    Italy-based subsea cable maker Prysmian has completed the laying phase of the inter-array cables for Iberdrola’s 350MW Wikinger offshore wind farm ahead of schedule.

  • 28 June 2017

    VBMS has published a photo of its cable laying vessels Stemat Spirit and Ndurance working at the Galloper offshore wind farm, while Seajacks Hydra is accommodating the personnel at the wind farm site.

  • 4 February 2013
    Technology

    Soil Machine Dynamics Ltd (SMD) announced the early delivery of an HD3 inter array cable plough to Reef Subsea Power & Umbilical Ltd. (RSPU). RSPU has named the vehicle HDIA (Heavy Duty Inter Array) Plough and is to be mobilised onto the Polar Prince subsea construction vessel. The HD3 cable plough, which is scheduled to […]

  • 28 May 2020
    Contracts & Tenders, Wind Farm Update

    Ailes Marines has awarded Prysmian Group with a contract to provide the inter-array cable systems for the Saint-Brieuc offshore wind farm in France. Prysmian will design, supply, install, and commission 90 kilometres of three core 66 kV HVAC XLPE-insulated inter-array cables. The value of the contract is around EUR 80 million. Cable cores will be […]

  • 20 May 2020
    Contracts & Tenders

    LOC Group has secured a contract with Ørsted to provide marine warranty survey services (MWS) for the Greater Changhua 1 & 2a offshore wind farms in Taiwan. Under the agreement, LOC will provide MWS services for the transportation and installation of the inter-array and export cables. Technical document review and operational approvals will be undertaken […]

  • 13 February 2019
    Business & Finance, Contracts & Tenders

    Royal Boskalis Westminster N.V. has signed a contract for inter-array cable work at an undisclosed offshore wind farm. Under the EUR 80 million contract, the Dutch company is in charge of replacing and repairing a part of the inter-array cables at the project. Boskalis will use three anchored barge spreads, including the cable repair assets Bokabarge 82 and recently acquired […]

  • 1 February 2013

    Sandbank Offshore Wind GmbH has invited tender for offshore wind farm works. The whole project consists of 96 wind turbine generators, foundations, inter-array cables and an offshore substation. The wind farm is located in the German Bight offshore area, 90kms west of the island of Sylt, in the German Exclusive Economic Zone (EEZ) with water […]

  • 26 February 2016
    Wind Farm Update

    CT Offshore today installed the last inter-array cable on DONG Energy’s Gode Wind 1+2 Offshore Wind Farm in the German part of the North Sea. “Gode Wind is the largest project to date for CT Offshore and it is a great achievement that our project team and offshore crew have now completed the installation of […]

  • 9 November 2017
    Wind Farm Update

    Dutch company Ridderflex has produced and delivered about 180 customised polyurethane hang-offs and plugs to GeoSea, the company now using these tools to connect the inter-array cables to the wind turbines at Belgian Rentel offshore wind farm.

  • 9 October 2017
    Wind Farm Update

    DeepOcean has completed the installation and burial of all 91 inter-array cables at DONG Energy’s 573MW Race Bank offshore wind farm off North Norfolk.

  • 9 September 2015
    Grid Connection

    Canyon Offshore Ltd, the robotics subsidiary of Helix Energy Solutions Group Inc., has been awarded a multi-million pound project with VBMS Ltd on the Statoil, Masdar and Stakraft Dudgeon Offshore Wind Farm for the supply of its services to provide the trenching solution for inter array cables. As part of the cable contract VBMS will […]

  • 7 September 2017
    Grid Connection, Wind Farm Update

    All inter-array cables have been laid at the Race Bank offshore wind farm and the works on burial will be completed in the near future, DONG Energy, the owner and developer of the 573MW project off North Norfolk said.

