  • 29 November 2019
    Wind Farm Update

    The 300MW CTGNE Yangjiang Shapa Phase 1 wind farm has started delivering electricity after the first wind turbines were connected to the Chinese grid, China Three Gorges said. CTGNE Yangjiang Shapa Phase 1 comprises 55 5.5MW wind turbines and is the Three Gorges Group’s first wind project off the Guangdong Province. The wind farm is […]

  • 30 May 2019
    Operations & Maintenance

    The Singapore-based Nautec is supporting the grouting work at the CTGNE Yangjiang Shapa Phase 1 offshore wind farm in China. The company said that its material specialists and grouting engineers are assisting with grouting for turbine and substation jacket foundations at the 300MW project. Nautec is supplying its NaX grouting materials for a total of 10 […]

  • 17 July 2020
    Grid Connection, Wind Farm Update

    Ningbo Orient Cable (NBO) has completed the installation of the export cable at the China Three Gorges New Energy (CTGNE) Yangjiang Shapa Phase 1 offshore wind project. According to NBO, the installation of two 220kV export cables was finished after 14 months and now the offshore engineering team is installing the 35kV inter-array cables. Seven circuits […]

  • 26 May 2020
    Wind Farm Update

    Ningbo Orient Cable (NBO) has delivered 39.6 kilometres of 220 kV export cable for the China Three Gorges New Energy (CTGNE) Yangjiang Shapa Phase 1 offshore wind farm. The company was awarded a contract for the 300 MW project in July 2018, and delivered and installed the first 39.6 kilometres of export cable the following […]

  • 20 March 2020
    Wind Farm Update

    Guangzhou Salvage Bureau has appointed SPT Offshore to install three suction pile jacket foundations at the CTGNE Yangxi Shaba Phase I offshore wind farm in China. SPT Offshore will perform the suction installation services including all related engineering preparations, such as suction installation procedures and suction pile penetration analysis and grouting consultation.  The Netherlands-based company […]

  • 10 March 2020
    Contracts & Tenders, Wind Farm Update

    China Three Gorges has selected Ningbo Orient Wires & Cables to deliver and install submarine cables at the 1,000MW Yangjiang Shapa Phases 3-5 offshore wind farms. Earlier this year, Orient Cables secured a contract to deliver and install the 35kV inter-array and the 220kV export cable at the 400MW Yangjiang Shapa Phase 2 wind farm. […]

  • 7 April 2020
    Business & Finance, Wind Farm Update

    China Three Gorges New Energy (CTGNE) plans to launch an initial public offering (IPO) of its A shares at a total value of CNY 25 billion (approximately EUR 3.3 billion), with most of the raised funds to be used to invest in seven offshore wind projects.

  • 24 February 2020
    Wind Farm Update

    China Three Gorges (CTG) has started construction on what the state-owned utility describes as offshore wind ‘’super projects’’ with a combined capacity of 2,200MW. The two wind farms in question are the 1,400MW Yangjiang Shapa Phases 2-5 project off the city of Yangjiang, Guangdong Province, and the Jiangsu Rudong 800MW (H6, H10) wind farm offshore […]

  • 17 July 2020
    Technology, Wind Farm Update

    MingYang Smart Energy will install the first floating wind turbine off the coast of Yangjiang City in Guangdong Province, China, in 2021. The turbine will have a rated output of 5.5 MW. MingYang has completed the integrated load simulation calculation, and is currently carrying out R&D work on the prototype. The news follows the floating […]

  • 5 November 2018
    Authorities, Business & Finance, R&D

    Chinese politicians and business people are looking to the Humber as they forge ahead with plans for 68GW of operational offshore wind capacity by 2035.

  • 11 March 2020
    Contracts & Tenders

    Orient Cable has been awarded a cable supply contract for the third phase of the Putian Pinghai Bay Offshore Wind Farm.

  • 4 February 2020
    Contracts & Tenders, Grid Connection

    Orient Cable has received a letter of award from China Three Gorges New Energy (CTG) to supply cables for the Guangdong Yangjiang Shaba-West (Phase II) offshore wind project in China.

