  • 14 January 2015
    Wind Farm Update

    With EnBW Baltic 2 in the Baltic Sea, about 32 kilometers north of Rügen, one of the largest offshore wind farms in Germany is under construction at the moment.  At the same time, EnBW is building a service station on the land of the Kraftwerks Rostock. When the wind farm goes into operation, service deployments will be […]

  • 23 May 2014

    Bladt Industries, an international steel contractor, has erected the first out of 41 Baltic 2 offshore wind farm jackets at its Lindoe construction site. Last year, the company received an order from ARGE Baltic 2 Foundations, a joint venture between HOCHTIEF Offshore Crewing, HOCHTIEF Solutions AG and GeoSea NV, who are responsible for the design, […]

  • 19 August 2014
    Wind Farm Update

    A barge that sank on Wednesday morning (August 13) off Darßer Ort in the Baltic Sea was carrying four working platforms for the EnBW Baltic 2 offshore wind farm, the company confirmed to Offshore WIND.  “We are still examining the impact and we cannot make a statement yet,” EnBW’s spokeswoman said. She added that the platforms will […]

  • 7 June 2023
    Business development, Industry

    A new report from Invest in Pomerania, a Polish investment promotion initiative in the Pomerania region, has been published with a focus on the region’s maritime sector and, within it, the region’s growing offshore wind industry and supply chain capabilities have taken centre stage. “When we decided that the subject of the next FOCUS ON […]

  • 1 June 2022
    Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Vessels

    EnBW has selected Njord Offshore and FRS Windcat Offshore Logistics to provide crew transfer vessels (CTVs) that will operate on the Baltic 1 and the Baltic 2 offshore wind farms in the German Baltic Sea. Njord Offshore will provide two 12-PAX CTVs for each of the wind farms, and FRS Windcat will supply one 18-PAX […]

  • 30 April 2014
    Grid Connection, Wind Farm Update

    The work on the cable connection of the EnBW Baltic 2 offshore wind farm to the grid is progressing at full speed off the Baltic coast of the German Federal State of Mecklenburg-Vorpommern. More than half of the project’s cables are now lying on the seabed. A total of sixty kilometers of submarine cables will […]

  • 25 June 2013

    Since 3 June 2013, AMBAU GmbH has been constructing 41 transition pieces to be used for the jackets at the “EnBW Baltic 2” wind farm on commission from Bladt Industries A/S. In April 2013, Bladt Industries announced that it had received an order to construct the 41 jackets to be installed in water depths of […]

  • 23 November 2011
    Grid Connection

    EnBW has commissioned a consortium consisting of the WeserWind and Alstom to build the substation for Baltic 2 offshore wind farm. Wind farm will consist of 80 Seiemens’ 3,6MW wind turbines located 32 km north of the island Rügen. Alstom will be in charge of electrical construction and Weser Wind in charge of steel construction. […]

  • 11 January 2013
    Business & Finance

    The European Investment Bank (EIB) has granted a loan of € 500 million to the largest offshore wind farm to date in the German Baltic Sea; EnBW Baltic 2. The project is being realised by EnBW Erneuerbare Energien GmbH. The financing contract was signed today in Karlsruhe. The position and scale of EnBW Baltic 2 […]

  • 5 June 2014
    Wind Farm Update

    Offshore WIND’s photo of the day: Large component for offshore wind farm EnBW Baltic 2 come in the port of Sassnitz. Located 32 kilometres north of the Baltic Sea island of Rügen, this wind farm will consist of 80 wind power plants with a total output of 288 MW. Baltic 2 will produce enough electricity […]

  • 8 October 2013

    A new rescue helicopter was commissioned into service for the Baltic 2 offshore wind project yesterday (October 7) at the airport in Güttin (Vorpommern-Rügen district). The Eurocopter BK 117 helicopter is specially equipped for rescue operations at sea. The network operator 50 Hertz and the wind turbine manufacturer EnBW are covering the hiring costs for […]

  • 26 March 2013
    Environment

    MMT (Sweden) has been appointed by Siem Offshore Contractors GmbH to conduct a pre lay survey and ROV inspection of the IAG at the Baltic 2 Offshore Wind Park. This project is now ongoing and MMT uses the survey & ROV vessel IceBeam, equipped with a Kongsberg EM2040 Dual Head Multibeam and a Sub-Atlantic Mohican […]

  • 27 March 2013
    Grid Connection

    Ballast Nedam has signed a contract for the installation of foundations at the German EnBW Baltic 2 offshore wind farm with ARGE BALTIC 2 Foundations, a joint venture between HOCHTIEF Solutions AG, GeoSea N.V. and HOCHTIEF Offshore Crewing GmbH. Ballast Nedam will erect the project’s 39 monopile and transition piece foundations and provide the logistics […]

