30 April 2019 Wind Farm Update

Swire Blue Ocean's jack-up Pacific Orca installed 77 out of 84 Siemens Gamesa 7MW wind turbines on the Beatrice wind farm offshore Scotland as of 29 April, with seven more turbines left to be installed. 73 of the turbines installed in the Outer Moray Firth were commissioned, Beatrice Offshore Windfarm Limited (BOWL), owner and developer of […]

5 April 2019 Wind Farm Update

Jack-up vessel Pacific Orca is installing the 70th Siemens Gamesa 7MW wind turbine on the 588MW Beatrice wind farm in the Outer Moray Firth, Scotland, Beatrice Offshore Windfarm Limited (BOWL) said. In total, Beatrice will comprise 84 wind turbines once fully built. The wind turbines are being commissioned shortly after the installation. Swire Blue Ocean’s […]

4 February 2019 Wind Farm Update

Swire Blue Ocean’s jack-up vessel Pacific Orca has installed two-thirds of a total of 84 turbines at the Beatrice offshore wind farm. The vessel installed 56 of the 7MW Siemens Gamesa turbines last week and has 28 to go, according to Beatrice Offshore Windfarm Limited (BOWL). ***MILESTONE*** We’re ending the week with two thirds of […]

24 December 2018 Vessels, Wind Farm Update

42 out of the 84 Siemens Gamesa 7MW wind turbines have been installed on the 588MW Beatrice wind farm offshore Scotland, Swire Blue Ocean said.

18 December 2018 Wind Farm Update

Forty wind turbines have been installed at the Beatrice offshore wind farm and the project is now two turbines away from reaching a halfway mark. 

14 November 2018 Wind Farm Update

33 of 84 Siemens Gamesa 7MW turbines have now been installed on the Beatrice offshore wind farm and are exporting power to the Scottish grid, SSE plc said.

18 October 2018 Wind Farm Update

A third of wind turbines has now been installed on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland, Beatrice Offshore Windfarm Limited (BOWL) said.

28 September 2018 Wind Farm Update

Innogy SE officially inaugurated the Galloper offshore wind farm in the UK today, 28 September.

21 August 2018 Wind Farm Update

Siem Offshore Contractors has completed the inter-array cable installation at the Beatrice offshore wind farm site, according to Beatrice Offshore Windfarm Limited's (BOWL) social media post from 21 August. 

16 August 2018 Ports & Logistics, Vessels, Wind Farm Update

Nine Siemens Gamesa 7MW wind turbines have so far been installed on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland, Beatrice Offshore Windfarm Limited (BOWL) said.

11 July 2018 Ports & Logistics, Wind Farm Update

Seaway Heavy Lifting's vessel Oleg Strashnov has installed the 86th and final jacket foundation on the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

10 July 2018 Vessels, Wind Farm Update

The walk-to-work vessel Stril Server, together with the crew transfer vessel Marieco Mariah, is currently working on cable commissioning works on wind turbine foundations at the Beatrice project site, in preparation for the installation of wind turbines.

28 May 2018 Wind Farm Update

The eleventh and final MHI Vestas turbine was erected on 26 May at the European Offshore Wind Deployment Centre (EOWDC), where the inter-array cable installation works are also coming to an end, thus moving the project to the final commissioning phase before it generates its first power later this summer. 

16 May 2018 Vessels, Wind Farm Update

Vattenfall is currently installing eleven MHI Vestas wind turbines on the European Offshore Wind Deployment Centre (EOWDC) in the Aberdeen Bay, including the two of the most powerful wind turbines in the world.

24 April 2018 Ports & Logistics, Vessels, Wind Farm Update

Wind turbine number three and foundation number five are being installed on the European Offshore Wind Deployment Centre (EOWDC) in the Aberdeen Bay, with the northern cable installation also ongoing, Vattenfall, the owner and developer of the wind farm said.

10 April 2018 Technology, Wind Farm Update

A hat-trick of offshore wind industry firsts has been achieved within a fortnight in North-East Scotland after the world’s most powerful single turbine was installed on Monday, 09 April, for Vattenfall’s European Offshore Wind Deployment Centre (EOWDC).

13 February 2018 Business & Finance

Swire Blue Ocean has appointed Mikkel Gleerup as Chief Executive Officer (CEO).

22 December 2017 Vessels, Wind Farm Update

The 56th and final Siemens Gamesa 6MW wind turbine was installed at the Galloper offshore wind farm today. The 353MW offshore wind farm is expected to be commissioned in Spring 2018.

20 November 2017 Business & Finance, Jobs & Recruitment

Lars Blicher, CEO and Director at Swire Blue Ocean, resigned from the position on 16 November.

17 October 2017 Vessels

Seazip Offshore Service has posted a photo taken from its service vessel Seazip 3, showing commissioning works at the 336MW Galloper offshore wind farm off the coast of Suffolk.

1 October 2017 Contracts & Tenders

DEME Tries to Take Possession of Unfinished Living Stone from LaNaval Shipyard Belgium’s DEME Group has attempted to take possession of the advanced cable lay vessel Living Stone, currently under construction at the financially troubled LaNaval shipyard in Bilbao, Spain, and tow the vessel to another location where the delayed construction could be completed. Wiking […]

4 September 2017 Vessels, Wind Farm Update

Fred. Olsen Windcarrier has been awarded a contract with Siemens Gamesa Renewable Energy (SGRE) for the transport and installation of wind turbines on the 336MW Galloper offshore wind farm off Suffolk, UK.

15 August 2017 Vessels, Wind Farm Update

DOF Subsea, a subsidiary of DOF ASA, has won the contract for Skandi Constructor for Siemens on the Galloper offshore wind farm project in the North Sea.

28 June 2017

VBMS has published a photo of its cable laying vessels Stemat Spirit and Ndurance working at the Galloper offshore wind farm, while Seajacks Hydra is accommodating the personnel at the wind farm site.

1 June 2017 Grid Connection, Operations & Maintenance, Vessels, Wind Farm Update

Rhenus Offshore Logistics has started working on its first project out of its new offshore base at the port of Great Yarmouth, carrying out supply runs during the commissioning of the offshore substation at the 336MW Galloper offshore wind farm.

23 May 2017

Innogy UK yesterday posted the first photo of the first wind turbine installed last week at the Galloper offshore wind farm.