Search results for: Saint-Brieuc

215 results

A list of search results

  • 7 May 2021
    Wind Farm Update

    Local fishermen have taken their protests against the construction of the French Saint-Brieuc offshore wind farm from land to the offshore project site on 7 May, when 70 fishing boats surrounded the Aeolus installation vessel in the Bay of Saint-Brieuc. To voice their opposition to the project, the fishermen have also fired distress flares while […]

  • 13 June 2022
    Contracts & Tenders, Wind Farm Update

    Haizea Breizh, the French subsidiary of the Spanish wind turbine tower producer Haizea Wind Group, has contracted SPIE Industrie & Tertiaire for the assembly of internal components on the 62 towers for the Saint-Brieuc offshore wind farm at Haizea’s facilities in the Port of Brest. The wind turbine towers will be manufactured and painted at […]

  • 25 November 2013
    Business & Finance, Ports & Logistics

    General Council of Côtes-d’Armor (Conseil général des Côtes-d’Armor) has issued a call for bids for quay construction works for Departmental Port of Saint-Brieuc Le Légué. The Council states that this development is essential to position the Légué port as a service port in the context of the completion of the offshore wind farm in the […]

  • 4 March 2021
    Ports & Logistics, Wind Farm Update

    Spain’s Windar renovables is shipping out the first batch of pin-piles manufactured for the Saint-Brieuc offshore wind project in France. Tadarsa Logistics is assisting Windar renovables in loading out the first 15 pin-piles for the turbine jacket foundations and four pin-piles for the substation jacket foundation at the port of Avilés. The vessel and the […]

  • 26 February 2020
    Grid Connection, Wind Farm Update

    Preliminary agreements to ensure the grid connection for the Saint-Brieuc offshore wind project in France and the Baltic Eagle and Wikinger Süd projects in Germany have been concluded, Iberdrola said. For Saint-Brieuc, a preliminary agreement has been concluded with grid operator RTE to ensure the grid connection will be available in the second quarter of […]

  • 26 February 2019
    Business & Finance

    Siemens Gamesa Renewable Energy has submitted a building permit application for a wind turbine production plant in Le Havre, France. Siemens Gamesa submitted the application to the mayor of Le Havre on 25 February, a spokesperson from the company told Offshore WIND. According to the company, the turbine production facility will be focused on supplying the Dieppe-Le […]

  • 2 August 2021
    Vessels, Wind Farm Update

    Van Oord’s Aeolus has resumed drilling work at the Saint-Brieuc wind farm offshore France after the activities were halted once again last week due to the spillage of hydraulic fluid from one of the drills. As reported last week, the drilling activities were halted after the drill leaked the hydraulic fluid into the marine environment […]

  • 3 December 2020
    Authorities, Wind Farm Update

    The Saint-Brieuc offshore wind project is now free from any appeals before the French courts, according to an update from Ailes Marines on 3 December. The appeal had been filed by the Association for the Protection of the Sites of Erquy and Surrounding Sites (ASPE), Erquy Environnement and others, requesting the Council of State to […]

  • 25 June 2021
    Authorities, Vessels, Wind Farm Update

    Trenching support vessel Aethra was forced to leave the Saint-Brieuc offshore wind farm after the local fishermen protesting the project breached several safety protocols and verbally threatened the safety of the captain and the crew. The Aethra was deployed on the site when a large number of fishing boats surrounded the vessel. The fishermen then […]

  • 3 July 2020
    Contracts & Tenders

    Van Oord has awarded Bauer Spezialtiefbau with a contract for piling works at the Saint-Brieuc offshore wind project in France. The German company will install 190 bored piles at 62 locations for three-legged jackets, as well as one substation location consisting of a four-legged jacket foundation. Bauer Spezialtiefbau is going the provide and operate the […]

  • 22 July 2020
    Contracts & Tenders

    Saipem revealed on 22 July that it won three contracts for offshore wind farms in Europe – Dogger Bank A and B, Seagreen, and Saint Brieuc – valued at more than EUR 90 million in total. With the Equinor-SSE Renewables join venture Dogger Bank Offshore Wind Farms, Saipem inked a deal for the transportation and […]

  • 3 July 2017
    R&D, Vessels, Wind Farm Update

    Fugro has started a complete geotechnical survey campaign at the site of the 496MW Saint-Brieuc offshore wind farm in France, Ailes Marines, the consortium behind the project, reports.

