Search results for: Wikinger

606 results

A list of search results

  • 24 October 2018
    Business & Finance, Wind Farm Update

    Spanish energy giant Iberdrola plans to spend around EUR 9 billion to reach the target of having 3GW of installed offshore wind capacity in the US and in Europe by 2023.

  • 29 March 2015

    Floaters ‒ Game Changers for Offshore Wind? At least nine floating projects are likely to come online by 2020, claims Douglas-Westwood. Danes Eye Floating Wind Projects Off Hawaii The Bureau of Ocean Energy Management (BOEM) has received unsolicited lease requests for proposed floating wind projects offshore Oahu, Hawaii from Alpha Wind Energy. Boskalis: Fugro’s Activities […]

  • 21 March 2016

    Reetec GmbH will supply aviation obstruction markers for the Wikinger offshore wind farm. Marking 70 Adwen’s wind turbines falls under German guidelines for the identification of aviation obstacles. Reetec will provide identification lights for the nacelles and towers, as well as the accompanying control and accessory components. Due to rotating blades, some identification requirements are specially adapted to the wind industry. Each nacelle will […]

  • 19 August 2015
    Wind Farm Update

    First of the total 82 A-frames for Wikinger offshore wind farm foundations is ready for the next step in the fabrication process, Bladt Industries reported via social media. The company will deliver 41 four-legged jacket foundations for Iberdrola’s wind farm in the German part of the Baltic Sea. The jacket foundations will be installed in water depths of […]

  • 11 February 2016
    Business & Finance, Operations & Maintenance, Wind Farm Update

    EnBW has once again chosen EMS Maritime Offshore GmbH (EMO) to provide a Maritime Coordination team for the construction phase of the 350 MW Wikinger offshore wind farm in the Baltic Sea. Last week, EnBW and Iberdrola, the developer of the Wikinger OWF, signed a contract under which EnBW will handle the coordination of shipping traffic, health and […]

  • 28 April 2016
    Vessels, Wind Farm Update

    The first wind turbine foundations have been installed at the 350MW Wikinger offshore wind farm, Iberdrola, the owner and developer of the wind farm located in the German part of the Baltic Sea, said. The milestone was announced in the Spanish utility’s financial report for the first quarter of 2016. Iberdrola awarded the EUR 135 million contract […]

  • 19 April 2017
    Grid Connection, Operations & Maintenance, Wind Farm Update

    Spanish energy company Iberdrola has awarded Offshore Marine Management (OMM) with a contract to provide topside and subsea Operations and Maintenance (O&M) services for the 350MW Wikinger offshore wind farm.

  • 27 July 2016
    Wind Farm Update

    Heavy transportation and lifting contractor ALE loaded-out the first of two 3,000-tonne jackets built for the Wikinger offshore substations, in Cadiz, Spain, last week. The jacket was built by Navantia shipyard in Puerto Real for Iberdrola’s 350MW Wikinger offshore wind farm currently under construction in the German Baltic Sea. In December 2014, Iberdrola awarded a EUR 160 million contract to […]

  • 26 October 2017
    Wind Farm Update

    On 22 October, Fred. Olsen Windcarrier’s jack-up Brave Tern completed the turbine installation at the site of the Wikinger offshore wind farm, developed by Iberdrola. The wind farm comprises 70 Adwen 5MW wind turbines supported by jacket foundations.

  • 14 July 2016
    Wind Farm Update

    The first jacket foundations built by Bladt Industries for the Wikinger offshore wind project have left the company’s facilities at Lindø Industripark on a barge early this morning, with Sassnitz in Germany as the next stop. The jacket foundations weigh approximately 650 tonnes and have a footprint of 23 x 23 metres each. They will be installed […]

  • 28 June 2016

    Joint venture partners Navantia and Windar will load the first of 29 jacket foundations for the Wikinger offshore wind farm onto a barge this week. The foundations for Iberdrola’s 350MW offshore wind farm in Germany are being constructed at the Navantia facilities in Fene, Northern Spain. After the first jacket is placed on a barge, the remaining foundations […]

  • 9 January 2017
    Vessels, Wind Farm Update

    Installation of first wind turbines at the Wikinger offshore wind farm is set to start as soon as weather conditions allow. First wind turbine components have been loaded onto the jack-up vessel Brave Tern at the Port of Sassnitz-Mukran, and the vessel is now waiting for a weather window to sail out to the offshore construction […]

  • 27 May 2016

    While the installation of the first foundations at the Wikinger offshore wind site started at the end of the last month, Bladt Industries is lining up further jackets at its Lindø Facility in Denmark.  In total, Bladt will deliver 41 four-legged jacket foundations for the Wikinger offshore wind farm, being built by Iberdrola off the coast of the island of […]

  • 20 February 2017
    Vessels, Wind Farm Update

    The first of 70 Adwen 5MW turbines has been successfully installed at the Wikinger offshore wind farm, Iberdrola’s 350MW project in the German Baltic Sea.

