  • 29 April 2020
    Wind Farm Update

    Ørsted’s Borssele 1 & 2 offshore wind farm has delivered first power to the Dutch grid. According to the Danish company, the first Siemens Gamesa 8 MW turbine began producing electricity on 28 April. “This is a big milestone for Borssele 1 & 2. Ørsted is doing its utmost to allow the construction of the […]

  • 22 April 2020
    Contracts & Tenders, Ports & Logistics

    Dutch offshore wind services provider Gould has secured contracts for work on the wind farms in the Borssele zone. Van Oord has selected Gould to act as their key logistic hub for the Borssele Ill and IV offshore wind farm. For this, Van Oord will make use of Gould’s offshore service base in Vlissingen. The […]

  • 10 April 2020
    Wind Farm Update

    DEME has installed half of the 94 monopile foundations at the Borssele 1+2 offshore wind farm site.

  • 9 April 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME’s jack-up Sea Challenger is en route to the Borssele 1 + 2 offshore wind farm in the Dutch North Sea loaded with the first batch of wind turbine components. As reported earlier, Sea Challenger loaded the turbine components at the Port of Esbjerg in Denmark. Owned and developed by Ørsted, the 752 MW Borssele 1 […]

  • 7 April 2020
    Grid Connection

    The Borssele Beta offshore substation topside has been installed at the project site in the Dutch North Sea. The topside sailed out from HSM Offshore’s yard in Schiedam at the end of March to the site but was awaiting favorable weather conditions to be installed. Borssele Beta will connect the 731.5 MW Borssele III and […]

  • 30 March 2020
    Grid Connection

    The Borssele Beta offshore substation topside has sailed out from HSM Offshore’s yard in Schiedam to the installation site in the Dutch North Sea, TenneT said. The 700MW offshore grid connection is scheduled to be operational on September 1, the Dutch transmission system operator said. Borssele Beta will connect the 731.5MW Borssele III and IV […]

  • 27 March 2020
    Wind Farm Update

    FairWind has completed the electrical installation of 59 transition pieces for the Borssele 1+2 offshore wind farm for Bladt Industries. The project scope included mounting circuit breakers, lights, cabling, filling high voltage switchgear with liquid air, and all other electrical components. The TP segments were assembled in Aalborg harbor, Denmark, before installation at the 752MW wind […]

  • 20 March 2020
    Grid Connection

    The Borssele Beta offshore substation topside will sail out from HSM Offshore’s yard in Schiedam to the installation site in the Dutch North Sea on 22 March, TenneT said. The 700MW offshore grid connection is scheduled to be operational on September 1. From then on, the 731.5MW Borssele III and IV wind farm that is […]

  • 17 March 2020
    Wind Farm Update

    Bladt Industries A/S has loaded out the last six transition pieces and anode cages for the Borssele 1 & 2 offshore wind farm project in the Netherlands. Bladt Industries’ scope covered the manufacture of 59 transition pieces, each one weighing approximately 390 tonnes, with a diameter of up to 6 metres and a length of […]

  • 10 March 2020
    Grid Connection

    HSM Offshore has loaded out the Borssele Beta offshore substation topside at its yard in Schiedam, the Netherlands. The 700MW Borssele Beta high voltage substation will connect the 731.5MW Borssele 3 & 4 wind farm to the Dutch grid. The substation’s jacket foundation, also built by HSM Offshore, was installed at the site off Zeeland in May 2019. The […]

  • 6 March 2020
    Grid Connection

    HSM Offshore B.V. has appointed Rhenus Offshore Logistics B.V. for the commissioning logistics of the Borssele Beta offshore high voltage substation. The 700MW Borssele Beta will connect the Borssele 3 & 4 offshore wind farm to the Dutch grid. Offshore construction on the 731.5MW project started in October 2019, with the commissioning scheduled for 2021. HSM Offshore rolled out […]

  • 5 March 2020
    Wind Farm Update

    ProCon Wind Energy has completed the electrical construction of 35 transition pieces for the Borssele 1 & 2 offshore wind project at EEW Offshore Structures (Britain) Ltd. ProCon stated that all its tasks have been finished and now only an O&M manual remains for total completion. The company has been providing electrical pre-assembly, installation and […]

  • 13 February 2020
    Vessels, Wind Farm Update

    DEME Offshore’s jack-up Innovation has installed 18 out of 94 monopile foundations on the 752MW Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation is loading the monopiles and the transition pieces at Sif’s facility on Maasvlakte 2 in Rotterdam and installing them at the site some 22 kilometres off the coast of […]

  • 28 January 2020
    Contracts & Tenders, Wind Farm Update

    Ørsted has contracted Manor Renewable Energy (MRE) to provide temporary power during the turbine commissioning phase at the Borssele 1 + 2 offshore wind project.

