Search results for: Inter-Array

9570 results

A list of search results

  • 16 July 2018
    Grid Connection, Wind Farm Update

    Deutsche Offshore Consult GmbH (DOC) has completed the supervision of the inter-array cable installation at the 396MW Merkur offshore wind farm in the German North Sea.

  • 6 June 2019
    Grid Connection, Wind Farm Update

    Van Oord has deployed its trencher Dig-It to bury the laid inter-array cables at the Deutsche Bucht offshore wind farm in Germany. The inter-array cables are being buried at the required depth of 1.5m below the seabed at the 269MW project, Van Oord said. The Dutch company reported that its cable laying vessel Nexus installed […]

  • 9 September 2015
    Grid Connection

     Advanced Global Energy and Dynamo Electrical have formed a new engineering company Inter Array Engineering. Inter Array Engineering will offer a OWF package for clients with services including all of the following, MV/HV/EHV termination and testing, fibre optic services, wind farm management, wind farm consultancy and full training facilities and packages. Both of Inter Arrays […]

  • 24 July 2019
    Wind Farm Update

    The installation and the testing of the inter-array cables at the Deutsche Bucht wind farm in the German North Sea has been completed according to Northland Power, the owner and developer of the project. Van Oord, the Balance of Plant contractor (BoP) for the 269MW project, awarded Norddeutsche Seekabelwerke (NSW) with a contract to design, produce and deliver 45 kilometres […]

  • 20 May 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Vattenfall has signed final contracts with Prysmian Powerlink S.r.l. and B.V. Twentsche Kabelfabriek (TKF) for the manufacturing and supply of the inter-array cable systems for the Hollandse Kust Zuid 1-4 offshore wind farm. The inter-array cable systems will connect approximately 140 Siemens Gamesa 11 MW wind turbines with two offshore high voltage stations in the […]

  • 31 October 2014
    Business & Finance, Grid Connection

    Eolien Maritime France, a subsidiary of EDF EN France and DONG Energy, has invited tenders for the delivery and installation of inter-array grid for Courseulles sur Mer, Fecamp and Saint-Nazaire’s offshore wind farms. The scope concerns the design, engineering, procurement, construction, transport, storage, installation, commissioning, testing and other services for the three wind farms. Divided in three lots, […]

  • 25 August 2017
    Grid Connection, Wind Farm Update

    Hartlepool-based subsea cable specialist JDR has manufactured the inter-array cables for the 588MW Beatrice offshore wind farm, Beatrice Offshore Wind Farm Ltd (BOWL) said.

  • 16 August 2018
    Grid Connection, Vessels, Wind Farm Update

    Boskalis Subsea’s cable laying vessel Stemat Spirit has started laying inter-array cables on the 497MW Hohe See, EnBW, the developer and majority owner of the wind farm in the German North Sea, said.

  • 12 May 2020
    Wind Farm Update

    Oceaneering International Services Ltd (OISL) is about to start clearing the inter-array cable routes at the Moray East site. According to a Notice of Operations, boulder clearance at the export cable routes should finish on 12 May. Immediately after that, the same work at the inter-array routes is set to commence. Clearing the inter-array cable […]

  • 5 August 2015
    Business & Finance

    Prysmian Group has been awarded contracts by Nobelwind NV, an offshore wind farm developer, to supply wind turbine inter-array cables for the Bligh Bank 2 (Belwind 2) offshore wind farm, located off the coast of Zeebrugge in Belgium. Prysmian is responsible for the design, manufacture and supply of the 33 kV submarine cables with various […]

  • 27 May 2020
    Grid Connection, Wind Farm Update

    DEME Group has completed inter-array cable laying works at the SeaMade offshore wind farm in Belgium. DEME’s DP3 cable installation vessel Living Stone laid 64 inter-array cables with a total length of 71.2km. According to the company, the vessel operated at peak production levels, laying up to three cables per day. To remind, the inter-array […]

  • 17 July 2018
    Wind Farm Update

    The cable laying vessel (CLV) Siem Aimery will commence the third inter-array cable installation campaign at the Beatrice offshore wind farm on 17 July, according to the latest Notice to Mariners from the project’s marine coordination team. 