  • 4 February 2016
    Business & Finance, Wind Farm Update

    EnBW and Iberdrola have concluded a contract under which EnBW will provide services for the construction of the Wikinger offshore wind farm in the German Baltic Sea. The two-year contract covers services dealing with the coordination of shipping traffic, health and safety and environmental protection at the construction site. The EnBW Offshore Team will share their […]

  • 27 July 2015

    Reach Subsea has signed a contract with Iberdrola Renovables Offshore Deutschland GmbH in Germany for the removal of nine piles at the Wikinger Wind Farm. Reach will execute the contract using Ocean Installer’s Normand Mermaid. Total contract duration is approximately two weeks. Sales and Marketing Manager Bård Thuen Høgheim says: “We are pleased to see that […]

  • 18 August 2016

    Bladt Industries today posted a picture taken this morning at its Lindø facilities, showing Wikinger jacket foundations.  The first jacket foundations built by Bladt for the Wikinger offshore wind project left the company’s facilities at Lindø Industripark on a barge in mid-July. Bladt Industries has fabricated 41 four-legged jackets and 164 piles for the 350MW Wikinger offshore […]

  • 22 November 2016
    Wind Farm Update

    The last jacket foundations manufactured by Bladt Industries for the Wikinger offshore wind farm are now on their way to the offshore wind farm site in the German sector of the Baltic Sea, following a load-out last Thursday.  The four-legged jackets weigh approximately 650 tonnes and have a footprint of 23 x 23 metres each. They will […]

  • 17 March 2016
    Wind Farm Update

    Iberdrola officially launched the construction of its Wikinger offshore wind farm today. Components for the foundations have been manufactured and the installation will commence in the coming days. The work will be done by using the installation vessel Giant 7, which is currently being mobilized in Rostock, where another ship with the first 32 foundation […]

  • 23 July 2020
    Contracts & Tenders, Wind Farm Update

    Spanish energy company Iberdrola is finalizing the selection of the main contractors for the Baltic Eagle and Wikinger Süd offshore wind projects in the German Baltic Sea. The 476 MW Baltic Eagle and the 10 MW Wikinger Süd were selected in the second public tender organised by Germany’s Federal Network Agency (Bundesnetzagentur) in April 2018. As previously […]

  • 12 July 2016

    The first of 29 Navantia’s jacket foundations for Wikinger offshore wind farm has set sail from Spain and is heading to the Baltic Sea, ScottishPower informed via social media.  The foundations for Iberdrola’s 350MW offshore wind farm in Germany are being constructed at the Navantia facilities in Fene, Northern Spain. The first jacket, weighing 625t, was […]

  • 22 July 2016
    Business & Finance, Operations & Maintenance, Technology

    Navantia has delivered the first jacket foundations to Iberdrola for its Wikinger offshore wind farm located in the German part of the Baltic Sea.

  • 8 October 2015

    Iberdrola was joined yesterday (7th October) by Adwen, Navantia, Offshore WindForce and Prysmian to introduce the €1.4 bn Wikinger offshore wind energy project to German companies and open a forum where local supply chain businesses can investigate collaboration possibilities with Wikinger contractors and partners. Supported by Christian Pegel, Minister for Energy, Infrastructure and Regional Development for […]

  • 28 September 2016
    Operations & Maintenance, Vessels, Wind Farm Update

    Danish shipping company World Marine Offshore has been contracted by Iberdrola Renovables Offshore Deutschland to provide crew transfer vessels (CTVs) during O&M for the 350MW Wikinger offshore wind farm in Germany. Iberdola Renovables Offshore Deutschland GmbH is developing Wikinger in the German Baltic Sea. The wind farm is located in water depths around 30-40m and […]

  • 7 November 2017
    Business & Finance, Contracts & Tenders

    Spanish energy company Iberdrola is actively preparing to participate in the next round of offshore wind auctions in Germany scheduled for April 2018.

  • 29 October 2018
    Wind Farm Update

    Iberdrola is set to officially open its Wkinger offshore wind farm in Germany today, 29 October.