  • 13 January 2020
    Wind Farm Update

    DEME Group has installed the first foundations at Ørsted’s Borssele 1&2 offshore wind project in the Netherlands. DEME’s jack-up vessel Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 earlier this month and transported them to the wind farm. “The first monopile installed was also the heaviest and tallest on the wind farm, […]

  • 9 January 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has loaded the first set of monopiles to be installed on the Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 in the Port of Rotterdam. DEME is in charge of transporting and installing the 94 monopile […]

  • 9 December 2019
    Wind Farm Update

    Bladt has completed the second load out of transition pieces for the Borssele 1+2 offshore wind project in the Netherlands. According to the company, the second load out of the 26m tall transition pieces took place last week. Ørsted’s Borssele 1+2 will comprise 94 Siemens Gamesa 8MW turbines installed some 23km off the coast of […]

  • 4 December 2019
    Wind Farm Update

    EEW Offshore Structures (Britain) has carried out the final Test on Completion for Ørsted’s Borssele contract. The Teesside-based company was tasked with manufacturing and delivering a total of 35 transition pieces for the 752MW Borssele 1 + 2 wind farm in the Dutch North Sea. ALE Heavy Lift is providing the transportation services which are […]

  • 3 December 2019
    Wind Farm Update

    SAL Heavy Lift’s multi-purpose cargo ship Svenja has arrived at the Redcar Bulk Terminal, the UK, to pick up the third batch of transition pieces for the Borssele 1+2 offshore wind project. Svenja is picking up six transition pieces, which were produced by EEW Offshore Structures Britain (OSB) and barged down to the Redcar terminal […]

  • 2 December 2019
    Grid Connection

    HSM Offshore BV has rolled out the topside for the Borssele Beta offshore high voltage substation at its yard in Schiedam, the Netherlands. Once completed in 2020, the 700MW Borssele Beta will connect the 731.5MW Borssele 3 & 4 wind farm to the Dutch grid. The offshore construction on the wind farm started in October […]

  • 22 October 2019
    Wind Farm Update

    EEW Offshore Structures Britain (OSB) has completed the load-out of the first six transition pieces built for the Borssele 1+2 offshore wind farm in the Dutch North Sea. The Teesside-based company will manufacture and deliver a total of 35 transition pieces for Ørsted’s 752MW wind farm. ALE Heavy Lift is providing the transportation services. Denmark’s Bladt […]

  • 16 October 2019
    Vessels

    Ørsted has signed a contract with CWind for the delivery of a hybrid-powered Surface Effect Ship (SES) for the Borssele 1 & 2 offshore wind project. The hybrid SES crew transfer vessel (CTV) will be operating from the Dutch port of Vlissingen to the Borssele 1 & 2 site located 23km from the coast in the […]

  • 27 August 2019
    Ports & Logistics, Wind Farm Update

    Sif Holding has entered into an agreement with DEME Offshore to use Maasvlakte 2 in the Netherlands for marshaling services for the Borssele 1 & 2 offshore wind project. The deal comes as Sif agreed with the Port of Rotterdam on the lease of an additional 20ha of industrial land, adjacent to the company’s existing operations at […]

  • 27 May 2019
    Wind Farm Update

    The first external platform produced by Energomontaż-Północ Gdynia (EPG) for the 731.5MW Borssele 3 & 4 wind farm is ready for final outfitting, the Polish manufacturer said. In total, EPG will manufacture and deliver 76 external platforms for the project in the Dutch North Sea. The Borssele 3 & 4 wind farm is being developed by the Blauwwind […]

  • 13 May 2019
    Grid Connection

    The second cable that will connect the Borssele Alpha offshore high voltage substation in the Dutch North Sea to the transformer station at Borssele has made landfall, according to TenneT. Boskalis Subsea Cables & Flexibles, former VBMS, and NKT are in charge of supplying, delivering and installing two 61km long export cables for the Borssele Alpha […]

  • 10 May 2019
    Grid Connection

    The topside for the Borssele Alpha substation has departed from HSM Offshore in Schiedam towards the project site in the Dutch North Sea. The topside will travel through the Nieuwe Waterweg and Hoek van Holland where it will enter the North Sea. Upon arrival to the project site, it will be placed onto its jacket foundation, […]