Search results for: SeaMade

1097 results

A list of search results

  • 18 June 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up Apollo has left the REBO terminal in Oostende loaded with the first set of turbine components to be installed on the 487 MW SeaMade wind farm offshore Belgium. Apollo arrived at the REBO heavy load terminal in the Port of Oostende on 14 June, after undergoing spudcan shoes extension at Damen Shiprepair […]

  • 18 December 2019
    Grid Connection, Wind Farm Update

    DEME Group has completed the pull-in of two export cables of the SeaMade offshore wind project into Elia’s Offshore SwitchYard (OSY) platform.  DEME’s cable-laying vessel Living Stone picked up the export cables for the 487MW project from Hellenic Cables’ facility in Soussaki, Greece, in mid-November. SeaMade will have two offshore substations, which will collect the […]

  • 14 October 2020
    Wind Farm Update

    Thirty-nine out of 58 Siemens Gamesa 8.4 MW turbines have been installed at the SeaMade offshore wind project in Belgium. According to Aspiravi, one of the project owners, 36 of the Siemens Gamesa units are operational. DEME Group’s jack-up vessel Apollo installed the first turbine at the project site located some 50km off the coast in mid-June. The […]

  • 20 March 2020
    Wind Farm Update

    Tekmar Energy Limited has completed the delivery of TekLink® cable protection systems to DEME Offshore for the SeaMade offshore wind farm in Belgium. SeaMade is a 487MW offshore wind farm currently under construction off the coast of Belgium and integrates two wind farm sites known as Mermaid and Seastar. Tekmar Energy was awarded a contract […]

  • 7 August 2020
    Wind Farm Update

    Sixteen out of 58 Siemens Gamesa 8.4 MW turbines have been installed at the SeaMade offshore wind project in Belgium. According to Otary CEO Mathias Verkest, the 9th turbine load-out is currently being prepared at the Port of Oostende. DEME’s Apollo installed the first turbine at the project site located some 50km off the coast in […]

  • 7 January 2020
    Wind Farm Update

    DEME Group has completed the installation of 58 turbine foundations and two substation foundations at the SeaMade offshore wind project in Belgium. DEME’s jack-up vessel Innovation installed the last monopile foundation at the project site some 50km off the coast from Ostend on 2 January. According to the company, a new monopile gripper was deployed onboard […]

  • 15 November 2019
    Grid Connection, Wind Farm Update

    DEME’s cable laying vessel Living Stone has departed Greece carrying the export cables for the 487MW SeaMade offshore wind farm in the Belgian North Sea. Living Stone loaded the export cables with a combined length of around 28 kilometres at Hellenic Cables’ facility in Soussaki. The vessel is currently en route to Vlissingen, the Netherlands. […]

  • 14 August 2020
    Wind Farm Update

    Haizea Wind has sent off the final two towers for the SeaMade offshore wind turbines from Bilbao. The Spain-based Haizea Wind is delivering 12 wind turbine towers for the project, which will feature 58 Siemens Gamesa 8.4 MW turbines. The first tower parts arrived from the port of Aviles in Spain to Belgium in mid-March, onboard […]

  • 11 December 2018
    Business & Finance, Grid Connection, Wind Farm Update

    Eneco has concluded a long-term power purchase agreement (PPA) for the SeaMade offshore wind project in Belgium.

  • 26 March 2020
    Wind Farm Update

    The first two turbine towers destined for the SeaMade offshore wind project have arrived at the Port of Ostend, Belgium. According to Otary, the first six tower parts arrived in Belgium on 24 March from the port of Aviles in Spain onboard the special purpose vessel Rotra Vente. Over the coming months, Rotra Vente and […]

  • 5 March 2020
    Grid Connection, Wind Farm Update

    The first of two offshore substations for the SeaMade offshore wind farm has been installed at the project site in the Belgian North Sea. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. The 1,200t topside, which has four decks and is 14m tall, has been installed […]

  • 20 May 2020
    Grid Connection, Wind Farm Update

    DEME Offshore and Hellenic Cables have completed the testing and energization of the export cable connections at the SeaMade offshore wind project in Belgium. DEME said it is currently carrying out the inter-array cable installation and preparing for the turbine installation campaign, set to begin in mid-June. “Another important milestone for the SeaMade offshore wind […]

  • 13 December 2018
    Business & Finance, Contracts & Tenders

    Dredging International has contracted Sif to produce the monopiles and, in joint venture with Smulders, the transition pieces for the SeaMade offshore wind farm in Belgium.

