Search results for: Iemants

88 results

A list of search results

  • 2 December 2016

    8.2 Consulting has carried out BSH collision friendliness analyses of the support structures at three Iemants projects, including the offshore wind farms Veja Mate and EnBW Hohe See. 8.2AG outlined the necessary verifications and performed a hull-retaining verification assessment. This includes the preparation of a numerical crash-worthiness analysis to evaluate the consequences of vessel collision […]

  • 6 March 2017
    Wind Farm Update

    The second offshore substation for the Race Bank offshore wind farm set sail to the UK on 5 March, ENGIE Fabricom and Iemants reported.

  • 20 March 2017
    Grid Connection, Wind Farm Update

    The Engie Fabricom and Iemants consortium has shipped the first of two offshore substations built for DONG Energy’s 660MW Walney Extension offshore wind farm in the Irish Sea from the construction yard in Hoboken, Belgium.

  • 26 October 2018
    Grid Connection, Ports & Logistics, Wind Farm Update

    Smulders, acting for and on behalf of the JV Iemants-Eiffage, has rolled out the substation topside for the Deutsche Bucht offshore wind farm at the yard of Damen Shiprepair Vlissingen. The milestone was achieved 10 months after starting the final assembly in January 2018. The topside was driven outside for further outfitting on 21 October. Offshore […]

  • 8 September 2017
    Wind Farm Update

    Iemants, part of the Smulders Group, loaded out the jacket foundation for the Merkur wind farm offshore substation from its facility in Vlissingen, the Netherlands, on Tuesday, 5 September.

  • 10 March 2017
    Grid Connection, Wind Farm Update

    The load-out of the first of two substations built by the Engie Fabricom-Iemants consortium for DONG Energy’s 660MW Walney Extension offshore wind farm took place in Hoboken, Belgium, on Thursday, 9 March. The topside was removed from its base on the production site and put on the pontoon. The topside was loaded next to the jacket foundation which […]

  • 28 November 2014
    Grid Connection

    All construction activities on Eneco’s four-story transformer station have been completed. The Offshore High Voltage Station is sitting on large grounds of Fabricom Cofely (GDF SUEZ) in Hoboken (Antwerp) where it will be finished and tested prior to the installation scheduled for February next year. The transformer station will collect electricity generated by 43 turbines […]

  • 14 November 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Energinet.dk and 50Hertz Transmission GmbH have awarded Iemants and Jan De Nul Group with a contract to construct, install, ballast and protect gravity based foundations (GBFs) for two offshore substations. The two offshore substations will serve Vattenfall’s 600MW Kriegers Flak offshore wind farm in the Danish part of the Baltic Sea, and will also serve as an interconnector between […]

  • 31 March 2017
    Grid Connection, Wind Farm Update

    The second offshore substation built by the Engie Fabricom/Iemants consortium for DONG Energy’s 660MW Walney Extension wind farm has set sail from the Engie Fabricom site in Hoboken, Belgium, bound for the wind farm in the Irish Sea.

  • 14 December 2017
    Grid Connection, Wind Farm Update

    An offshore substation topside built by Engie Fabricom-Tractebel and Iemants for the Merkur offshore wind farm has been loaded out at ENGIE Fabricom’s yard in Hoboken, Belgium.

  • 30 November 2017
    Grid Connection, Wind Farm Update

    ENGIE Fabricom has rolled out the substation topside being built for the Hohe See offshore wind farm at the company’s yard in Hoboken, Belgium.

  • 29 August 2016
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    ENGIE Fabricom-Tractebel and Iemants have joined forces to carry out engineering, procurement, construction, testing and commissioning of an offshore substation and an associated jacket for the 396MW Merkur offshore wind farm in the German North Sea.  ENGIE Fabricom is in charge of the overall integration of all systems of the offshore substation which will be built throughout 2016 […]

  • 29 October 2013

    On Saturday October 18th Verbrugge Terminals in the Port of Vlissingen and its partner Sarens successfully completed the load-out of five tripods for the German offshore wind farm Global Tech I. The consortium Iemants N.V. and Eiffage Construction Métallique S.A.S were responsible for the load-out, including stability engineering of the tripods and engineering of the […]

  • 16 March 2017
    Wind Farm Update

    The jacket foundation for the Race Bank 01 offshore substation (OSS), installed after the Race Bank 02 OSS, was placed and fixed to the seabed at the offshore wind farm site on 15 March, with the 2,900t topside up next.

