Search results for: Iemants

70 results

A list of search results

8 September 2017 Wind Farm Update

Iemants, part of the Smulders Group, loaded out the jacket foundation for the Merkur wind farm offshore substation from its facility in Vlissingen, the Netherlands, on Tuesday, 5 September.

2 December 2016

8.2 Consulting has carried out BSH collision friendliness analyses of the support structures at three Iemants projects, including the offshore wind farms Veja Mate and EnBW Hohe See. 8.2AG outlined the necessary verifications and performed a hull-retaining verification assessment. This includes the preparation of a numerical crash-worthiness analysis to evaluate the consequences of vessel collision […]

14 November 2016 Business & Finance, Grid Connection, Wind Farm Update

Energinet.dk and 50Hertz Transmission GmbH have awarded Iemants and Jan De Nul Group with a contract to construct, install, ballast and protect gravity based foundations (GBFs) for two offshore substations. The two offshore substations will serve Vattenfall’s 600MW Kriegers Flak offshore wind farm in the Danish part of the Baltic Sea, and will also serve as an interconnector between […]

29 August 2016 Business & Finance, Grid Connection, Technology, Wind Farm Update

ENGIE Fabricom-Tractebel and Iemants have joined forces to carry out engineering, procurement, construction, testing and commissioning of an offshore substation and an associated jacket for the 396MW Merkur offshore wind farm in the German North Sea.  ENGIE Fabricom is in charge of the overall integration of all systems of the offshore substation which will be built throughout 2016 […]

8 January 2019

Markets Outlook: Belgian Offshore Platform Offshore wind energy in Belgium There are currently 8 offshore wind projects in the Exclusive Economic Zone (EEZ) representing a total installed capacity of 2.267MW offshore wind energy. In 2018, five projects, C-Power, Belwind, Northwind, Nobelwind and Rentel, representing 1.186MW, are fully operational and meet the electricity needs of about […]

26 October 2018 Grid Connection, Ports & Logistics, Wind Farm Update

Smulders, acting for and on behalf of the JV Iemants-Eiffage, has rolled out the substation topside for the Deutsche Bucht offshore wind farm at the yard of Damen Shiprepair Vlissingen. The milestone was achieved 10 months after starting the final assembly in January 2018. The topside was driven outside for further outfitting on 21 October. Offshore […]

13 June 2018 Wind Farm Update

Ørsted and its project partners, Macquarie and Sumitomo, officially opened the 573MW Race Bank offshore wind farm on 13 June at a ceremony in Grimsby, UK.

12 June 2018 Grid Connection, Ports & Logistics, Wind Farm Update

ENGIE Fabricom has loaded out the EnBW Hohe See substation topside at its yard in Hoboken, Belgium. The topside is expected to leave the yard and head to the installation site in the German North Sea soon. The substation’s jacket foundation was installed earlier this month. The substation, built by a consortium of ENGIE Fabricom, Iemants […]

30 May 2018 Wind Farm Update

Smulders sent off the jacket foundation for the EnBW Hohe See offshore substation (OSS) from its yard in Vlissingen on 29 May and the structure is now travelling to the German project site in the North Sea, where it will be installed on 31 May or 1 June. 

29 May 2018 Business & Finance, Operations & Maintenance, Wind Farm Update

Ørsted and its Race Bank project partners, Macquarie and Sumitomo, will hold an inauguration ceremony for the 573MW offshore wind farm in Grimsby, UK, on 13 June.

11 April 2018 Ports & Logistics, Vessels, Wind Farm Update

EnBW has started the offshore construction on two wind farms in the German North Sea – the 497MW Hohe See and the 112MW Albatros. 

17 January 2018 Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

A barge loaded with two gravity-based foundations (GBFs) for the high voltage station of the 605MW Kriegers Flak offshore wind farm has arrived in Koge, Denmark, Blue Water Shipping (BWS), the port agents for the project, told Offshore WIND.

12 January 2018 Operations & Maintenance, Vessels

Our latest photo of the day shows Seacat Services’ crew transfer vessel (CTV) Seacat Volunteer picking up technicians from the substation at Ørsted’s 573MW Race Bank offshore wind farm located off the North Norfolk coast, UK.

12 January 2018 Grid Connection, Vessels, Wind Farm Update

The 2,660t topside for the Merkur offshore substation was lifted yesterday, 11 January, from a transport barge to the Oleg Strashnov heavy lift vessel, which is expected to install it on its foundation today. 

9 January 2018 Ports & Logistics, Vessels, Wind Farm Update

A barge carrying two gravity based foundations (GBFs) for the high voltage station of the Danish 605MW Kriegers Flak offshore wind farm has left the port of Ostend, Belgium.

14 December 2017 Grid Connection, Wind Farm Update

An offshore substation topside built by Engie Fabricom-Tractebel and Iemants for the Merkur offshore wind farm has been loaded out at ENGIE Fabricom’s yard in Hoboken, Belgium.

11 December 2017 Wind Farm Update

Jan De Nul and Iemants have completed the two gravity-based foundations for Kriegers Flak substations. The steel structures, designed and built by Iemants (Smulders), have been placed on top of their corresponding concrete structures and the foundations are now being prepared to be transported from the port of Ostend in Belgium to Denmark by the end of December. 

30 November 2017 Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

The first steel structure which will support one of Kriegers Flak offshore substations was placed onto the concrete section of the gravity based foundation (GBF) at the port of Ostend, Belgium, Jan De Nul said.

30 November 2017 Grid Connection, Wind Farm Update

ENGIE Fabricom has rolled out the substation topside being built for the Hohe See offshore wind farm at the company’s yard in Hoboken, Belgium.

11 October 2017 Vessels, Wind Farm Update

Seaway Heavy Lifting’s vessel Oleg Strashnov is currently at the Merkur offshore wind farm site as the vessel is deployed on installing the jacket foundation for the Merkur offshore substation. According to vessel’s AIS data, Oleg Strahnov has arrived at the site on 8 October. 

22 September 2017 Grid Connection

German transmission system operator TenneT has awarded UK companies RPS Energy Limited and Ordtek Limited with contracts to provide consultancy and QA/QC services for unexploded ordnance (UXO) survey campaigns on two separate projects.

29 June 2017 Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

Jan De Nul Group has taken delivery of the multipurpose vessel Adhémar de Saint-Venant which as of next week will start working on the Kriegers Flak OSS project in Denmark.

13 April 2017 Grid Connection, Vessels, Wind Farm Update

Seaway Heavy Lifting’s vessel Oleg Strashnov has installed two offshore substations on DONG Energy’s 660MW Walney Extension wind farm in the Irish Sea.

31 March 2017 Grid Connection, Wind Farm Update

The second offshore substation built by the Engie Fabricom/Iemants consortium for DONG Energy’s 660MW Walney Extension wind farm has set sail from the Engie Fabricom site in Hoboken, Belgium, bound for the wind farm in the Irish Sea.

27 March 2017 Wind Farm Update

Following the installation of the jacket foundation on 15 March, the 2,900t topside for the second offshore substation at the Race Bank offshore wind farm was installed over the weekend.

20 March 2017 Grid Connection, Wind Farm Update

The Engie Fabricom and Iemants consortium has shipped the first of two offshore substations built for DONG Energy’s 660MW Walney Extension offshore wind farm in the Irish Sea from the construction yard in Hoboken, Belgium.