  • 23 July 2019
    Operations & Maintenance, Vessels

    DEME Group’s jack-up vessel Innovation is undergoing a major maintenance and repair program at the Damen Verolme yard in Rotterdam, the Netherlands. According to DEME, the program is almost completed and saw the installation of two new leg sections on the offshore installation vessel. After the extensive dry dock, Innovation will set sail to the SeaMade offshore […]

  • 15 February 2019
    Contracts & Tenders, Wind Farm Update

    Belgian offshore wind developer SeaMade NV has selected Waves Group to provide Marine Warranty Surveyor services during the construction of the 487MW SeaMade offshore wind farm. Waves Group is currently providing MWS services for the installation of foundations, infield cables, wind turbines, export cables, and two offshore substations. Associated operations include loadouts, installations, and pulling in cables to both […]

  • 12 June 2020
    Ports & Logistics, Vessels

    DEME Offshore’s jack-up Apollo has undergone spudcan shoes extension installation at Damen Shiprepair & Conversion’s yard in Dunkerque, France. With the new spudcan extensions, Apollo will be able to get more stability on a wider variety of seabed soils, Damen said. Following her stay at the Dunkerque yard, the vessel is now ready to sail […]

  • 28 July 2022
    Contracts & Tenders, Wind Farm Update

    Aurubis Olen, part of the Aurubis Group, has signed a ten-year Power Purchase Agreement (PPA) with Eneco to procure renewable energy from the SeaMade offshore wind project in Belgium. The agreement entails the purchase and supply of 12 MW of wind power over the next decade, with delivery to begin in January 2023. Inge Hofkens, […]

  • 30 January 2019
    Business & Finance, Operations & Maintenance

    Siemens Gamesa has placed an order with Seasight Davits for 58 davit cranes for the SeaMade offshore wind farm in Belgium. The cranes will be manufactured by Seasight Davits’ parent company Hvide Sande Shipyard, Steel and Service and will have an outreach of 3.2m and a one-ton lifting capacity. According to the Danish davit crane supplier, the […]

  • 13 October 2020
    Wind Farm Update

    Windar has sent off the last wind turbine tower sections for the SeaMade offshore wind project in Belgium. Special purpose vessel Rotra Ventre set sail with the last six tower sections from Windar’s facilities in the port of Avilés, Spain, to the Port of Ostend, where the REBO sites are serving as storage and pre-assembly […]

  • 13 March 2020
    Grid Connection, Wind Farm Update

    Scaldis Salvage & Marine Contractors is currently preparing for the installation of the second offshore substation at the SeaMade wind farm in Belgium. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. This second topside, which recently arrived in Vlissingen, the Netherlands, will be installed at the Seastar […]

  • 5 June 2019
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Hartlepool-based JDR Cables has signed a contract with DEME Offshore to provide inter-array cables and accessories for the SeaMade offshore wind farm in the Belgian North Sea. JDR, part of the TFKable Group, will design, manufacture and deliver 78.1 kilometres of aluminium core inter-array cables and a range of cable accessories, including repair joints and connectors. […]

  • 14 April 2020
    Wind Farm Update

    DEME’s cable installation vessel Living Stone has started the inter-array cabling work at the SeaMade offshore wind farm.

  • 3 March 2020
    Grid Connection, Wind Farm Update

    The first of two offshore substations for the SeaMade offshore wind farm has left Engie Fabricom’s construction yard in Hoboken and is on its way towards the project site in the Belgian North Sea. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. The 1,200t topside, […]

  • 17 December 2018
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    On 14 December, Siemens Gamesa and REBO (Renewable Energy Base Oostende) signed a contract for Belgian SeaMade offshore wind farm, which will feature 58 Siemens Gamesa offshore wind turbines. 

  • 18 March 2020
    Grid Connection, Wind Farm Update

    The second SeaMade offshore substation topside has been installed in the Seastar concession area in the Belgian North Sea. The wind farm’s first substation was installed in the Mermaid concession area at the beginning of March. Each with a weight of 1,200 tonnes, the substations transform the wind energy that is produced to 225kV, which in […]

  • 19 November 2019
    Contracts & Tenders, Grid Connection

    JECS Offshore Services has secured a contract to provide support to Hellenic Cables during termination works on the export cables at the SeaMade offshore wind farm in Belgium. JECS Offshore will design, supply and erect the scaffolding access platforms required for technicians to prepare and position the cables and carry out the terminations of the […]