  • 30 October 2017
    Contracts & Tenders, Grid Connection

    TenneT has awarded the consortium between VBMS and NKT Cables with a contract for the installation of two 67km export cables that will connect the Borssele Beta substation, i.e. the Borssele 3 & 4 offshore wind farms, to the Dutch onshore grid.

  • 6 March 2020
    Grid Connection

    HSM Offshore B.V. has appointed Rhenus Offshore Logistics B.V. for the commissioning logistics of the Borssele Beta offshore high voltage substation. The 700MW Borssele Beta will connect the Borssele 3 & 4 offshore wind farm to the Dutch grid. Offshore construction on the 731.5MW project started in October 2019, with the commissioning scheduled for 2021. HSM Offshore rolled out […]

  • 7 April 2020
    Grid Connection

    The Borssele Beta offshore substation topside has been installed at the project site in the Dutch North Sea. The topside sailed out from HSM Offshore’s yard in Schiedam at the end of March to the site but was awaiting favorable weather conditions to be installed. Borssele Beta will connect the 731.5 MW Borssele III and […]

  • 31 October 2017
    Business & Finance, Contracts & Tenders, Grid Connection

    NKT’s part of the contract for Borssele Beta, won in a consortium with VBMS, is valued at approximately EUR 90 million. As reported earlier, the contract value for VBMS is approximately EUR 70 million.

  • 27 November 2017
    Contracts & Tenders, Grid Connection, Technology

    HSM Offshore has contracted Joulz Energy Solutions as subcontractor for TenneT’s 700MW Borssele Beta to be built offshore at Borssele in the south-west of the Netherlands.

  • 10 March 2020
    Grid Connection

    HSM Offshore has loaded out the Borssele Beta offshore substation topside at its yard in Schiedam, the Netherlands. The 700MW Borssele Beta high voltage substation will connect the 731.5MW Borssele 3 & 4 wind farm to the Dutch grid. The substation’s jacket foundation, also built by HSM Offshore, was installed at the site off Zeeland in May 2019. The […]

  • 30 July 2018
    Grid Connection, Ports & Logistics, Wind Farm Update

    HSM Offshore has loaded out onto a barge the jacket foundation for the Borssele Alpha offshore transformer station at its yard in Schiedam, the Netherlands.

  • 2 December 2019
    Grid Connection

    HSM Offshore BV has rolled out the topside for the Borssele Beta offshore high voltage substation at its yard in Schiedam, the Netherlands. Once completed in 2020, the 700MW Borssele Beta will connect the 731.5MW Borssele 3 & 4 wind farm to the Dutch grid. The offshore construction on the wind farm started in October […]

  • 21 January 2019
    Grid Connection

    HSM Offshore has commenced the assembly of the jacket foundation for the Borssele Beta offshore transformer station at its yard in Schiedam, the Netherlands. The Dutch company secured a contract by TenneT TSO for the construction of the Borssele Beta platform in September 2017, after it had cut the first steel for the Borssele Alpha transformer station. HSM […]

  • 3 May 2019
    Grid Connection

    HSM Offshore has loaded out the jacket foundation for the Borssele Beta offshore transformer station onto a barge at its yard in Schiedam, the Netherlands. To remind, HSM Offshore began the assembly of the jacket in Schiedam at the beginning of the year, The Dutch company secured a contract by TenneT TSO for the construction of the Borssele Beta […]

  • 30 March 2020
    Grid Connection

    The Borssele Beta offshore substation topside has sailed out from HSM Offshore’s yard in Schiedam to the installation site in the Dutch North Sea, TenneT said. The 700MW offshore grid connection is scheduled to be operational on September 1, the Dutch transmission system operator said. Borssele Beta will connect the 731.5MW Borssele III and IV […]

  • 26 June 2020
    Business & Finance, Grid Connection

    Works to install the Borssele Beta export cable in the Netherlands will set TenneT back an additional EUR 50 million after contractors discovered unstable soil along the cable route. Namely, the cable installation contract TenneT signed with NKT and VBMS (now Boskalis Subsea) in 2016/2017 will now be worth EUR 210 million, instead of EUR […]

  • 1 September 2017
    Grid Connection

    Dutch transmission system operator TenneT TSO B.V. and the Schiedam-based HSM Offshore have cut the first steel for the Borssele Alpha offshore transformer station and have signed a contract for the construction of the Borssele Beta platform.

