  • 7 July 2020
    Vessels, Wind Farm Update

    The first jacket foundation is now in place at the Moray East offshore wind farm in Scotland. DEME Offshore, in charge of the installation works, is currently using the Seajacks Scylla jack-up vessel to install the jackets. The 950 MW offshore wind project will comprise 100 MHI Vestas 9.5 MW wind turbines and three offshore substations, […]

  • 12 February 2020
    Technology, Vessels, Wind Farm Update

    This is the first wind farm in the world to use drilled XL-monopile foundations, DEME said.

  • 23 January 2020
    Business & Finance

    The first turbines, with a capacity of 1.5MW, were installed in 2000 at the 10.5MW Utgrunden offshore wind farm in the Baltic Sea in Sweden.

  • 18 April 2019

    The Offshore Wind Conference 2019 team is proud to announce that leading provider of services and solutions for the offshore energy industry DEME Offshore is the main sponsor of this year’s conference on 7 and 8 October at the Amsterdam RAI. DEME Offshore provides the most comprehensive offering to offshore energy customers. In the renewables […]

  • 26 April 2019
    Contracts & Tenders, R&D, Wind Farm Update

    DEME Offshore has signed an agreement with Equinor to carry out a study examining potential floating concrete substructures for the planned Hywind Tampen floating wind farm in the Norwegian North Sea. The agreement was signed early December 2018 with a five-month duration, and the study is a part of the engineering works before the final investment […]

  • 21 February 2019
    Business & Finance

    DEME Group has integrated the activities of its subsidiaries GeoSea, Tideway, A2Sea and EverSea into one business. DEME Offshore will combine renewable energy and oil & gas activities, as well as other offshore related activities. Hugo Bouvy is the Managing Director of the new business, with Bart De Poorter assuming the role of General Manager […]

  • 31 May 2019
    Vessels

    Dordrecht-based Safeway BV has won a contract to deliver its Osprey-type motion compensated offshore access system for DEME Offshore’s installation vessel Orion.   According to Safeway, the most unique feature of this custom made Safeway walk-to-work system is that the gangway is vertically integrated in a specially designed staircase, which means that the ‘plug and play’ […]

  • 24 March 2020
    Business & Finance

    Japanese marine contractor Penta-Ocean Construction and DEME Offshore have concluded a memorandum of understanding (MOU) regarding comprehensive cooperation for the construction of offshore wind farms in Japan. In light of recent regulations which promote offshore wind power generation in the general sea areas, as well as in port and harbour areas, the development of offshore […]

  • 1 March 2019
    Operations & Maintenance, Technology

    DEME Offshore has partnered with the aerospace industry supplier SABCA to develop and deploy unmanned vehicles to perform surveillance and inspection works in the offshore industry. The companies are convinced that these technologies have a game-changing potential to increase health and safety of their employees, lower the impact on the environment in the O&M phase of […]

  • 17 May 2019
    Contracts & Tenders, Wind Farm Update

    DEME Offshore has won contracts to transport and install foundations and wind turbines on Ørsted’s 1.4GW Hornsea Two offshore wind farm in the UK. The Hornsea Two offshore wind farm is located approximately 89 kilometres off the Yorkshire coast and will comprise 165  Siemens Gamesa 8.4MW wind turbines installed on monopile foundations. DEME Offshore will transport […]

  • 9 January 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has loaded the first set of monopiles to be installed on the Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 in the Port of Rotterdam. DEME is in charge of transporting and installing the 94 monopile […]

  • 29 May 2020
    Business & Finance

    DEME Offshore has joined the team behind the PosHYdon project that aims to integrate offshore wind, offshore gas, and offshore hydrogen in the Dutch part of the North Sea. Within the project, DEME Offshore will be in charge of providing the hydrogen unit for installation on the Q13a platform, operated by Neptune Energy. There, the […]

  • 30 January 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has installed 13 of the 94 monopile foundations on the 752MW Borssele 1&2 offshore wind farm in the Dutch North Sea, Ørsted said. Innovation is loading the monopiles and transition pieces at Sif’s Maasvlakte 2 facility before transporting and installing them at the site located some 22 kilometres off the […]

