Search results for: nexans aurora

173 results

A list of search results

  • 8 December 2017
    Grid Connection, Ports & Logistics, R&D, Vessels, Wind Farm Update

    Nexans’ cable laying vessel Nexans Skagerrak has completed the laying and burial of the first 70-kilometer 220kV export cable which will connect the 588MW Beatrice offshore wind farm to the Scottish grid.

  • 6 December 2017
    Wind Farm Update

    Beatrice Offshore Windfarm Ltd (BOWL) posted a photo on its social media pages today, 6 December, showing Nexans Skagerrak, Siem Aimery and Siem Stingray vessels working at the offshore construction site in the Outer Moray Firth off Scotland.

  • 4 December 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) has installed the 86th and final four-pile set at the Beatrice offshore wind farm site. SHL carried out the piling work with the heavy-lift vessel Stanislav Yudin, which will now re-mobilise for jacket foundation installation.

  • 22 November 2017
    Grid Connection, R&D, Technology

    Nexans has opened a new high voltage test laboratory at its Calais Center of Excellence in France, making it fully operational with the capacity to test cable systems up to 1.5 million volts.

  • 30 October 2017
    Grid Connection, Wind Farm Update

    The second campaign of the installation of two export cables in the export corridors and construction site of the Beatrice offshore wind farm will start around 2 November, according to the project’s Notice to Mariners. 

  • 23 October 2017
    Wind Farm Update

    Seaway Heavy Lifting (SHL) is set to commence the first pre-lay grapnel run campaign at the Beatrice offshore wind farm site to clear the inter-array cable routes from debris and prepare them for cable installation.

  • 9 October 2017
    Wind Farm Update

    Nexans has started jetting/trenching of the installed section of the first Beatrice offshore wind farm export cable (EC1.1) from around 2km North of the beach at Portgordon.

  • 9 October 2017
    Operations & Maintenance, Technology

    Osbit has secured a contract for the delivery of its MaXccess T12 crew-transfer ‘walk-to-work’ access system for a vessel that will be deployed at Binhai offshore wind farms in China, developed by State Power Investment Corporation (SPIC).

  • 9 October 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessel Stanislav Yudin has installed 80 out of 86 sets of foundation piles for the 588MW Beatrice offshore wind farm off Scotland.

  • 28 September 2017
    Grid Connection, Vessels, Wind Farm Update

    Nexans has commenced the first installation campaign of two export cables for the Beatrice offshore wind farm. The project’s notice to mariners states that the works have been set to start around 28 September.

  • 4 October 2017
    Wind Farm Update

    Approximately 76 kilometres of subsea cable for the 385MW Arkona offshore wind farm has arrived to the basis station of Mukran Port on Rugen island.

  • 3 September 2017

    Nexans Boosts Cable Laying Fleet with High Capacity Newbuild Nexans has announced the start of construction of a new cable-laying vessel for submarine high voltage (HV) cable systems installation. Analysis: Neart Na Gaoithe Offshore Wind Farm to Have GBP 827 Million Impact on Scottish GDP The 450MW Neart Na Gaoithe offshore wind project is estimated […]

  • 28 August 2017
    Vessels

    Nexans has announced the start of construction of a new cable-laying vessel for submarine high voltage (HV) cable systems installation. Being built by Uljanik Group, a Croatia-based shipyard, the high capacity Nexans vessel is designed for worldwide installation of large volumes of HVDC and HVAC cable systems, even in the most severe weather conditions, the […]

  • 4 September 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s vessels Stanislav Yudin and Oleg Strashnov have installed 69 pile clusters and 12 jacket foundations in the Outer Moray Firth off Scotland for the 588 Beatrice offshore wind farm project.

  • 28 August 2017
    Vessels, Wind Farm Update

    Heavy lift vessel Stanislav Yudin has installed more than three quarters of the foundation piles on the 588MW Beatrice wind farm off Scotland, Beatrice Offshore Windfarm Ltd (BOWL), reports.

  • 1 August 2017
    Grid Connection, Vessels

    The installation of the 1.4GW NordLink high voltage direct current (HVDC) subsea interconnector between Norway and Germany has started, Norway’s Stattnet reports.

  • 23 July 2017

    Offshore WIND’s most read news from 16 to 23 July 2017.

  • 21 July 2017
    Wind Farm Update

    Half of the wind turbine foundation piles have been installed at the Beatrice offshore wind site, the developer informed via social media. The piling is being carried out by Seaway Heavy Lifting (SHL) with their heavy lift vessel Stanislav Yudin.

  • 17 July 2017
    Contracts & Tenders, Grid Connection

    Siemens has received an order from TenneT to supply the entire technology for efficient direct-current transmission for DolWin6, a grid connection for offshore wind farms in the German waters of the North Sea. The order is valued at high three-digit millions euros range.

  • 19 July 2017
    Wind Farm Update

    Seaway Heavy Lifting has contracted FoundOcean for the grouting of the 84 wind turbine jacket foundations and two offshore transmission module (OTM) jackets at the Beatrice offshore wind farm, and has chosen BASF MasterFlow 9800 bulk-supplied grout. 

  • 28 June 2017
    Grid Connection, Vessels, Wind Farm Update

    Ecosse Subsea Systems (ESS) has completed a 14-day seabed clearance project on the Beatrice Offshore Windfarm Ltd project, located approximately 13km off the Caithness coast.

  • 22 June 2017
    Wind Farm Update

    Siem Offshore Contractors (SOC) has awarded Canyon Offshore Limited, an Aberdeen-based trenching solutions provider, a contract for the provision of trenching services on DONG Energy’s Hornsea Project One offshore wind farm.

  • 17 May 2017
    Vessels, Wind Farm Update

    The two vessels contracted to carry out the trenching along the export cable route for the Beatrice offshore wind farm project are expected to arrive in the Buckie harbour in Scotland this week and start mobilising for the project.

  • 18 May 2017
    Grid Connection, Wind Farm Update

    The first power transformer built by Siemens for the Beatrice offshore wind farm has left the factory in Dresden and is on its way to Rotterdam. The transformer is expected to arrive on site by end of May, the company’s spokesperson told Offshore WIND.

  • 23 May 2017
    Grid Connection, Wind Farm Update

    Beatrice Offshore Windfarm Limited (BOWL) has started the first stage of export cable works for the Beatrice offshore wind farm at Portgordon near Buckie, as it plans to install the export cables beneath Portgordon Beach.

  • 15 May 2017
    Wind Farm Update

    On 11 May, Seaway Heavy Lifting (SHL) installed the 11th set of jacket foundation piles at the Beatrice offshore wind farm in Outer Moray Firth.