  • 23 September 2014
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    VBMS has awarded JDR the inter-array cable contract for the Vattenfall AB Sandbank offshore wind farm. JDR will design and manufacture 105 kilometres of inter-array cable, including a new coilable 630mm2 copper core cable and a range of cable accessories. The Sandbank offshore wind farm will be constructed 90km west of Sylt island, within the […]

  • 28 December 2017
    Vessels, Wind Farm Update

    Siem Offshore Services’ cable laying vessel Siem Aimery has installed 15 inter-array cables during the first cable installation campaign on the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

  • 10 November 2017
    Wind Farm Update

    The first inter-array cable installation campaign at the Beatrice offshore wind farm started today, 10 November, as the cable laying vessel Siem Aimery, supported by CSV Siem Stingray, is set to install up to 24 cables in the south part of the project site.

  • 6 July 2015
    Grid Connection, Wind Farm Update

    JDR has been awarded a subcontract by Siem Offshore Contractors GmbH to supply submarine composite power cables and related accessories as well as termination and testing services for the Veja Mate offshore wind farm.  The 67 Siemens 6 MW wind turbines will be inter-connected by an inner array grid of JDR-designed and manufactured 33 kV medium […]

  • 10 April 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Dutch cable manufacturer Twentsche Kabel Fabriek (TKF) has revealed further details about the company’s scope of work on the 342 MW Kaskasi offshore wind project. As reported earlier, Seaway 7 awarded TKF with a contract to deliver 33 kV inter-array cables for the wind farm. Under the contract, TKF will manufacture and deliver 52 kilometres […]

  • 24 March 2017
    Grid Connection, Vessels, Wind Farm Update

    The cable laying vessel Stemat Spirit is being loaded with the first batch of inter-array cables for the Galloper offshore wind farm at JDR Cables’ facility in Hartlepool.

  • 27 February 2020
    Grid Connection, Wind Farm Update

    The first inter-array cable has been installed at the Borssele 1 & 2 offshore wind project in the Netherlands. Nexans is providing up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW project, while Van Oord is in charge of the transport and installation. Van Oord is deploying its […]

  • 13 June 2012
    Grid Connection

    JDR Cable Systems has won its first ever offshore wind farm export wire supply contract. Danish developer Dong has selected the subsea inter-array specialist to manufacture a 12km medium-voltage link for the two-turbine Gunfleet Sands demonstrator. The cable is being produced in JDR’s Hartlepool facilities and will be finished by the end of next month […]

  • 21 March 2018
    Vessels, Wind Farm Update

    After installing 16 inter-array cables at the Beatrice offshore wind farm in late 2017, the cable laying vessel Siem Aimery continued the works with the second campaign that started on 10 March.

  • 17 March 2020
    Wind Farm Update

    30 monopile foundations and 14 inter-array cables have so far been installed on the 752MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, Ørsted said. Located some 23 kilometres off the coast of Zeeland, Borssele 1 + 2 will comprise 94 Siemens Gamesa 8MW wind turbines scheduled to be operational by […]

  • 16 May 2017
    Wind Farm Update

    After EnBW recently reached the final investment decision for the 112MW Albatros offshore wind farm and awarded the Tier 1 supply contracts, VBMS – in charge of inter-array cabling – informed that part of the scope is to interconnect Albatros and EnBW Hohe See.

  • 29 December 2016
    Grid Connection, Vessels, Wind Farm Update

    Siem Offshore Contractors GmbH ( SOC) has shared a video of two of its vessels, the cable lay vessel Siem Aimery and the installation support vessel Siem Moxie, laying inter-array cables at the 332MW Nordsee One offshore wind farm in the North Sea. Siem worked at the site from June to August 2016. The inter-array cables were supplied […]

  • 14 May 2020
    Wind Farm Update

    Ørsted has provided an update on the ongoing offshore construction work at the 752 MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, saying that all activities are going according to plans. So far, DEME’s installation vessel Innovation has installed 73 out of the 94 monopile foundations at the site some […]

  • 7 November 2017
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Vos Prodect Innovations has won a contract by TKF (Twentsche Kabelfabriek) for the design and supply of sealed inter-array cable hang-off systems for the 497MW Hohe See offshore wind farm project located in the German North Sea.