  • 3 March 2020
    Contracts & Tenders, Wind Farm Update

    Jumbo Shipping has secured a contract with DEME Offshore for the transport of foundations for the Hornsea Two offshore wind project. Jumbo will transport 165 monopiles from Rostock, Germany, and 135 transition pieces from Aalborg, Denmark, to Eemshaven, the Netherlands, with a K3000 class vessel. Additionally, the company will undertake the project management for the […]

  • 1 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has arrived at the Borssele 1+2 offshore wind farm in the Dutch North Sea with the final monopiles. Innovation picked up the monopiles last night at Sif Rotterdam, a spokesperson from DEME Offshore said. Sif was in charge of providing 47 monopiles for the project, with EEW SPC, the parent […]

  • 10 June 2019
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up vessel Sea Installer has arrived in Great Yarmouth to load the first set of wind turbine components and install them on the 714MW East Anglia ONE offshore wind farm. The first load-out is ongoing and the vessel is expected to depart for the installation site soon. Back in November 2016, A2SEA, now […]

  • 11 March 2020
    Contracts & Tenders, Wind Farm Update

    The Buss Terminal Eemshaven, in the Netherlands, has secured a contract to serve as a base port for installing the foundations of the Hornsea Two offshore wind project. Under the deal secured with DEME Offshore, the Buss Terminal is responsible for the handling, storage and terminal logistics of the 165 monopiles and transition pieces at […]

  • 4 June 2019

    We are proud to announce Offshore Wind Conference 2019 will officially be opened by DEME Offshore Managing Director Hugo Bouvy. As the world transitions to lower-carbon energy solutions the energy industry needs to determine: what makes commercial and environmental sense and how does offshore wind fit in? Find out during Offshore Wind Conference. Join the […]

  • 18 March 2020
    Grid Connection, Wind Farm Update

    The second SeaMade offshore substation topside has been installed in the Seastar concession area in the Belgian North Sea. The wind farm’s first substation was installed in the Mermaid concession area at the beginning of March. Each with a weight of 1,200 tonnes, the substations transform the wind energy that is produced to 225kV, which in […]

  • 13 February 2020
    Vessels, Wind Farm Update

    DEME Offshore’s jack-up Innovation has installed 18 out of 94 monopile foundations on the 752MW Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation is loading the monopiles and the transition pieces at Sif’s facility on Maasvlakte 2 in Rotterdam and installing them at the site some 22 kilometres off the coast of […]

  • 24 February 2020
    Grid Connection, Wind Farm Update

    The consortium of ENGIE Fabricom, Smulders and DEME Offshore has loaded out the offshore substation destined for the Mermaid offshore wind project in Belgium.

  • 20 May 2020
    Grid Connection, Wind Farm Update

    DEME Offshore and Hellenic Cables have completed the testing and energization of the export cable connections at the SeaMade offshore wind project in Belgium. DEME said it is currently carrying out the inter-array cable installation and preparing for the turbine installation campaign, set to begin in mid-June. “Another important milestone for the SeaMade offshore wind […]

  • 28 May 2019
    Ports & Logistics, Vessels

    Invergordon-based PSG Marine & Logistics Ltd has started loading in and loading out the jacket prepiles and the related equipment from the Port of Cromarty Firth as part of the port marshalling contract awarded by DEME Offshore in support of the Moray East offshore wind project. As reported earlier, DEME’s installation vessel Apollo is carrying out […]

  • 22 June 2020
    Wind Farm Update

    DEME Offshore has installed the first wind turbine at the SeaMade offshore wind farm in Belgium, using its jack-up installation vessel Apollo. The vessel will install 57 wind turbines more at the site located 35-50 kilometres off Oostende, where the 487 MW offshore wind farm is scheduled to be fully up and running by the […]

  • 21 October 2019
    Contracts & Tenders

    CSBC DEME Wind Engineering (CDWE) has signed a Balance of Plant (BOP) Preferred Supplier Agreement (PSA) for the Hai Long 2 and 3 offshore wind projects in Taiwan. Under the BOP package, CDWE is in charge of the Engineering, Procurement, Construction and Installation (EPCI) of foundations, inter-array and export cables, and transportation and installation of turbines. Offshore installation […]

  • 28 August 2019
    Vessels

    DEME Group’s jack-up vessel Innovation is undergoing a final stage of a maintenance and repair program at the Damen Verolme yard in Rotterdam, the Netherlands. The photo shows the vessel during full height jacking trials at the yard. Following the jacking trials and final tests, Innovation will head to ”a full schedule of work”, which […]