  • 4 May 2021
    Vessels, Wind Farm Update

    Van Oord’s offshore installation vessel Aeolus is starting the installation of the first of 62 jacket foundations for the Saint-Brieuc offshore wind farm project. The 496 MW wind farm is located 16.3 kilometres off the coast of Brittany, France. Van Oord is using the port of Cherbourg as the pin pile marshalling port. The pin […]

  • 1 July 2022
    Wind Farm Update

    Installation of jacket foundations has started at the site of the French Saint-Brieuc offshore wind farm, the country’s second project of this kind and the first to use jacket foundations. Five vessels have been mobilised for this work. Seven Borealis is being used for the lifting and installation of the foundations, North Sea Giant for […]

  • 28 February 2018
    Authorities, Business & Finance, Environment, Wind Farm Update

    France’s Environmental Authority has dismissed an appeal against its recent decision that a new environmental assessment study is not needed for the 496MW Bay of Saint-Brieuc offshore wind project following the switch from the Adwen 8MW to the Siemens Gamesa 8MW turbine.

  • 4 January 2023
    Wind Farm Update

    Iberdrola has revealed that it completed the first phase of construction for its 496 MW Saint-Brieuc wind farm offshore France, with works continuing in January depending on weather conditions. A total of 65 per cent of the piles and 40 per cent of the jacket foundations that will support wind turbines have now been installed […]

  • 1 October 2012
    R&D, Wind Farm Update

    The company Ailes Marines, created by IBERDROLA and EOLE-RES to develop the offshore wind farm in the bay of Saint Brieuc, announces the launch of two technical feasibility campaigns. These campaigns will be conducted on the site of the future offshore wind farm in the bay of Saint Brieuc. Ailes Marines has commissioned the company […]

  • 20 September 2017
    Wind Farm Update

    Following Siemens Gamesa’s decision to replace Adwen’s 8MW turbines, proposed to be installed at three French offshore wind farms, Ailes Marines informed it had sought the approval from the French Minister for the Ecological and Inclusive Transition, Nicolas Hulot, with the decision expected shortly. 

  • 20 April 2017
    Authorities, Wind Farm Update

    Ailes Marines, the developer and future operator of the 496MW offshore wind farm project in the Bay of Saint-Brieuc, France, has received the three administrative authorisations required to construct and operate the wind farm. The company has now obtained the concession of utilisation of the maritime public domain; the Unique Authorisation for the installations Structures, Works and […]

  • 3 September 2020
    Vessels, Wind Farm Update

    Bokalift 1 has been deployed on the Saint-Brieuc offshore wind project in France, where drilling tests are now taking place and will continue throughout September. Ailes Marines, the developer of the 496 MW offshore wind farm, said via social media that the vessel was chartered by Van Oord and the drilling testing campaign began following […]

  • 7 March 2022
    Vessels, Wind Farm Update

    Construction works on the 496 MW Saint-Brieuc offshore wind farm are now resuming, the developer Ailes Marines informed on 7 March, saying the installation vessel Aeolus will be working at the site without interruption in 2022 and 2023. According to the vessel’s AIS data, Van Oord’s jack-up was at the Saint-Brieuc offshore wind farm site […]

  • 16 September 2019
    Contracts & Tenders, Wind Farm Update

    The Spanish consortium of Navantia and Windar Renovables has won a contract to manufacture 62 jacket foundations for the 496MW Saint-Brieuc offshore wind farm. The consortium was revealed as the winner of the contract on Monday, 16 September, during an event organised in Brest, France, by Ailes Marines, the developer of the project. This is the […]

  • 18 June 2020
    Contracts & Tenders, Wind Farm Update

    Spain’s Navantia-Windar consortium has received a firm order from the compatriot energy company Iberdrola for the turbine jacket foundations to be installed on the Saint-Brieuc wind farm offshore France. The contract, valued at EUR 350 million, will see Navantia-Windar manufacture and assemble 62 jacket foundations and the accompanying pin piles which will support the wind […]

  • 16 July 2021
    Vessels, Wind Farm Update

    Van Oord’s jack-up vessel Aeolus arrived at the Saint-Brieuc offshore wind farm site today (16 July) after leaving the Port of Rotterdam’s Maasvlakte terminal on 14 July following the maritime authorities’ go-ahead to return to work off France. The vessel will now resume with the drilling and installation of piles for the offshore wind farm’s […]

  • 10 January 2018
    Authorities, Business & Finance, Wind Farm Update

    Ailes Marines, the developer of the 496MW Bay of Saint-Brieuc offshore wind farm in France, does not need to carry out a new environmental assessment study for the project following the recently approved switch from the Adwen 8MW to the Siemens Gamesa 8MW turbine.

  • 20 February 2017
    Authorities, Contracts & Tenders

    On 16 February, the Administrative Court in Rennes dismissed complaints filed by Nass & Wind and Alstom Wind France, requesting a cancellation of the French government’s authorisation given to Ailes Marines for modification of the Saint Brieuc project and Prefect of Côtes-d’Armor’s decision to allow for one more year to submit applications for the authorisation.