  • 14 May 2019
    Grid Connection

    The jacket foundation for the 700MW Borssele Beta offshore platform has been transported to the installation site in the Dutch North Sea and the installation process has begun, TenneT said. The jacket foundation departed from the HSM Offshore’s yard in Schiedam on Monday, 13 May. The jacket left the yard soon after the Borssele Alpha […]

  • 20 March 2020
    Grid Connection

    The Borssele Beta offshore substation topside will sail out from HSM Offshore’s yard in Schiedam to the installation site in the Dutch North Sea on 22 March, TenneT said. The 700MW offshore grid connection is scheduled to be operational on September 1. From then on, the 731.5MW Borssele III and IV wind farm that is […]

  • 29 November 2018
    Business & Finance, Grid Connection

    The France-headquartered Vallourec is supplying structural tubes for the Borssele Alpha and Beta offshore transformer stations in the Dutch North Sea.

  • 4 September 2019
    Grid Connection

    Dutch transmission system operator TenneT inaugurated the 700MW Borssele Alpha offshore high voltage substation on Thursday, 5 September. The final piece for the completion of the Borssele Alpha project was the certification provided by DNV GL, TenneT said. The Borssele Alpha will collect the electricity generated at Ørsted’s soon to be built Borssele 1 + 2 offshore […]

  • 10 May 2019
    Grid Connection

    The topside for the Borssele Alpha substation has departed from HSM Offshore in Schiedam towards the project site in the Dutch North Sea. The topside will travel through the Nieuwe Waterweg and Hoek van Holland where it will enter the North Sea. Upon arrival to the project site, it will be placed onto its jacket foundation, […]

  • 27 March 2017
    Grid Connection, Wind Farm Update

    The governments of Flanders and the Netherlands have reached an agreement on the Borssele subsea cables that will run through the Western Scheldt (Westerscheld), the estuary of the Scheldt river and an important shipping route for the Belgian Port of Antwerp.

  • 21 July 2017
    Contracts & Tenders, Grid Connection, Technology, Wind Farm Update

    In October, Australian company Gap Explosive Ordnance Detection (EOD) will deliver a new system for detection of unexploded ordnance (UXO) to Boskalis, recently contracted together with Fugro to survey and identify UXO along the cable routes for the planned grid connection between TenneT’s two offshore platforms and its high-voltage substation onshore.

  • 14 February 2017
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Dutch transmission systems operator TenneT TSO B.V. has awarded a contract to the Schiedam-based HSM Offshore for the construction of offshore transformer stations required to link up the wind farms to be built offshore at Borssele in the south-west of the Netherlands. The contract concerns the offshore platform for the Borssele Alpha wind farm zone. […]

  • 13 May 2019
    Grid Connection

    The second cable that will connect the Borssele Alpha offshore high voltage substation in the Dutch North Sea to the transformer station at Borssele has made landfall, according to TenneT. Boskalis Subsea Cables & Flexibles, former VBMS, and NKT are in charge of supplying, delivering and installing two 61km long export cables for the Borssele Alpha […]

  • 30 April 2019
    Grid Connection, Wind Farm Update

    HSM Offshore has loaded out the Borssele Alpha substation topside onto a barge at its yard in Schiedam, the Netherlands. The 700MW Borssele Alpha will collect the electricity generated by Ørsted’s Borssele 1 + 2 offshore wind farm and feed it into the Dutch grid. The substation’s jacket foundation was installed in August 2018. The platform […]

  • 9 May 2019
    Grid Connection

    The topside for the Borssele Alpha substation will set sail from HSM Offshore towards the project site on Friday, 10 May, according to TenneT. The topside will begin its journey from HSM Offshore’s site in Schiedam at around 7:30 a.m. local time and will travel via the Nieuwe Waterweg and Hoek van Holland where it will […]

  • 7 August 2018
    Grid Connection

    Seaway Heavy Lifting’s vessel Oleg Strashnov has installed the jacket foundation for TenneT’s Borssele Alpha offshore transformer station in the Dutch North Sea.

  • 15 April 2019
    Grid Connection

    The first cable that will connect the Borssele Alpha offshore high voltage substation in the Dutch North Sea to the transformer station at Borssele has made landfall, TenneT said. On Friday, 12 April, Boskalis started to pull in the sea cable on land and early Saturday morning the cable reached the newly built transformer station. […]