  • 7 September 2016

    Iberdrola will today place an order with Navantia and Windar Renovables for a portion of jacket foundations that will hold Siemens 7MW wind turbines at the East Anglia ONE wind farm in the UK, according to Spanish media.  Iberdrola had split the construction of 102 foundations into three lots, with the awardees producing 28, 34 and 40 3-legged jacket foundations, and […]

  • 6 December 2016
    Wind Farm Update

    ScottishPower Renewables will kick off the pre-construction activities for East Anglia ONE in January 2017. Iberdrola Engineering & Construction has been appointed to undertake engineering design and is the Principle Contractor for the pre-construction and construction works. From January, work along the 37km onshore cable route, from Bawdsey to Bramford, will be carried out to […]

  • 1 March 2016

    ScottishPower Renewables (SPR) has agreed a 2016 sponsorship agreement with the East of England Energy Group (EEEGR) for five important industry events in East Anglia this year. The deal comes on the back of ScottishPower Renewables’ final investment decision for the East Anglia ONE offshore wind farm, which will see the £2.5 billion project go […]

  • 17 May 2018
    Vessels

    Wind farm installation vessel Seajacks Scylla is set to begin working on the East Anglia One offshore wind farm at the end of July or the beginning of August, a spokesperson on behalf of Seajacks told Offshore WIND.

  • 25 April 2016
    Business & Finance

    Sembmarine SLP hopes it will win a contract for the offshore substation for the East Anglia ONE offshore wind project.  At an event celebrating the completion and delivery of the offshore substation for the Dudgeon offshore wind farm, the company issued a rallying campaign call to the East of England energy industry. Paul Thomson, managing director […]

  • 18 October 2019
    Operations & Maintenance, Ports & Logistics

    ScottishPower Renewables has opened the new operations and maintenance building for the 714MW East Anglia ONE offshore wind farm at the Port of Lowestoft, UK. Located at Associated British Port’s Hamilton Dock, the O&M building is part of a GBP 25 million investment made by ScottishPower Renewables into the Port of Lowestoft. The site is now the […]

  • 17 January 2017
    Vessels, Wind Farm Update

    Van Oord and Seajacks have been awarded contracts to install the jacket foundations at the East Anglia ONE offshore wind farm, with the main installation vessel being the Seajacks Scylla.

  • 4 July 2018
    Wind Farm Update

    Navantia has completed the construction of the East Anglia ONE offshore substation (topside), which is scheduled to set sail from the shipyard at Puerto Real in Spain in early August and arrive at the UK construction site in early September. 

  • 22 May 2018
    Contracts & Tenders, Technology

    Fern Communications has won a contract to provide its radio communication system during the construction of ScottishPower Renewables’ East Anglia One offshore wind farm.

  • 16 December 2019
    Contracts & Tenders, Operations & Maintenance

    ScottishPower Renewables has awarded James Fisher Marine Services (JFMS) with a contract to provide scheduled maintenance at the East Anglia One offshore wind project. Under the GBP 5.6 million contract, JFMS will provide scheduled and corrective maintenance to the wind farm, with work including statutory inspections, equipment maintenance and structural integrity checks for components. The […]

  • 5 June 2015
    Business & Finance, Wind Farm Update

    ScottishPower Renewables has selected Siemens as its preferred turbine supplier for the East Anglia ONE offshore wind farm. The turbine agreement, which will be the largest individual contract placed as part of the £2 billion project, will see up to 102 of Siemens’ 7 megawatt (MW) turbines supplied. As part of the agreement, Siemens will use […]

  • 14 March 2018
    Vessels, Wind Farm Update

    UK and Netherlands-based subsea provider N-Sea is part-way through a multi-million-pound unexploded ordnance (UXO) clearance campaign for ScottishPower Renewables on the 714MW East Anglia ONE offshore wind farm.

  • 6 September 2017
    Contracts & Tenders, Vessels, Wind Farm Update

    Lamprell Energy Ltd. has awarded Dockwise, a wholly-owned subsidiary of Royal Boskalis Westminster N.V., with a contract to transport jacket foundations for the 714MW East Anglia ONE offshore wind farm from the United Arab Emirates to the Netherlands. 

