  • 16 June 2021
    Business & Finance, Wind Farm Update

    Parkwind has reached financial close on the Arcadis Ost 1 offshore wind farm, its first project in Germany, which now officially enters construction phase. Belgian offshore wind developer said the project raised about EUR 570 million of debt from a group of nine lenders. The lenders are KBC Bank, Belfius Bank, Helaba, KfW IPEX-Bank, Coöperatieve […]

  • 18 September 2019
    Contracts & Tenders

    Parkwind has awarded COWI with a contract to design the foundations for the turbines and offshore substation of the Arcadis Ost 1 offshore wind farm in Germany. COWI’s Hamburg office is in charge of the geotechnical design, loads calculations, primary and secondary steel design, limit state verification, and all activities pertaining to the approval of the design. According […]

  • 3 April 2023
    Vessels, Wind Farm Update

    Heerema Marine Contractors, using its giant crane vessel Thialf, has installed 24 Vestas 9.5 MW turbines at the Arcadis Ost 1 offshore wind farm in Germany. The installation of the three remaining units is now scheduled for Autumn. Offshore construction at the project site in the Baltic Sea began in June 2022 with the installation […]

  • 2 March 2022
    Wind Farm Update

    The first three XXL monopiles for the 257 MW Arcadis Ost 1 offshore wind farm have set sail from Steelwind Nordenham’s fabrication plant to the Port of Roenne, the marshalling harbor for the project. Located northeast of the island of Rügen in German Baltic Sea, Arcadis Ost 1 comprises 27 wind turbines and one offshore […]

  • 13 July 2023
    Authorities, Business & Finance, Business development, Research & Development

    The European Climate, Infrastructure and Environment Executive Agency (CINEA) has approved a EUR 18.7 million co-funding for ELWIND, a 1 GW Latvia-Estonia cross-border offshore wind project. The co-funding is said to enable research to determine the environmental impact of the Latvian-Estonian ELWIND offshore wind farm sites and to plan the transmission network cross-border connections and […]

  • 8 January 2020
    Ports & Logistics

    MHI Vestas has selected the Port of Roenne in Denmark for pre-assembly and shipment of turbine components for the Arcadis Ost 1 offshore wind project in Germany. MHI Vestas will provide 27 V174-9.5MW turbines for the Arcadis Ost 1 wind farm located off the coast of the Rugen island. The turbine installation is set to take […]

  • 7 January 2021
    Business & Finance, Wind Farm Update

    Offshore wind developer Parkwind has secured a loan from the European Investment Bank (EIB) for the construction of the 257 MW Arcadis Ost 1 wind farm. The amount approved is EUR 450 million. Located some 19 kilometres off the island of Rugen in the German Baltic Sea, Arcadis Ost 1 will comprise 27 MHI Vestas […]

  • 3 November 2022
    Wind Farm Update

    DEME has completed the installation of the secondary steel on all the XXL monopiles at Parkwind’s Arcadis Ost 1 offshore wind farm in the German part of the Baltic Sea, with the project now ready to enter the next stage of construction. The offshore construction specialist installed the final XXL monopile, manufactured by Steelwind, at […]

  • 27 April 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Parkwind and Bladt Industries have signed an agreement for the design, fabrication, and installation of the Arcadis Ost 1 substation in the German Baltic Sea. Bladt Industries is to deliver the complete substation for Parkwind, with Semco Maritime and ISC Engineering as key partners. Semco Maritime will be responsible for the design and implementation of […]

  • 13 February 2013
    Authorities

    Last week, German regulators awarded the preliminary approval for the Arcadis Ost 1 offshore wind farm project. The wind farm will be located on the 30 square kilometers area, approximately 19 kilometers northeast of Cape Arkona. The developer chose Alstom’s 6MW wind turbines for this project. “After Baltic 1 wind farm went into operation in […]

  • 2 June 2021
    Contracts & Tenders, Wind Farm Update

    DEME Offshore has signed a contract with Poland’s Energomontaż-Północ Gdynia (EPG) for the fabrication and delivery of equipped secondary steel structures for the Arcadis ost 1 offshore wind farm in the German Baltic Sea. EPG will deliver 27 sets of equipped secondary steel structures for turbine foundations, and for one offshore substation transition piece. The […]

  • 28 June 2021
    Wind Farm Update

    Parkwind has selected 24Sea for the engineering, procurement, installation and commissioning of the structural health monitoring systems on the wind turbine foundations at the Arcadis Ost 1 offshore wind farm in Germany. The 257 MW offshore wind farm will feature 27 TP-less monopiles, with the towers to be be connected directly to the monopiles. 24Sea […]

  • 30 May 2022
    Vessels, Wind Farm Update

    The installation of 28 XXL monopiles for 27 wind turbines and one substation of the Arcadis Ost 1 offshore wind farm is about to begin as DEME Offshore’s installation vessel Orion has arrived at the Port of Roenne, the project’s storage and marshaling port. According to available AIS data, Orion arrived at the port this […]

