72 results found for 'Port of Cromarty Firth'

72 results found for 'Port of Cromarty Firth'
Order results by

A list of search results

  • 19 December 2023
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Boskalis’ DP installation vessel Bokalift 1 has installed the first offshore substation platform (OSP) at the Moray West offshore wind farm site in Scotland. The heavy lift operations in the Port of Nigg and on-site were completed safely and successfully, according to the developer Ocean Winds. As offshore commissioning starts, the previously laid export cable […]

  • 3 July 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 882 MW Moray West offshore wind farm has delivered first power from the first series of wind turbines and exported to Scotland’s National Electricity Transmission System (NETS), Ocean Winds said. The wind farm is nearing the end of the construction phase and will become fully operational in 2025 in line with the originally projected […]

  • 15 March 2023
    Infrastructure, Ports & Logistics, Vessels

    A new report by the Floating Wind Offshore Wind Taskforce says up to eleven ports around the UK will need to be transformed as fast as possible into new industrial hubs to enable the roll-out of floating offshore wind at scale. The report contains a series of recommendations which could see 34 GW of floating […]

  • 11 December 2023
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Work on the installation of the two offshore substations (OSS) at the Moray West offshore wind farm site has started, with Boskalis’s DP installation vessel Bokalift 1 currently moored in the Port of Nigg with the components for the first OSS on board. The Moray West project team notified about the commencement of the OSS […]

  • 28 December 2020
    Wind Farm Update

    The 103rd and final jacket foundation has been installed at the Moray East offshore wind farm site in Scotland. The Seajacks Scylla jack-up vessel installed the first three-legged jacket in July. The wind farm’s three offshore transformer modules (OTMs), together with their three jacket foundations, have been in place since mid-September. DEME’s installation vessel Orion, initially scheduled to be […]

  • 14 November 2016
    Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) has appointed GAC UK to provide shipping services support during the construction and installation of foundations, inter-array cables and offshore substations at the 588MW Beatrice offshore wind farm. SHL, the engineering, procurement, construction and installation (EPCI) contractor, will design, supply and install the piled foundations, jacket substructures and inter-array cables for the […]

  • 21 May 2018
    Wind Farm Update

    North Highland Initiative has posted a photo of a batch of Beatrice wind turbine towers lined up and the Ro-Ro vessel Rotra Mare anchored alongside the Nigg Energy Park site, where Siemens Gamesa has set up its pre-assembly area for the project.

  • 20 June 2018
    Wind Farm Update

    Seaway Heavy Lifting (SHL), using its vessel Oleg Strashnov, installed the 77th jacket foundation at the Beatrice site on 20 June, according to some media posts from those involved in the project, following the project’s Notice to Mariners from 18 June that reported 76 jackets being in place.

  • 29 January 2013
    Business & Finance

    Highlands and Islands Enterprise (HIE) has signed joint working agreements with four of the region’s leading ports to support the development of the offshore wind sector. The partnership aims to help the Ports attract a potential £100m of investment to the Highlands. The First Minister Alex Salmond, announced the Memorandums of Understanding (MoU) in his […]

  • 18 April 2024
    Collaboration, Floating Wind, Industry, Infrastructure, Outlook & Strategy, Supply Chain, Transition

    Major South Korean shipbuilder, HD Hyundai Heavy Industries, has signed a Memorandum of Understanding with two Scottish enterprise agencies which is expected to unlock expertise in the design and manufacture of floating offshore wind substructures. Scottish Enterprise (SE) and Highlands & Islands Enterprise (HIE) signed the MoU with Hyundai Heavy in Edinburgh, described as a […]

  • 25 January 2022
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    Siemens Gamesa has conditionally selected Port of Nigg in the Cromarty Firth, Scotland, as the planned location for the pre-assembly and installation of wind turbines for the Moray West offshore wind farm. Siemens Gamesa, as the preferred bidder for the supply of the offshore wind turbines, has signed a conditional agreement with Global Energy Group […]

  • 21 February 2022
    Contracts & Tenders

    Metec Group (Metec), a South Tyneside manufacturing company, has been awarded a six-figure offshore contract to supply and install a 30-year cathodic protection system for what’s set to be “the largest offshore wind tower factory in the UK”. The company will produce around 400 sacrificial anodes for the development of the new quay in Cromarty […]

  • 15 June 2016
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Global Energy Group and Siemens have signed a contract for the use of Nigg Energy Park fabrication yard on the Cromarty Firth during the construction of the 588MW Beatrice offshore wind farm. This multi million pound contract award is scheduled to commence in the spring of 2018 with every likelihood of retaining and creating in excess of […]

  • 28 January 2021
    Ports & Logistics

    Development agency Highlands and Islands Enterprise (HIE) has approved an investment of up to GBP 8.3 million in Scottish Government funding for an GBP 18.9 million project to develop the East Quay at Port of Nigg in Easter Ross. Owned by Global Energy Group (GEG), Port of Nigg is home to the largest graving dock […]

  • 29 January 2013

    Scotland has set a target to cut carbon emissions from electricity generation by more than four-fifths by 2030, underlining the huge market for offshore wind beyond 2020. First Minister Alex Salmond revealed the new target at the Scottish Renewables-Scottish Enterprise Offshore Wind & Supply Chain Conference, Aberdeen. He also announced the signing of new Memorandums […]

  • 11 August 2021

    The first jacket superstructures destined for the 1.1 GW Seagreen offshore wind farm have arrived at Port of Nigg in Cromarty Firth, Scotland. The jacket components will be installed as part of the foundations in the deep waters of the North Sea, 27 kilometres off the Scottish coast near Angus. The components were welcomed to […]

  • 23 June 2022
    Contracts & Tenders, Wind Farm Update

    Offshore wind contractor Cadeler has signed a firm contract with Siemens Gamesa to provide the transportation and installation of a total of 60 wind turbines for the 882 MW Moray West wind farm offshore Scotland. The contract for the installation of the giant SG 14-222 DD offshore wind turbines at the Moray West offshore wind […]

  • 12 February 2021
    Contracts & Tenders, Ports & Logistics

    Global Energy Group (GEG) has signed an agreement with ScottishPower’s newly established Green Hydrogen Business to explore the best solution to power the operations at the Port of Nigg with green hydrogen. The companies will undertake a feasibility study to assess the full potential range of processes that could be supported by hydrogen and the […]

  • 24 October 2011
    Authorities

    First Minister Alex Salmond has welcomed the successful sale of the Nigg fabrication site on the Cromarty Firth to Global Energy Group (GEG) and announces £1.8m support to transform yard into a renewables hub. GEG has today announced the completion of the sale from American company KBR and the Wakelyn Trust. The purchase paves the […]

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]