Search results for: Jacket Installation

11293 results

A list of search results

  • 20 June 2018
    Wind Farm Update

    Seaway Heavy Lifting (SHL), using its vessel Oleg Strashnov, installed the 77th jacket foundation at the Beatrice site on 20 June, according to some media posts from those involved in the project, following the project’s Notice to Mariners from 18 June that reported 76 jackets being in place.

  • 14 November 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Oleg Strashnov will return to the Beatrice site on 16 November and will continue installing jacket foundations until mid-December, when it will leave the site once again and SHL’s vessel Stanislav Yudin will take over. 

  • 3 April 2018
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has been deployed on the jacket installation at the Beatrice offshore wind farm as the heavy lift vessel Oleg Strashnov left the site to handle the substation installation at the Arkona offshore wind farm in the German part of the Baltic Sea.

  • 9 May 2012

    Installation of the first offshore components at Gwynt y Môr, one of the largest offshore wind farms in Europe, has begun off the north Wales coast yesterday. Work to install two steel jacket foundation structures was started earlier yesterday the Seaway Heavy Lifting crane vessel ‘Stanislav Yudin’, and is continuing approximately 10 miles off the […]

  • 26 September 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessels Stanislav Yudin and Oleg Strashnov are working full-steam at the Beatrice offshore wind farm site and have installed 78 pile sets and 24 jacket foundations so far, according to the project’s latest Notice to Mariners.

  • 13 June 2018
    Operations & Maintenance

    The Netherlands-based Temporary Works Design (TWD) has provided Van Oord with a jacket lifting tool for the installation of the foundations at the East Anglia One offshore wind farm.

  • 5 May 2020
    Business & Finance, Vessels

    DEME is currently looking for a replacement vessel for the installation of Moray East jacket foundations, following the crane accident onboard the installation vessel Orion. The company is considering both the vessels in its own fleet and externally to carry out the installation of Moray East jackets, first eight of which have now arrived at […]

  • 4 October 2016

    Eco-Fish Consultants have reported that they delivered Marine Mammal Observer (MMOs) and Passive Acoustic Monitoring (PAM) services during the installation of a substation jacket at the Rampion offshore wind farm. The main objective was to ensure that the installation was carried out with minimal disturbance to marine mammals, which could potentially be caused by underwater sound […]

  • 4 October 2017
    Vessels, Wind Farm Update

    The installation of jacket foundations at the Beatrice offshore wind farm is now suspended as Seaway Heavy Lifting’s vessel Oleg Strashnov left the site on 2 October and Stanislav Yudin’s re-mobilisation for the work is awaited.

  • 19 September 2017
    Technology

    Trelleborg’s engineered products operation has added to its portfolio of offshore floatover solutions with a custom designed skirt pile gripper (SPG).

  • 23 May 2017

    ACE Winches has mobilised and installed a winch package for use on the jacket installation and float-over of the topside of the DolWin gamma platform, the centrepiece of the 900MW DolWin3 grid connection.

  • 14 August 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessel Oleg Strashnow has installed the first of 86 jacket foundations on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

  • 28 March 2014
    Technology

    Preparations for the loading of Siemens’ HelWin beta jacket are in full swing at Heerema Fabrication Group’s Vlissingen yard, the company informed via social media. The 3,500-ton jacket will be moved on site to the quayside for the loading on a barge. In June 2012, Siemens awarded Heerema Fabrication Group (HFG) a contract that comprises […]

  • 12 January 2018
    Grid Connection, Vessels, Wind Farm Update

    The 2,660t topside for the Merkur offshore substation was lifted yesterday, 11 January, from a transport barge to the Oleg Strashnov heavy lift vessel, which is expected to install it on its foundation today. 

  • 11 December 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s (SHL) vessel Oleg Strashnov – which left the Beatrice site after installing the 24th jacket foundation in late September and returned to the job in November – has put the 25th jacket in place and thus officially resumed the works after more than two months of suspension. 

  • 2 February 2018
    Operations & Maintenance, R&D, Wind Farm Update

    Harland and Wolff has manufactured and exported 24 suction buckets for the Borkum Riffgrund 2 offshore wind farm to ST3 Offshore’s serial manufacturing plant in Stettin, Poland.

  • 4 September 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessels Stanislav Yudin and Oleg Strashnov have installed 69 pile clusters and 12 jacket foundations in the Outer Moray Firth off Scotland for the 588 Beatrice offshore wind farm project.

  • 10 September 2019
    Wind Farm Update

    DEME Group’s jack-up vessel Apollo has installed 156 out of 309 pin piles at the Moray East offshore wind project in the UK, marking the halfway milestone. According to DEME, a pile installation template is being used, where three pin piles are stabbed into the seabed through the piling temple and then driven to target depth […]

  • 28 September 2017

    Dutch company Ridderflex delivered 4,150 dampening pads to Seaway Heavy Lifting (SHL) in March, with SHL now installing them in the jacket pile grippers as part of foundation installation works currently ongoing at the Beatrice offshore wind farm.

  • 27 May 2019
    Wind Farm Update

    The 950MW Moray East wind farm has entered the offshore construction phase with the start of piling operations earlier this month. The piling operations started on 19 May and are expected to take place over a period of approximately eleven months, a Notice of Operations said. Moray East contracted GeoSea NV Geotechnical & Offshore Solutions, […]

  • 23 September 2013
    Wind Farm Update

    Alstom has hired “Bold Tern” jack-up installation vessel, owned by Fred. Olsen Windcarrier, to complete the offshore operations at the Belwind offshore wind farm. Recently, the company announced that they have faced a delay during the installation of Alstom’s 6MW Haliade 150 offshore wind turbine, for which they found a solution in the form of […]

  • 9 April 2018
    Grid Connection, Vessels, Wind Farm Update

    The jack-up vessel Seajacks Hydra will arrive on the Beatrice site this week and connect to OTM 1, the first of the two Siemens Offshore Transformer Modules that the wind farm will feature, to provide accommodation facilities during its commissioning.

  • 28 February 2017

    IHC IQIP will provide jacket pile grippers, the Hydrohammer S-2500 with two specially designed hammer sleeves, and an internal lifting tool to Seaway Heavy Lifting (SHL), the EPCI contractor in charge of foundations for the Beatrice project.

  • 30 August 2013
    Technology, Wind Farm Update

    Installation of Alstom’s 6MW Haliade 150 offshore wind turbine at the Belwind offshore wind farm has been delayed because of some unexpected problems that occurred during the civil works, the company told Offshore WIND. The wind turbine was scheduled to be completely installed in July, however, pile dredging and grouting of the jacket installation have […]

  • 29 January 2018
    Business & Finance, Environment, Grid Connection, Operations & Maintenance, R&D, Wind Farm Update

    The 588MW Beatrice offshore wind farm is expected to produce first electricity in July this year, SSE, one of the owners of the wind farm, said.

  • 14 November 2017
    Business & Finance

    Production problems and cost overruns related to the Beatrice jacket foundations order are at the root of financial issues that the Scottish company BiFab is currently facing, resulting in its staff coming to work as usual despite the company having no money to pay their wages, just so the Beatrice order placed by Seaway Heavy Lifting (SHL) could be kept at BiFab.