30 November 2012 Authorities

Germany’s Federal Minister of Economic Affairs and Technology, Dr. Philipp Rösler, visited the submarine cable manufacturer Norddeutsche Seekabelwerke GmbH (NSW) in Nordenham. During the minister’s guided tour of the company’s facilities and factory, NSW’s Managing Director Rudolf Stahl showed him the production plant for submarine power cables, inaugurated in 2009. This state-of the-art factory, featuring […]

18 October 2012

Norddeutsche Seekabelwerke GmbH (NSW), a wholly-owned subsidiary of General Cable, has received a newly refurbished DP2 cable laying vessel under a long term charter agreement from the vessel management company Meriaura. The vessel M/V Aura has been refurbished to the exact specifications of NSW and will greatly enhance its ability to install subsea energy cable. […]

30 July 2012 Operations & Maintenance

Wind turbine installation projects will face greater competition from oil and gas projects for chartering specialist vessels. Offshore wind farm developers in Europe and their contractors for engineering procurement, construction and installation are likely to struggle to secure specialist tonnage in the mid and long terms despite some current easing in the market due to […]

5 July 2012

At its harbour location Nordenham, Rhenus Midgard delivered, stored and handled about 30 km ofsubmarine cables on behalf of Nexans in May. The submarine cables of the world's leading manufacturer in the cable industry will connect a part of the 111 wind turbines of Denmark's largest offshore wind farm Anholt. With this project Rhenus Midgard […]

22 June 2012

The Blue Offshore management team announced that it has succesfully finalised the construction phase of the company’s first self-owned cable carousel system, Turntable I. Turntable I has positively passed Factury Acceptance Testing (FAT) to ensure it meets the design and performs as required. Turntable I was designed by the Blue Offshore in-house engineering department in […]

1 March 2012

Norddeutsche Seekabelwerke GmbH (NSW) has agreed to long-term charter the DP2 vessel MV Aura from the Finnish Meriaura Ltd for use in subsea cable installation projects in the North and Baltic Sea. Under the terms of the agreement NSW will charter the vessel starting in summer 2012. Constructed in 2008, the vessel will be converted […]

29 February 2012

Vos Prodect Innovations B.V. announced today that it has been contracted by Norddeutsche Seekabelwerke GmbH (NSW) for the supply of Cable Hang-off Systems for an offshore wind farm project in the North Sea. This is the second supply contract the company has secured upon launching the best system to meet NSW’s technical and commercial requirements […]

24 February 2012 Grid Connection

One of the key elements in the successful construction of an offshore wind park is the skilful installation of cables – a complicated task that is often subject to huge repair costs. Cable damage causes over 70% of all insurance claims on installed wind parks, which shows that there is great need for improving the […]

30 November 2011 Grid Connection

The planned construction of offshore wind power parks in the North Sea and Baltic Sea can only prosper if specialist port services providers, suppliers and manufacturers work together closely and if the public sector provides the necessary financial support. That was the conclusion reached at the Rhenus Midgard press conference at the "2011 EWEA OFFSHORE" […]

17 November 2011 Grid Connection

For the connection of the offshore wind farm Borkum Riffgrund 1 with the offshore converter platform DolWin alpha via two parallel 155 kV AC submarine cable systems, Norddeutsche Seekabelwerke GmbH (NSW) has been awarded on November 8, 2011 by TenneT TSO GmbH (TenneT) the order for the supply and installation of 26 kilometers 155 kV […]

10 November 2011 Grid Connection

Vos Prodect Innovations B.V. has been awarded an order by Norddeutsche Seekabelwerke GmbH (NSW), for the supply of Cable Hang-off Systems for an offshore wind farm project in the North Sea. Vos Prodect has carried an intensive development program to launch the best system to meet the technical & commercial requirements of NSW for the […]

12 July 2011 Operations & Maintenance, Wind Farm Update

  On July 8, 2011 WindMW GmbH and Norddeutsche Seekabelwerke GmbH (NSW) signed a contract for the delivery and installation of 108 km medium-voltage submarine cables for the inter-array cabling of the wind farm project Meerwind. With the installation scheduled to start in the second half of 2012, completion is planned in 2013. The project […]

7 June 2011 Grid Connection

On 17 May 2011, Global Tech I Offshore Wind GmbH (Global Tech) signed an order with a consortium of Norddeutsche Seekabelwerke GmbH (NSW) and Global Marine Systems Ltd. (GMSL) to deliver and install over 100 km of medium-voltage submarine array cables for the Global Tech I offshore wind farm. The installation work will start in […]

27 April 2011

  Blue Offshore announced today the appointment of Stijn Folkers to the role of Commercial Director. Folkers will be responsible for the management of Blue Offshore’s Commercial Departments. Folkers has a strong background in the offshore industry. He served most recently as Manager of Contracts at Seaway Heavy Lifting, where he was responsible for negotiating […]

21 March 2011

Blue Offshore has been awarded a lease agreement for a subsea cable installation system by Norddeutsche Seekabelwerke GmbH (NSW). The system includes the uniquely adaptable modular turntable system, loading arm assembly, tensioners, trackways and associated equipment, to assist with the installation of submarine transmission cables. The order value has not been disclosed, with mobilization beginning […]

4 February 2011 Grid Connection

On 20 December 2010, Trianel Windkraftwerk Borkum GmbH & Co KG (“TWB”) activated an order with Norddeutsche Seekabelwerke GmbH (“NSW”) to deliver and install 65 km of medium-voltage submarine cables for the first construction phase of the Trianel Borkum West II offshore wind farm. The order is worth an amount in excess of € 22 […]

9 December 2010 Grid Connection, Technology

Continuing rising demand for sustainable wind-based energy plants in the North Sea has led Nostag Gmbh to contract Berg Propulsion to upgrade its cable layer, Nostag 10, by equipping the vessel with two azimuthing thrusters. Nostag, a consortium comprised of German companies Ludwig Freytag, Norddeutsche Seekabelwerke GmbH and Tiefbau GmbH Unterweser, has been operating the […]

14 October 2010 Grid Connection

General Cable Corporation (NYSE: BGC) (the Company), a global leader in the wire and cable industry, through its wholly-owned subsidiary Norddeutsche Seekabelwerke GmbH (NSW), has been awarded a major order by 50Hertz Offshore GmbH, a subsidiary of the German-based transmission network operator 50Hertz Transmission GmbH, to provide a complete turn-key solution including the supply and […]