  • 15 June 2022
    Grid Connection, Operations & Maintenance, Wind Farm Update

    Parkwind and 50Hertz have installed the offshore substation for the 257 MW Arcadis Ost 1 offshore wind farm in the Baltic Sea. The 2,380-tonne, 30-metre high offshore substation was installed by the Scaldis crane ship Gulliver on its monopile foundation at the project site, located around 19 kilometres east of Rügen island in Germany. The […]

  • 25 November 2022
    Vessels, Wind Farm Update

    The first of the total of 27 Vestas’s V174-9.5 MW wind turbines to be installed at the Arcadis Ost 1 offshore wind farm in the Baltic Sea is now up. The offshore wind farm is developed and owned by Belgian developer Parkwind, for which this is its first project in Germany. The 257 MW Arcadis Ost […]

  • 31 May 2022
    Contracts & Tenders, Wind Farm Update

    Vestas has selected Global Wind Service (GWS) to provide wind turbine pre-assembly services for the 27-turbine Arcadis Ost 1 offshore wind farm in Germany. The pre-assembly works will start soon at Rønne Havn on the Danish Bornholm Island in the Baltic Sea. In June last year, Parkwind ordered 27 Vestas V174-9.5 units which will be […]

  • 6 September 2021
    Contracts & Tenders, Wind Farm Update

    Global Marine Group companies Global Offshore, CWind, and OceanIQ will install the inter-array cables at the Arcadis Ost 1 offshore wind farm in Germany, under a turnkey contract signed with Parkwind. Global Offshore will install and bury the inter-array cables by using the Normand Clipper and Global Symphony vessels, with the work scheduled to commence […]

  • 27 January 2022
    Ports & Logistics, Wind Farm Update

    DEME Offshore has selected the Port of Roenne on Denmark’s Bornholm Island as the storage and marshaling hub for the 257 MW Arcadis Ost 1 offshore wind farm in the German Baltic Sea. DEME is the EPCI contractor for the project’s 27 wind turbine foundations and one offshore substation foundation. ”We have chosen Port of […]

  • 24 June 2021
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Following the financial close on the Arcadis Ost 1 offshore wind farm, Vestas has secured a firm order for Parkwind’s first project in Germany, which will also be the first to use a new floating installation method to erect the wind turbines. Under the contract with Parkwind, Vestas will deliver 27 of its 9.5 MW […]

  • 3 July 2020
    Contracts & Tenders, Wind Farm Update

    Offshore wind developer Parkwind has signed a contract with Steelwind for the fabrication of the monopile foundations for the Arcadis Ost 1 offshore wind farm. The contract was signed at Steelwind’s headquarters in Nordenham, Germany. This signature follows Parkwind’s recent order of the wind farm’s offshore substation at Bladt Industries. Under the contract, Steelwind will […]

  • 20 July 2022
    Grid Connection, Wind Farm Update

    Transmission system operator 50Hertz has announced that the Arcadis Ost 1 offshore substation has been connected to the German extra-high voltage grid after the 220 kV submarine cable required for this was pulled into place on the platform over the past few days. Final assembly and commissioning works will now follow. “We are very proud […]

  • 29 June 2021
    Grid Connection

    German transmission system operator for the Baltic Sea, 50Hertz, has pulled in the land cables for the Ostwind 2 offshore grid connection. The Ostwind 2 land cables have now been installed underground over a distance of three kilometres from the landing point, where the sea cables meet the mainland, to the Lubmin transformer station. Using […]

  • 17 March 2023
    Grid Connection, Wind Farm Update

    JDR Cable Systems has begun the subsea cable termination and testing works on behalf of its client Parkwind for the Arcadis Ost 1 offshore wind farm in Germany. In 2021, JDR won a contract to supply, test, and terminate 45 kilometres of 33 kV array cable that will connect the wind farm’s 27 MHI Vestas […]

  • 9 November 2021
    Grid Connection, Wind Farm Update

    The final section of the second of the three 220 kV export cable systems for the Ostwind 2 project is being laid in the German Baltic Sea, 50Hertz Transmission GmbH said. Around 170 kilometres of export cables have been laid at sea and on land over the past months to connect two offshore wind farms […]

  • 16 September 2021
    Operations & Maintenance, Wind Farm Update

    Ems Maritime Offshore (EMO), Vestas, and Parkwind have signed lease agreements for an operations and maintenance (O&M) building in the Port of Sassnitz–Mukran for Parkwind’s Arcadis Ost 1 offshore wind farm. The building will see up to 40 professionals overseeing and maintaining the 257 MW project, located northeast of the island of Rügen in the […]

  • 4 July 2022
    Contracts & Tenders, Wind Farm Update

    Parkwind has awarded Semco Maritime a five-year service contract for the offshore substation at the Arcadis Ost 1 offshore wind farm in the German Baltic Sea. From 2022 to 2027, Semco Maritime will perform service assignments at the offshore platform northeast of Rügen island in Germany. The company’s scope of work will include scheduled and […]