  • 29 January 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Heerema Fabrication Group (HFG) has been awarded a contract by Petrofac for the procurement and construction of the jacket and piles for the 900 MW BorWin3 HVDC platform. Petrofac, in a consortium with Siemens, has the full responsibility for the construction and offshore installation of the BorWin3 platform of TenneT, which will house a Siemens HVDC station […]

  • 20 August 2019
    Grid Connection

    The BorWin3 offshore wind grid connection in the German North Sea has started transmitting power. According to Petrofac, the 900MW project has begun converting three-phase electric power generated by offshore wind farms into direct current and transmitting it 160km back to shore into the German national grid. “We are delighted to have reached this key milestone with […]

  • 28 May 2018
    Grid Connection

    The jacket foundation for the 900MW BorWin3 offshore grid platform has been installed in the North Sea, nearly 130 kilometres off the German coast, Petrofac said.

  • 13 August 2019
    Grid Connection

    TenneT has commissioned the 900MW BorWin3 offshore grid platform in the German North Sea. BorWin3 will connect the 497MW EnBW Hohe See and the 400MW Global Tech I offshore wind farms to the German grid. It represents TenneT’s twelfth offshore wind project and takes the company’s offshore transmission capacity in the North Sea to more than 7GW, […]

  • 16 February 2015
    Business & Finance, Grid Connection, R&D, Wind Farm Update

    DC Netz BorWin3 GmbH has awarded a contract to N-Sea Offshore Wind BV to undertake unexploded ordnance (UXO) surveys at BorWin3 site.  Specifically, the work covers surveying of the seabed to help the identification and removal of undiscovered ordnance along the cable route of BorWin3. The planned BorWin3 submarine cable connection is a DC power transmission link with a […]

  • 20 May 2016
    Grid Connection

    A foundation stone for the land-based converter station, which is part of the BorWin3 grid connection project, was laid yesterday. At the converter station’s Emden / East site, a time capsule with coins, national newspaper and building plans was taken into the ground and thus marked the groundbreaking ceremony. With the BorWin3 project a high voltage direct current (HVDC) […]

  • 9 May 2018
    Grid Connection, Ports & Logistics

    Heerema Fabrication Group (HFG) has shipped out the jacket foundation for TenneT’s 900MW BorWin3 HVDC platform.

  • 7 October 2016
    Grid Connection

    Transmission systems operator TenneT and Siemens have held a topping-out ceremony for the Emden/Ost converter station, part of the 900MW BorWin3 grid connection project. The land station Emden/Ost is an essential element for the grid connection of offshore wind farms, TenneT said. With the BorWin3 project a high voltage direct current (HVDC) transmission will be realized […]

  • 7 February 2017
    Grid Connection

    The transformer for TenneT’s substation, which will collect and distribute the electricity from the BorWin3 offshore grid connection, has been transported on Saturday from the seaport in Emden to the site at Emden/Ost in the northwest of Germany.

  • 15 May 2018
    Grid Connection

    The jacket foundation for TenneT’s 900MW BorWin3 HVDC platform has been installed in the German North Sea.

  • 14 May 2019
    Grid Connection

    Corrosion Protection Consult GmbH has signed a contract to provide corrosion protection inspection on the BorWin gamma converter station in the German North Sea. The contract started recently and is expected to be completed by the end of June. The scope of work includes monitoring and inspection of the coating works at the newly installed converter […]

  • 13 October 2014
    Grid Connection

    Drydocks World has signed an agreement with Petrofac to build the BorWin3 high voltage direct current (HVDC) converter platform in the North Sea, named BorWin gamma. When completed, this will provide an essential renewable offshore resource to meet increasing energy demands. Drydocks World has successfully secured the contract for the fabrication, commissioning and load out […]

  • 20 August 2018
    Contracts & Tenders

    Petrofac has hired SeaRenergy to support the hook-up and commissioning of TenneT’s 900MW BorWin3 HVDC platform (BorWin Gamma), once the topside is installed on top of its foundation already in place at the site off Germany.

