Search results for: Inter-Array

496 results

A list of search results

24 July 2019 Wind Farm Update

[…]

6 June 2019 Grid Connection, Wind Farm Update

[…]

6 June 2019 Contracts & Tenders

[…]

5 June 2019 Contracts & Tenders, Grid Connection, Wind Farm Update

[…]

29 May 2019 Grid Connection

[…]

30 April 2019 Grid Connection, Wind Farm Update

[…]

13 February 2019 Business & Finance, Contracts & Tenders

[…]

30 August 2018 Contracts & Tenders, Wind Farm Update

Ørsted has awarded a multi-million pound contract to JDR Cables for the supply of inter-array cables and termination work for Hornsea Project Two, which will become the world’s biggest offshore wind farm, once operational in 2022.

17 July 2018 Wind Farm Update

The cable laying vessel (CLV) Siem Aimery will commence the third inter-array cable installation campaign at the Beatrice offshore wind farm on 17 July, according to the latest Notice to Mariners from the project’s marine coordination team. 

16 July 2018 Grid Connection, Wind Farm Update

Deutsche Offshore Consult GmbH (DOC) has completed the supervision of the inter-array cable installation at the 396MW Merkur offshore wind farm in the German North Sea.

28 May 2018 Wind Farm Update

The eleventh and final MHI Vestas turbine was erected on 26 May at the European Offshore Wind Deployment Centre (EOWDC), where the inter-array cable installation works are also coming to an end, thus moving the project to the final commissioning phase before it generates its first power later this summer. 

21 March 2018 Vessels, Wind Farm Update

After installing 16 inter-array cables at the Beatrice offshore wind farm in late 2017, the cable laying vessel Siem Aimery continued the works with the second campaign that started on 10 March.

20 February 2018 Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

Van Oord has awarded Norddeutsche Seekabelwerke GmbH (NSW), a subsidiary of General Cable Corporation, to design, produce and deliver 45km of medium-voltage submarine power cables for the inter-array grid of the Deutsche Bucht (DeBu) offshore wind farm.

28 December 2017 Vessels, Wind Farm Update

Siem Offshore Services’ cable laying vessel Siem Aimery has installed 15 inter-array cables during the first cable installation campaign on the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

10 November 2017 Wind Farm Update

The first inter-array cable installation campaign at the Beatrice offshore wind farm started today, 10 November, as the cable laying vessel Siem Aimery, supported by CSV Siem Stingray, is set to install up to 24 cables in the south part of the project site.

9 November 2017 Wind Farm Update

Dutch company Ridderflex has produced and delivered about 180 customised polyurethane hang-offs and plugs to GeoSea, the company now using these tools to connect the inter-array cables to the wind turbines at Belgian Rentel offshore wind farm.

26 October 2017 Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

VBMS has signed a Preferred Bidder Agreement for the supply and installation of the inter-array cables for Moray Offshore Windfarm East (MOWE) off Scotland, the UK.

23 October 2017 Wind Farm Update

Seaway Heavy Lifting (SHL) is set to commence the first pre-lay grapnel run campaign at the Beatrice offshore wind farm site to clear the inter-array cable routes from debris and prepare them for cable installation.

9 October 2017 Wind Farm Update

DeepOcean has completed the installation and burial of all 91 inter-array cables at DONG Energy’s 573MW Race Bank offshore wind farm off North Norfolk.

7 September 2017 Grid Connection, Wind Farm Update

All inter-array cables have been laid at the Race Bank offshore wind farm and the works on burial will be completed in the near future, DONG Energy, the owner and developer of the 573MW project off North Norfolk said.

25 August 2017 Grid Connection, Wind Farm Update

Hartlepool-based subsea cable specialist JDR has manufactured the inter-array cables for the 588MW Beatrice offshore wind farm, Beatrice Offshore Wind Farm Ltd (BOWL) said.

4 July 2017 Grid Connection, Vessels, Wind Farm Update

Fugro has laid the final inter-array cable at the 400MW Rampion offshore wind farm off Sussex, UK.

22 June 2017 Wind Farm Update

Siem Offshore Contractors (SOC) has awarded Canyon Offshore Limited, an Aberdeen-based trenching solutions provider, a contract for the provision of trenching services on DONG Energy’s Hornsea Project One offshore wind farm.

7 April 2017 Wind Farm Update

On 6 April, first inter-array cable was installed at the Galloper offshore wind farm in the UK, according to innogy UK.

24 March 2017 Grid Connection, Vessels, Wind Farm Update

The cable laying vessel Stemat Spirit is being loaded with the first batch of inter-array cables for the Galloper offshore wind farm at JDR Cables’ facility in Hartlepool.

24 March 2017 Business & Finance, Operations & Maintenance, Wind Farm Update

North Yorkshire-based Specialist Marine Consultants has won a contract to provide client representatives to monitor turbine installation and inter-array cable installation works on DONG Energy’s 573MW Race Bank offshore wind farm off North Norfolk.