  • 18 July 2019
    Wind Farm Update

    Van Oord has installed the last jacket foundation on the East Anglia ONE offshore wind farm and delivered it to client ScottishPower Renewables. This marks the marine contractor’s completion of its work for this 714MW UK wind project. As the main contractor, Van Oord transported and installed all 102 foundations. This is the largest number […]

  • 1 July 2012
    Grid Connection

    East Anglia Offshore Wind (EAOW), a joint venture owned 50:50 by ScottishPower Renewables and Vattenfall, is holding a second series of consultations regarding the required onshore work for East Anglia ONE, an offshore wind farm 43km off the coast of Suffolk. East Anglia ONE will consist of up to 325 offshore wind turbines to provide an […]

  • 7 July 2015

    ScottishPower Renewables and East of England Energy Group (EEEGR) will deliver a Supply Chain Event specifically focusing on the East Anglia ONE offshore wind project. The event will be held on Thursday, 16th July, at Norwich City Football Club. It will provide local companies with more information on the scope of work to be carried out, explain how they can […]

  • 4 May 2020
    Business & Finance, Wind Farm Update

    The second phases of the East Anglia One and Hornsea One offshore wind projects in the UK have begun receiving payments under their Contracts for Difference (CfDs). This means that 285 MW from East Anglia One and 400 MW from Hornsea One have passed their Operational Conditions Precedent (OCPs) and achieved a confirmed start date on […]

  • 11 February 2019
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    Siemens Gamesa has contracted wind turbine installation and service company Global Wind Service (GWS) to assemble all 102 towers for the East Anglia ONE offshore wind farm in the UK. The towers will be assembled at the Norfolk port of Great Yarmouth ahead of their load-out and installation offshore as part of the wind farm […]

  • 14 March 2022
    Authorities, Wind Farm Update

    The decision on the development consent applications for East Anglia One North and East Anglia Two offshore wind farms is scheduled to be made on 31 March, after the UK Secretary of State for Business, Energy and Industrial Strategy set a new deadline in December 2021. The new Development Consent Order (DCO) deadline was set after […]

  • 3 April 2019
    Contracts & Tenders, Wind Farm Update

    Dutch high voltage offshore wind specialist Visser & Smit Hanab has been awarded the contract to perform all array cable terminations and testing work at the East Anglia One wind farm. The scope of the work entails the 66kV array cable terminations in all 102 turbines, as well as the installation of the custom-designed cable […]

  • 17 December 2012
    Authorities, Wind Farm Update

    Planning application for East Anglia ONE offshore wind farm has been submitted by East Anglia Offshore Wind (EAOW), a joint venture between Vattenfall and ScottishPower Renewables, EADT24 news site reports. National Infrastructure Directorate will now consider the planning application and, if approved, the onshore construction part could begin in 2016 and offshore work could begin […]

  • 24 December 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    UK energy market regulator Ofgem has named Transmission Capital Partners the preferred offshore transmission owner (OFTO) for the 714 MW East Anglia ONE offshore wind farm. Transmission Capital Partners is a consortium of Transmission Capital Partners Limited Partnership and International Public Partnerships Limited. Prior to becoming a successful OFTO bidder, Transmission Capital Partners needs to […]

  • 6 April 2018
    Contracts & Tenders, Vessels, Wind Farm Update

    Lowestoft-based crew transfer vessels (CTV) operator Turner Iceni has been awarded a contract exceeding GBP 4 million by ScottishPower Renewables to provide support for the construction of the East Anglia ONE offshore wind farm.

  • 16 January 2019
    Business & Finance, Ports & Logistics

    Peterson Offshore Passenger Terminal in the Netherlands has marked its 100th flight, which departed for the UK East Anglia One offshore wind project. The milestone flight, which took off on 3 January, is part of a contract that German helicopter operator Northern HeliCopter (NHV) secured for supporting the 714MW offshore wind farm. According to Peterson Terminal, […]

  • 19 November 2015
    Business & Finance, Operations & Maintenance, R&D, Technology, Wind Farm Update

    ScottishPower Renewables has agreed on a GBP 25 million, thirty-year deal with the Port of Lowestoft to act as a construction and operations hub for the East Anglia ONE offshore wind farm. Following discussions with Associated British Ports, ScottishPower Renewables will utilise the Port of Lowestoft as its construction management base for East Anglia ONE, […]

  • 26 January 2017
    Contracts & Tenders, Wind Farm Update

    ScottishPower Renewables and the Dutch BOW Terminal Vlissingen have signed an agreement for foundations marshalling yard services for the 714MW East Anglia One project. The agreement relates to the provision of up to 12-14ha for the storage of the project foundations. The foundations consist of a total of 102 jackets and 306 pinpiles. The maximum […]