3 December 2018 Wind Farm Update

All 32 turbine foundations for the 200MW Trianel Windpark Borkum II offshore wind farm have been installed at the construction site some 45 kilometers north of the island of Borkum in the German North Sea. “We are right on schedule with the construction of the offshore wind farm. We were able to compensate for the […]

3 December 2018 Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

SeaMade NV has awarded the consortium of ENGIE Fabricom, Tractebel, Smulders and GeoSea an Engineering, Procurement, Construction and Installation (EPCI) contract for the two substations of the SeaMade offshore wind farm in Belgium.

27 November 2018 Contracts & Tenders, Ports & Logistics, Vessels

Shipping logistics specialist SeaMar Services has started a vessel agency contract with Seaway Offshore Cables, a company in Subsea 7’s Renewables & Heavy Lifting Business Unit.

27 November 2018 Business & Finance, Wind Farm Update

Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

21 November 2018 Business & Finance, Grid Connection, Technology

The latest technology developments could help reduce the risks in offshore wind cable laying operations, according to LOC Renewables.

19 November 2018 Contracts & Tenders, Grid Connection, Wind Farm Update

French cable maker Nexans has won a contract to provide a subsea export cable system for the nearshore section of Ørsted's 1.4GW Hornsea Project Two offshore wind farm in the UK. The contract is worth over EUR 150 million and will see Nexans supplying 200 kilometres of the 245 kV high voltage alternating current (HVAC) subsea export […]

14 November 2018 Business & Finance, Wind Farm Update

German wind turbine manufacturer Senvion has started the production of the turbines for the 200MW Trianel Windpark Borkum II offshore wind farm.

13 November 2018 Contracts & Tenders, Grid Connection

Seaway Offshore Cables (SOC) has won a substantial contract for the supply and installation of the export and inter-array grid cable systems at the Yunlin offshore wind farm in Taiwan.

9 November 2018 Wind Farm Update

27 out of the 32 monopile foundations have been installed on the 200MW Trianel Windpark Borkum II (TWB II) offshore wind farm in the German North Sea.

8 November 2018 Contracts & Tenders, Wind Farm Update

Manor Renewable Energy (MRE) has signed a contract with Ørsted for the Hornsea Project One offshore wind farm, under which MRE will provide the full temporary power package of generators, personnel and vessels in case of need during the turbine installation and commissioning.

7 November 2018 Business & Finance, Contracts & Tenders, Grid Connection

Nexans will provide up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW Borssele 1 and 2 offshore wind project in the Netherlands as part of the recently-announced contract.

7 November 2018 Wind Farm Update

The 269MW Deutsche Bucht offshore wind project in the German North Sea is progressing on time and on budget, with 13 out of 33 foundations installed to date, Mike Crawley, President and CEO of Northland Power, said.

1 November 2018 Wind Farm Update

104 out of 174 turbine monopile foundations and 66 out of 174 inter-array cables have been installed on the 1,218MW Hornsea Project One wind farm, Ørsted said.

25 October 2018 Business & Finance, Contracts & Tenders, Grid Connection, Operations & Maintenance, Ports & Logistics, Wind Farm Update

Ørsted has added Bladt Industries, Nexans and Cordeel to the list of suppliers and contractors for the 752MW Borssele 1 and 2 wind farm in the Dutch North Sea, according to Henrik Egholm, EPC director Borssele 1 and 2.

22 October 2018 Contracts & Tenders, Wind Farm Update

Windplus has awarded Bourbon Subsea Services with a turnkey contract for the installation of the 25MW WindFloat Atlantic floating wind farm offshore Portugal.

18 October 2018 Contracts & Tenders, Grid Connection, Wind Farm Update

Lancashire-based VolkerInfra has signed a multi-million-pound contract with Ørsted to install 360 kilometres of high voltage onshore cables for the 1.4GW Hornsea 2 offshore wind farm.

16 October 2018 Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

Van Oord has won a contract to install inter-array cables on Ørsted's Borssele 1 + 2 offshore wind farm in the Dutch North Sea.

12 October 2018 Grid Connection, Jobs & Recruitment, Wind Farm Update

EDS HV Group has completed its scope of work at Vattenfall's European Offshore Wind Deployment Centre (EOWDC), also known as the Aberdeen offshore wind farm.

8 October 2018 Contracts & Tenders, Grid Connection, Wind Farm Update

Belgian offshore wind developer Northwester 2 has selected the French cable specialist Nexans to provide an export cable system for the 219MW Northwester 2 offshore wind farm.

8 October 2018 Business & Finance, Contracts & Tenders, Wind Farm Update

Northwester 2 has reached the official close of financial agreements with all key stakeholders and banks for the construction of the 219MW Northwester 2 offshore wind farm in the Belgian North Sea.

25 September 2018 Operations & Maintenance

JDR Cable Systems has completed the loadout of 55km of cable for the EnBW Hohe See offshore wind farm in the German North Sea.

24 September 2018 Grid Connection, Wind Farm Update

Subsea power cable specialist Prysmian Group has announced a successful commissioning of the inter-array cable system for Iberdrola's Wikinger offshore wind farm in the German Baltic Sea.

12 September 2018 Business & Finance, Contracts & Tenders

Ørsted has awarded its Taiwanese partner Woen Jinn Harbour Engineering (WJ) with a contract for the inter-array cable installation at the Greater Changhua offshore wind projects.

4 September 2018 Contracts & Tenders

A consortium of Louis Dreyfus TravOcean and Prysmian has officially secured a contract for the supply and installation of inter-array cables at the Saint-Nazaire offshore wind farm in France.

3 September 2018 Ports & Logistics, Vessels, Wind Farm Update

The jack-up vessel Seajacks Scylla has left Cuxhaven loaded with the first three monopiles and transition pieces to be installed on the 269MW Deutsche Bucht wind farm in the German North Sea.

29 August 2018 Contracts & Tenders, Wind Farm Update

Prysmian Group has secured inter-array cable contracts worth over EUR 220 million for three offshore wind farms in France.