  • 10 June 2020
    Business & Finance, Wind Farm Update

    China’s MingYang Smart Energy has agreed to sell a minority stake in a special purpose company developing a 300 MW offshore wind project to Poly Changda Engineering. Once the transaction is completed, Poly Changda Engineering will hold a 49 per cent stake in Yangjiang Mingyang Offshore Wind Power Development, with MingYang controlling the remaining 51 […]

  • 5 August 2011
    Operations & Maintenance, R&D

      China Ming Yang Wind Power Group Limited,a leading wind turbine manufacturer in China, announced that it signed a strategic cooperative agreement with China Three Gorges New Energy Corp. ,a fully-owned subsidiary of China Three Gorges Corporation to foster closer cooperation in both domestic and international wind power development. CTGPC is a wholly state-owned enterprise […]

  • 19 February 2019
    Operations & Maintenance, Wind Farm Update

    Siemens Gamesa has started producing the blades for the Formosa 1 Phase 2 offshore wind project in Taiwan. The company said the blades were cast at its Aalborg factory in Denmark using Swancor resin and hardener. Siemens Gamesa won the contract to supply 20 SWT-6.0-154 turbines, which will produce a capacity of 120MW, for the project in April last […]

  • 5 March 2020
    Vessels, Wind Farm Update

    Zhongtian Technology (ZTT) is set to deploy its fleet of installation vessels on the Jiangsu Rudong H6 offshore wind farm in China. ZTT will use its vessels Zhongtian 7, Zhongtian 8, Zhongtian 9, Yuanwei No. 8 and Zhongtian 5, built by Shanghai Yuanwei Construction Engineering Co., Ltd., to carry out its work. The company is in charge of installing […]

  • 11 March 2020
    Wind Farm Update

    China Energy Conservation and Environmental Protection Group (CECEP) has installed the first turbine at its 300MW Yangjiang Nanpeng offshore wind project. The first MySE 5.5-155 turbine was installed on 8 March at the project site some 28km off the coast, Ming Yang Smart Energy reported. The installation of all of the wind farm’s 55 turbines […]

  • 7 September 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Chinese cable manufacturer ZTT has won a contract to supply an export cable system for the 300MW CECEP Yangjiang Nanpeng Island offshore wind farm.

  • 26 December 2019
    Technology

    China’s Ming Yang Smart Energy has marked the start of the mass production of the MySE8-10MW typhoon-resistant offshore wind turbine at its factory in Yangjiang, Guangdong. The start of the mass production was launched at the Mingyang Yangjiang Smart Manufacturing Centre with the roll-out of the first nacelle for the typhoon-resistant turbine at the end […]

  • 20 December 2016
    Wind Farm Update

    Two Siemens 4MW turbines were installed off Taiwanese coast in October, representing the completion of the first phase of the Formosa 1 offshore wind farm, which is set to comprise 32 turbines by 2019.  Both the foundations and turbines were installed by using the vessel M/V TORBEN, formerly known as Friedrich Ernestine, owned by RWE Offshore […]

  • 11 July 2019
    Wind Farm Update

    China General Nuclear Power Corporation (CGN) has installed the first wind turbine on the 400MW CGN Yangjiang Nanpeng Island offshore wind farm. The installation of the first 5.5MW turbine off Guangdong Province in the South China Sea was completed on 27 June, CGN said. Also, 16 wind turbine jacket foundations have so far been installed […]

  • 21 April 2017
    Wind Farm Update

    Taiwan’s first two offshore wind turbines, set up as the first phase of the Formosa 1 offshore wind farm, are reportedly set to enter operations in May.

  • 12 November 2019
    Wind Farm Update

    Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]

  • 20 May 2019
    Wind Farm Update

    The Formosa 1 Phase 2 project has entered the construction phase following a groundbreaking ceremony held in Taiwan’s Miaoli County over the past weekend. Formosa 1 Phase 2 will comprise 20 Siemens Gamesa 6MW turbines installed on monopile foundations some 6km off the west coast of the Miaoli district in the Taiwan Strait. The project is owned by Formosa I Wind […]

  • 7 June 2018
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Jiangsu Hengtong High Voltage Submarine Cable, a subsidiary of Hengtong-Optic Electric, has won a contract to provide 220kV submarine power cables for the Yangjiang Nanpeng Island wind farm offshore Guangdong province, China.

  • 30 March 2020
    Wind Farm Update

    Construction at the Yangjiang Nanpeng Island offshore wind farm in China is back in full swing, according to MingYang Smart Energy. The 401.5MW wind farm, being developed by China General Nuclear Power Corporation (CGN), will comprise 73 MySE 5.5MW turbines offshore the Guangdong Province. The project team is now working full-speed, despite all the current obstacles […]