  • 28 January 2015
    Wind Farm Update

    Offshore WIND’s photo of the day: Last of the total 41 jacket foundations for the EnBW Baltic 2 offshore wind farm leaving Bladt Industries site in Denmark.  A little over a week ago, Bladt carried out the load out of these foundations and wrapped up the work that started in May last year. This job enabled the company to […]

  • 18 June 2015
    Business & Finance, Wind Farm Update

    Dutch pension fund manager PGGM is taking part in the new German offshore wind farm Baltic 2. PGGM will invest in the project alongside Macquarie Capital, who agreed to acquire a 49.89 percent stake in the project earlier this year.   This investment is in line with the ambition of PGGM’s clients to use pension money […]

  • 29 August 2013
    Wind Farm Update

    Bladt’s new facilities at Lindø Industrial Park are nearly all set and the production of the 41 jackets for ENBW Baltic 2 offshore wind farm is well under way. At the moment, almost 100 men are in full swing in the workshops where they have spent the last months preparing these with the so called […]

  • 4 April 2013
    Wind Farm Update

    PALFINGER WIND is now equipping the Baltic 2 wind farm in the German Baltic Sea with 80 cranes of type PS 23500 M. With this order for EnBW, PALFINGER WIND is now acting as supplier to three of Germany’s largest energy suppliers. Baltic 2 will generate a total output of 288 MW with 80 wind […]

  • 18 April 2013

    After already manufacturing the foundations for the OWF EnBW Baltic 1, EEW Special Pipe Constructions GmbH has now also been appointed with the delivery of 123 Pin Piles (Lot 2) as well as 39 Monopiles and Transition Pieces (Lot 3) for EnBW Baltic 2. The MPs/TPs will be manufactured in a joint venture with Bladt […]

  • 6 June 2023
    Contracts & Tenders, Grid Connection

    NKT has announced that it is finalising the power cable contract for the 1.2 GW Baltic Power offshore wind farm in Poland. For NKT, the order is expected to have a value of more than EUR 120 million (more than EUR 110 million in std. metal prices) and will comprise the design and production of […]

  • 18 November 2011

    Karlsruhe based publicly traded electric utilities company, EnBW, is looking for contractor for monitoring during the construction of offshore wind farms ‘EnBW Baltic 2’, including all necessary logistical and technical services. The scope of investigations are related to sediment and habitat structures, habitat use, hydrographic, benthos, fish, marine fauna (continual users and migration movements), marine […]

  • 9 August 2011

    nkt cables has entered into a contract with 50Hertz Offshore GmbH at a value of around 750 mDKK (95 mEUR) for the offshore wind farm Baltic 2. For nkt cables, Baltic 2 will be another turnkey project which includes armoured high-voltage subsea cables, accessories and installation. The cables will be manufactured at the production facilities […]

  • 20 December 2021
    Contracts & Tenders, Operations & Maintenance, Vessels

    EnBW is on the lookout for crew transfer vessels (CTVs) to be deployed at the company’s offshore wind farms in the German Baltic Sea. EnBW is in need of three CTVs to transfer technicians and cargo to and from the Baltic 1 and the Baltic 2 offshore wind farms on a daily basis. The bidders […]

  • 8 October 2013

    Ilsenburger Grobblech GmbH (ILG) and Salzgitter Mannesmann Grobblech GmbH (MGB), both member companies of the Salzgitter Group, will be delivering a total of 44,150 tons of plate, which is the major share of the material required for the steel tube constructions of the Baltic 2 offshore wind farm. Siemens and EEW Special Pipe Constructions are […]

  • 31 March 2014
    Business & Finance, Technology

    ESG Edelstahl und Umwelttechnik Stralsund GmbH will begin the construction of a transport structure intended for rotor blades of offshore wind turbines for EnBW Baltic 2 GmbH in April 2014. Specialist company ESG will build the so-called “Blade Rack System” at the Volkswerft shipyard in Stralsund within two months. The system will then be mounted […]

  • 19 December 2011
    Wind Farm Update

    EnBW Renewables GmbH has offered a briefing to public utilities and industrial companies, to participate in its second offshore wind farm EnBW Baltic 2. 19 municipal utilities had already participated in the first offshore wind farm Baltic EnBW 1. Stefan Thiele, CEO of EnBW Renewables GmbH, said that the completed financing for EnBW’s Baltic 1 […]

  • 23 January 2020
    Contracts & Tenders, Grid Connection

    German transmission system operator (TSO) 50Hertz has awarded Heinrich Hirdes GmbH, a subsidiary of Boskalis, with a contract to provide backfilling of the subsea cable routes on the Baltic 1 and Baltic 2 grid connections. The services relate to the entire project period. In designated areas along the affected submarine cable routes, the coverage of […]