  • 28 July 2016
    Grid Connection, R&D, Technology

    JDR, the UK based supplier of subsea power cables and umbilicals to the offshore energy industry, has showcased its new high-voltage inter-array cable and accessories at its latest customer technology day held at Hartlepool College of Further Education. The company says that its new 66 (72.5) kV cable technology ”will be critical to support the offshore wind […]

  • 14 December 2016
    Wind Farm Update

    DONG Energy has contracted Nexans to supply and terminate a total of 139km of a three-phase subsea cable for the first of three construction phases of the Hornsea Project One wind farm.  The 34kV cables of latest generation will be used for inter-linking a total of 58 wind turbines and connecting them to the offshore transformer […]

  • 14 June 2013

    Sandbank Offshore Wind GmbH, Hamburg, intends to build an offshore wind farm in the North Sea. In the first construction phase it is planned to build 72 wind turbines with a total output of 288 MW, inter array cables and an offshore substation. The project is located in the German Bight area, around 90 kms […]

  • 3 October 2014
    Business & Finance, Wind Farm Update

    Sandbank Offshore Wind GmbH has awarded Germanischer Lloyd Industrial Services and TÜV SÜD Industrie Service GmbH a contract for the certification of the Sandbank offshore wind farm. In the first construction phase it is planned to build 72 wind turbines with a total output of 288 MW, inter array cables and an offshore substation. The project is located in the […]

  • 14 August 2017
    Operations & Maintenance, Vessels

    VBMS has recently repaired two inter-array cables and one export cable in the Thames Estuary and the Irish Sea. VMBS used Stemat 82 to carry out the inter-array cable repairs in the shallow waters of the outer Thames Estuary due to its 8-point mooring system and 2.3m depth. The repair of the export cable was […]

  • 4 July 2017
    Grid Connection, Vessels, Wind Farm Update

    Fugro has laid the final inter-array cable at the 400MW Rampion offshore wind farm off Sussex, UK.

  • 14 January 2020
    Wind Farm Update

    Van Oord has installed the first inter-array cable on the 731.5MW Borssele III & IV offshore wind farm in the Dutch North Sea. The cable, provided by Prysmian Group, was installed by the cable-laying vessel Nexus. Located 22 kilometres off the coast of the Province of Zeeland, Borssele III & IV will feature 77 MHI […]

  • 14 October 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Tideway B.V., part of DEME Group, has awarded Prysmian Group with a EUR 13 million contract to supply inter-array cables and accessories for the 309MW Rentel offshore wind farm in Belgian North Sea.  Prysmian is responsible for the design, manufacture and supply of the 33 kV submarine cables in various cross-sections, together with the related cable […]

  • 5 December 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Equinor has signed an agreement with the Prysmian Group for the supply of inter-array cables for the Empire Wind offshore wind project in New York. Prysmian revealed that it is responsible for the design, supply and storage of approximately 150km of 66kV XLPE-insulated inter-array cables, which will transmit twice the current industry standard ensured by […]

  • 18 September 2019
    Contracts & Tenders, Grid Connection

    Ørsted has contracted Hellenic Cables to supply subsea cable that will be used as spares for its offshore wind farms in the UK. Under the contract, Hellenic Cables is in charge of the design, manufacture and testing of the 33kV inter-array submarine cable. The company will produce 23km of cable at its plant in Corinth, Greece, and is […]

  • 14 March 2014
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    Prysmian Cables and Systems USA has been awarded the contract for the eventual supply of the inter-array and export power cables for the Cape Wind’s offshore wind farm, while Caldwell Marine International has been awarded the contract for the installation of the project’s underwater cables. The onshore transmission cables would be manufactured by Prysmian at […]

  • 30 October 2015

    VBMS has been awarded two contracts with a total value of approximately €200 million for the Galloper Offshore Wind Farm. VBMS has signed a contract for the export cabling scope in a consortium with nkt cables, for the supply and installation of two 45km long export cables, including route preparation, landfall operations, burial, termination and testing […]

  • 20 February 2018
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Van Oord has awarded Norddeutsche Seekabelwerke GmbH (NSW), a subsidiary of General Cable Corporation, to design, produce and deliver 45km of medium-voltage submarine power cables for the inter-array grid of the Deutsche Bucht (DeBu) offshore wind farm.

  • 8 August 2016
    Grid Connection, Vessels, Wind Farm Update

    Siem Offshore’s recent additions to the fleet, the installation support vessel Siem Moxie and the cable lay vessel Siem Aimery, are expected to install all of the 59 inter-array grid cables for the 332MW Nordsee One offshore wind farm by the end of August. Siem Offshore Contractors GmbH (SOC), a wholly owned subsidiary of Siem Offshore, […]