  • 4 April 2013
    Contracts & Tenders, Grid Connection

    DC Netz BorWin3 GmbH is inviting tenders for offshore electrical distribution related to BorWin3. The invited tenders are for transmission system of electric power (approximately 900 MW) between the offshore wind farms in the cluster BorWin and a grid connection point on land. In particular, the transmission power, the losses, the availability and compliance with […]

  • 13 February 2020
    Grid Connection

    Siemens and Petrofac have handed over the 900MW BorWin3 offshore grid connection system in the German North Sea to TenneT. The grid link was handed over following several weeks of testing, and TenneT has now taken over the maintenance and operation of the connection. The link was commissioned in August 2019. Siemens was responsible for […]

  • 15 April 2014

    Prysmian Group has been awarded a major project worth in excess of € 250 million by the Dutch-German grid operator TenneT for the grid connection of offshore wind farms in Germany. The project involves supply, installation and commissioning of a High Voltage Direct Current (HVDC) 320 kV extruded submarine and land power bipole connection with […]

  • 10 March 2017
    Business & Finance, Grid Connection, Wind Farm Update

    Transmission System Operator TenneT has awarded the Chinese power cables manufacturer ZTT with a contract to supply and construct a 155kV HVAC grid connection between the 497MW EnBW Hohe See offshore wind farm and the 900MW BorWin3 DC grid connection system in the North Sea.

  • 12 July 2017
    Grid Connection, Wind Farm Update

    Chinese power cable manufacturer ZTT has contracted SeaRenergy to provide QHSE management & support for the HVAC export cable connection between the BorWin gamma platform and the 497MW EnBW Hohe See wind farm in the German North Sea.

  • 29 August 2014
    Environment, Grid Connection

    Grid operator in Germany, TenneT, is seeking contractor to conduct an unexploded explosive ordnance (UXO) survey, identification and removal on the cable route BorWin3 in the German sector of the North Sea. The planned BorWin3 submarine cable connection is a DC power transmission link with a length of 130 km. Landfall is at Hamswehrum in […]

  • 12 February 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Bayreuth-based TenneT TSO GmbH has, via DC-Netz BorWin3 GmbH, issued a tender for a supplier of an AC submarine cable to link an offshore wind farm in the German North Sea to the grid connection system. The tender calls for manufacture, supply and installation of the subsea cable in the Cluster 8 of the German Exclusive Economic Zone, including […]

  • 8 October 2018
    Grid Connection

    The BorWin gamma topside has completed its journey from Dubai to the installation site in the German North Sea, TenneT reports.

  • 16 August 2017
    Grid Connection, Vessels

    Prysmian’s cable laying vessel Cable Enterprise is getting ready to install the next section of the 130-kilometre subsea cable link which will connect the 900Mw BorWin3 offshore station to the German grid.

  • 11 September 2018
    Grid Connection, Ports & Logistics

    The BorWin gamma topside has started its journey from the Drydocks World – Dubai to the German North Sea.

  • 30 April 2012
    Contracts & Tenders, Grid Connection

    German wind farm developer, DC Netz BorWin3 GmbH is inviting tenders for installation of a system for the transmission of electrical energy (about 900 MW) between offshore wind farms in the BorWin clusters and a network connection point on land. In particular, the transmission power, the losses, the availability and compliance with the Grid Code […]

  • 29 January 2015
    Business & Finance, Grid Connection, Vessels

    TenneT  is on the market for a contractor for the provision of maritime consulting and support services for offshore installation projects in North Sea and Wadden Sea. The contract covers supervision of marine construction projects, primarily submarine cable laying, and provision of a vessel. Additionally, the contractor will be in charge of supervising the construction […]

  • 26 April 2018
    Business & Finance, Grid Connection, Operations & Maintenance, Technology, Wind Farm Update

    Tekmar Energy has won multiple contracts by Van Oord to supply its Cable Protection Systems (CPS) for the Deutsche Bucht offshore wind farm and the BorWin3 grid connection system in the German North Sea.