bladt Industries A/S. In April 2013, Bladt Industries announced that it had received an order to construct the 41 jackets to be installed in water depths of […]

  • 14 March 2013

    Sif Group has secured the EON Humber Gateway contract for the manufacturing of monopiles and transition pieces for the part consisting of 73 wind turbines. ”Sif will manufacture the primary steel for these foundations and Eiffage JV will manufacture the secondary steel,“ wrote sales manager Richard Jongen in an email. The Humber Gateway wind farm […]

  • 14 February 2013

    In spring of 2012, Jumbo’s DP2 heavy lift vessel Jumbo Javelin successfully installed the first Transition Pieces (TPs) for the Anholt Offshore Wind Farm. By the end of the summer, all TPs have been installed on 111 monopiles. Jumbo Javelin installed the TP’s with a record-breaking installation rate of 3 TP’s per day. The transport, […]

  • 29 October 2012

    EDF Energy Renewables has announced that the installation of transition pieces is completed at the Teesside offshore wind farm, writes Gazette Live. Namely, Dutch marine engineering contractor, Van Oord, has completed the installation of all 27 of the windfarm’s transition pieces. Within the next two weeks, jack-up vessel JB 114 will start the installation of […]

  • 7 June 2012
    Wind Farm Update

    The installation of monopiles and transition pieces is ongoing at full speed, and as of 1 June, 69 monopiles and 27 transition pieces are installed in the Anholt wind farm, and Jumbo Javalin has just arrived at the site with a new load of transition pieces. The installation of monopiles is expected to be completed […]

  • 3 May 2012

    On arrival at Aalborg, the vessel Jumbo Javelin started loading transition pieces at Bladt Industries on 13 April 2012, and already on 16 April the first transition piece was placed on the monopile in the wind farm. The transition piece is cast onto the monopile by means of special concrete. The transition secures that the […]

  • 27 April 2012

    Jumbo’s DP2 heavy lift vessel Jumbo Javelin has successfully installed the first Transition Pieces (TPs) for the Anholt Offshore Wind Farm in Denmark. The operation was performed as planned with respect to every detail: transport, installation, accessibility of the TP, grouting and safety. Once again Jumbo proved to have an efficient concept for the transport […]

  • 5 April 2012

    The vessel Jumbo Javelin, which will assemble the transition pieces, has just started mobilisation in Rotterdam and is expected to be calling at Aalborg Harbour in mid-April. At the same time, the water temperature is now above the 5 degrees Celsius required for the casting together of the monopile and the transition piece. In Aalborg, […]

  • 9 December 2011
    Technology

     MT Højgaard has awarded Enerpac the contract for the supply of cylinders for the Anholt Offshore Wind Farm (Denmark). The cylinders are used to level the 111 Transition Pieces in the Anholt Offshore Wind Farm. DONG Energy is developing the 400 megawatts wind farm. The Anholt Wind Farm is located in the ‘Kattegat’, near Anholt […]

  • 29 August 2011
    Wind Farm Update

      MT Højgaard has awarded Jumbo Offshore the transport and installation contract for all of the 111 Transition Pieces (TP’s) for the Anholt Offshore Wind Farm (Denmark). The 400 MW wind farm is currently being developed by DONG Energy. The Anholt Wind Farm is located in the ‘Kattegat’, near Anholt Island, and will be the […]

  • 22 August 2011
    R&D, Wind Farm Update

    The first transition piece for Walney 2 was placed on 16 April. Less than four months later, all 51 transition pieces have been installed. On the night of 5 to 6 August, the last TP was installed, and Goliath has now demobilised and left the site. 43 turbines installed in Walney 2 and 19 array […]

  • 10 September 2010
    Wind Farm Update

    DP2-vessel Jumbo Javelin completes installation project one month ahead of schedule transporting & installing 9 TP’s per trip. Jumbo Offshore has successfully completed its TP-installation project for the Greater Gabbard Offshore Wind Farm (GGOWF), off the UK’s south-east coast. For client Fluor, Jumbo’s DP2 Heavy Lift Vessel Jumbo Javelin installed 131 TP’s (out of 140 […]

  • 22 April 2010

    Jumbo Offshore’s crew, engineers and subcontractors have successfully completed the first leg of their current Transition Piece (TP)… [mappress] Source: pennenergy, April 21, 2010;