Search results for: Northland Deutsche Bucht

47 results

A list of search results

21 August 2017 Business & Finance, Wind Farm Update

MHI Vestas Offshore Wind received a firm and unconditional order for the Deutsche Bucht (DeBu) wind farm from Northland Power Inc. last Friday, when the Canadian company announced that the EUR 1.3 billion offshore wind project had reached financial close.

6 March 2017 Business & Finance, Wind Farm Update

Canadian energy company Northland Power has signed a definitive agreement to acquire 100% of Deutsche Bucht, a 252MW wind project in the German North Sea. The agreement was signed between Northland Power and a wholly-owned subsidiary of Highland Group Holdings. Deutsche Bucht, or DeBu, is Northland's third offshore wind project following the 600MW Gemini wind farm in the […]

6 June 2019 Wind Farm Update

Van Oord, MHI Vestas, and partners have installed the first V164-8.4MW wind turbine on the 269MW Deutsche Bucht wind farm in the German North Sea. The wind turbines are being transported from the Port of Esbjerg and installed at the site some 95km northwest of the Borkum Island by Van Oord's jack-up Aeolus. “We are very […]

28 May 2019 Wind Farm Update

Van Oord has completed the laying of inter-array cables at the 269MW Deutsche Bucht offshore wind farm in the German North Sea ahead of schedule, Northland Power, the owner and developer of the project, said. The cables were laid by Van Oord's cable laying vessel Nexus. The cable burial at the site some 95 kilometres northwest of […]

21 May 2019 Ports & Logistics

Van Oord has appointed the Esbjerg-based Niels Winther Maritime to serve as an agent for the wind farm installation vessel Aeolus over the summer. Aeolus will be working out of the Port of Esbjerg over the summer, loading turbine components for the Deutsche Bucht offshore wind project and then transporting and installing them in the German […]

20 May 2019 Wind Farm Update

The Northland Power team is gearing up for the beginning of the turbine installation campaign at the Deutsche Bucht offshore wind farm. According to the company, the team is working to quickly assemble the towers for the MHI Vestas 8.4MW turbines, with the loadout expected to start shortly at the Port of Esbjerg. Global Wind […]

30 April 2019 Grid Connection, Wind Farm Update

Van Oord and Norddeutsche Seekabelwerke (NSW) have begun the inter-array cable work for the Deutsche Bucht offshore wind farm in Germany. According to project developer Northland Power, NSW is loading out the cables at its facility in Nordenham, Germany, with cable laying, the next construction phase, also currently in motion by Van Oord's vessel Nexus. In […]

4 April 2019 Grid Connection, Wind Farm Update

Heavy lift vessel Seaway Strashnov has installed the jacket foundation and the substation topside on the 269MW Deutsche Bucht offshore wind farm in the German North Sea. “With the installation of the offshore substation completed, we have once more accomplished another milestone on schedule,” said Jens Poulsen, Project Director at Northland Deutsche Bucht GmbH. “In […]

27 March 2019 Grid Connection, Wind Farm Update

The jacket foundation for the Deutsche Bucht offshore substation has arrived at the installation site in the German North Sea and will be installed as soon as there is a suitable weather window, a spokesperson for Northland Deutsche Bucht GmbH told Offshore WIND. The substation topside has been towed from Vlissingen to Eemshaven in the Netherlands, as the […]

18 March 2019 Contracts & Tenders, Operations & Maintenance

DHSS has won a contract by Van Oord for call-off helicopter services for the Deutsche Bucht offshore wind farm in Germany. Helicopter flights will take off from Den Helder Airport in the Netherlands, while the Eemshaven heliport is also an option if required since DHSS has a vessel and helicopter support base in the vicinity. […]

13 March 2019 Grid Connection, Ports & Logistics, Wind Farm Update

The topside for the offshore substation of the Northland Power’s Deutsche Bucht offshore wind farm has been loaded on the pontoon at the Damen Shiprepair yard in Vlissingen, the Netherlands. The topside was loaded out on Sunday 24 February, Smulders said. The accompanying jacket was loaded on the pontoon earlier that week. The topside will […]