  • 11 December 2017
    Wind Farm Update

    Jan De Nul and Iemants have completed the two gravity-based foundations for Kriegers Flak substations. The steel structures, designed and built by Iemants (Smulders), have been placed on top of their corresponding concrete structures and the foundations are now being prepared to be transported from the port of Ostend in Belgium to Denmark by the end of December. 

  • 16 June 2016
    Wind Farm Update

    Topside and jacket of the high voltage offshore substation (OSS) for the Burbo Bank Extension offshore wind farm left ENGIE Fabricom’s Hoboken yard yesterday, as they start their journey from Antwerp towards the site off the west coast of England.  By the end of this month, the jacket and topside will be installed at the construction site of […]

  • 11 October 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessel Oleg Strashnov is currently at the Merkur offshore wind farm site as the vessel is deployed on installing the jacket foundation for the Merkur offshore substation. According to vessel’s AIS data, Oleg Strahnov has arrived at the site on 8 October. 

  • 23 February 2017
    Wind Farm Update

    The topside and jacket of the second substation for the Race Bank offshore wind farm have been loaded onto a pontoon in Hoboken, Belgium, according to Seacontractors’ latest social media post.

  • 9 January 2018
    Ports & Logistics, Vessels, Wind Farm Update

    A barge carrying two gravity based foundations (GBFs) for the high voltage station of the Danish 605MW Kriegers Flak offshore wind farm has left the port of Ostend, Belgium.

  • 26 September 2013
    Business & Finance

    The Metal branch of Eiffage has signed a contract for the acquisition of the main entities of the Smulders group: Smulders, Iemants, Willems and Spomasz. The acquired businesses will generate about €200 million of revenues for 2013 (for the full year) with 770 employees located in Belgium, Netherlands and Poland. With this acquisition, Eiffage is […]

  • 27 February 2017

    GeoSea has appointed Con4Mare to provide marine warranty survey services for the 396MW Merkur offshore wind farm (formerly known as MEG I), located 45km north of Borkum, Germany, in the North Sea.

  • 20 November 2016
    Authorities, Business & Finance, Environment, Grid Connection, Operations & Maintenance, R&D, Technology, Training & Education, Vessels, Wind Farm Update

    Iemants and Jan De Nul Win Kriegers Flak OSS Foundations Work Energinet.dk and 50Hertz Transmission GmbH have awarded Iemants and Jan De Nul Group with a contract to construct, install, ballast and protect gravity based foundations (GBFs) for two offshore substations. ABB Unveils Lightweight, AC Platform-Free HVDC Solution ABB has presented a new, compact, high-voltage […]

  • 19 March 2015

    Always wanted to know how a transition piece for an offshore wind turbine is fabricated? The Belgium-based steel construction specialist, Smulders Group, gives us an insight into the whole process from planning to the finished product. The Smulders Group is an international organization with a total of approximately 800 employees spread over 4 main entities: […]

  • 29 June 2017
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Jan De Nul Group has taken delivery of the multipurpose vessel Adhémar de Saint-Venant which as of next week will start working on the Kriegers Flak OSS project in Denmark.

  • 4 July 2016
    Wind Farm Update

    The topside of the substation for Dong Energy’s 258MW Burbo Bank Extension offshore wind farm was installed on 25 June, Smulders reported.  The substation topside and jacket left Engie Fabricom’s Hoboken yard in Belgium on 15 June. A consortium of ENGIE Fabricom and Iemants has been contracted by DONG Energy for the fabrication of the offshore substation. The load-out […]

  • 21 August 2015
    Wind Farm Update

    The first offshore transformer station at the Gemini offshore wind farm was placed on top of the jacket foundation yesterday. After installing the jackets earlier this month, the heavy-lift vessel Rambiz is also carrying out the rest of the work on the substation installation. A joint venture between Cofely Fabricom, CG and Iemants, is in charge of the two offshore […]