22 February 2019 Business & Finance

Northland Power has reported CAD 1.4 billion in gross profit in 2018, a 17% increase, said to be primarily due to all turbines of the Nordsee One offshore wind farm producing power and higher wholesale market prices at the Gemini project. The two wind farms, as well as thermal projects Thorold and North Battleford, brought Northland […]

21 February 2019 Wind Farm Update

Smulders has loaded out the jacket foundation for the Northland Power’s Deutsche Bucht offshore substation in Vlissingen, the Netherlands. The jacket, weighing more than 1,700 tons, will be transported to the German North Sea at the beginning of March, weather permitting, Smulders said. The substation topside, which was assembled at the Damen Shiprepair Vlissingen yard, […]

9 January 2019 Grid Connection, Operations & Maintenance

The Denmark-headquartered PcP. has provided louvre gratings for the offshore substation of the Deutsche Bucht offshore wind farm in Germany. According to PcP., the seawater resistant gratings will provide protection and ventilation for vulnerable transformer chambers of the substation. The protection was necessary due to extreme conditions, such as high winds and often heavy rains, the […]

8 January 2019 Ports & Logistics, Vessels, Wind Farm Update

Northland Deutsche Bucht GmbH has completed the installation of all 31 monopile foundations on the 269MW Deutsche Bucht wind farm in the German North Sea. The milestone concludes the first phase of construction within the planned timeframe, the developer said. “Installation work on the construction site, which is more than 100 kilometers off the coast, […]

7 November 2018 Wind Farm Update

The 269MW Deutsche Bucht offshore wind project in the German North Sea is progressing on time and on budget, with 13 out of 33 foundations installed to date, Mike Crawley, President and CEO of Northland Power, said.

29 October 2018 Contracts & Tenders, Wind Farm Update

Van Oord has contracted Universal Foundation to support the installation of two mono bucket foundations at the Deutsche Bucht offshore wind farm. 

26 October 2018 Grid Connection, Ports & Logistics, Wind Farm Update

Smulders, acting for and on behalf of the JV Iemants-Eiffage, has rolled out the substation topside for the Deutsche Bucht offshore wind farm at the yard of Damen Shiprepair Vlissingen. The milestone was achieved 10 months after starting the final assembly in January 2018. The topside was driven outside for further outfitting on 21 October. Offshore […]

15 October 2018 Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

Northland Deutsche Bucht has awarded Danish-based Semco Maritime with a 5-year service contract for the Deutsche Bucht offshore wind farm in the German part of the North Sea.

25 September 2018 Operations & Maintenance, Wind Farm Update

Canadian power company Northland Power Inc. has opened an offshore wind operations hub in Germany.

4 September 2018 Ports & Logistics, Vessels, Wind Farm Update

The first of the 31 monopile foundations has been installed on Northland Power's 269MW Deutsche Bucht offshore wind farm in the German North Sea.

3 September 2018 Ports & Logistics, Vessels, Wind Farm Update

The jack-up vessel Seajacks Scylla has left Cuxhaven loaded with the first three monopiles and transition pieces to be installed on the 269MW Deutsche Bucht wind farm in the German North Sea.

28 August 2018 Ports & Logistics, Vessels

Van Oord is using the new berth at the Cuxport Terminal in Cuxhaven for the Deutsche Bucht offshore wind project, Cuxport informed, saying that the berth no. 4 has thus become the location for its first offshore project even before its official launch. 

17 August 2018 Ports & Logistics, Wind Farm Update

German offshore foundations manufacturer EEW Special Pipe Constructions GmbH has loaded out the first monopiles built for the 269MW Deutsche Bucht offshore wind farm.

9 August 2018 Business & Finance

Northland Power reported CAD 192.6 million in offshore wind sales in the second quarter of 2018, a CAD 31.9 million increase compared to the same period last year, mostly due to all turbines at the 332MW Nordsee One project producing power.

19 July 2018 Business & Finance, Operations & Maintenance, Technology, Wind Farm Update

The Deutsche Bucht Mono Bucket pilot demonstrator project has reached financial close, Northland Deutsche Bucht GmbH said.