  • 2 January 2012
    Authorities

    The Federal Maritime and Hydrographic Agency has approved 97 wind turbines in German North Sea. 97 wind turbines are planned for the 43 square kilometers area. Dong Energy will build BR2 as the second phase of BR1. Borkum Riffgrund 1 will consist of up to 89 turbines with 3.6MW capacity each from Siemens Wind Power […]

  • 7 February 2014
    Grid Connection

    CT Offshore A/S has entered German market by inking a deal with DONG Energy for the cable installation and burial of inter-array cables at Borkum Riffgrund 1 OWF. Located 37 km from the north-west coast of Germany, the 277MW wind farm consists of 77 wind turbines. The cable installation vessel SIA, together with  MV NICO […]

  • 4 July 2014
    Operations & Maintenance

    Providing power for offshore operations on a transition piece in the construction phase is an essential service when working on the lifeless transition piece. Recently GeoSea chartered the Guardian, Braveheart Shipping’s survey vessel, to provide power by cable to the transition piece in the Borkum Riffgrund 1 wind farm on which they were carrying out […]

  • 5 September 2014

    Pontoon Loaded with OW Turbine Parts Sinks Off Germany A pontoon loaded with parts for offshore wind turbines sank on Wednesday morning (August 13) in the Baltic Sea, German media informs. Vattenfall Orders Turbines and Servicing from Siemens Vattenfall has awarded Siemens Energy an order for 72 Model SWT-4.0-130 wind turbines for its new Sandbank […]

  • 27 May 2015
    Wind Farm Update

    DONG Energy has installed the last of a total of 78 turbines at Borkum Riffgrund 1 offshore wind farm in the German North Sea.   The next step will be the final commissioning of all remaining wind turbines. More than half have been already commissioned. All closing activities will run during summer. When fully operational. […]

  • 24 April 2013

    Early this morning, a team of Bladt’s blacksmiths and engineers combined with raw crane power made use of the early sunrays to start raising the jacket foundation for the Borkum Riffgrund 1 offshore substation. Everything went as planned and the jacket and the substation will be ready for load out later this year as scheduled. […]

  • 27 April 2015
    Operations & Maintenance, Wind Farm Update

    DONG Energy is officially opening its operation management centre at Norddeich harbour today in the presence of the Parliamentary State Secretary Enak Ferlemann (Federal Ministry for Transport and Digital Infrastructure), Norden’s Mayoress Barbara Schlag and invited guests from business, public administration and politics. In her welcome speech, Trine Borum Bojsen, Managing Director for Germany of […]

  • 21 August 2014
    Business & Finance, Technology, Wind Farm Update

    Dong Energy’s 312MW offshore wind farm Borkum Riffgrund 1 has encountered an obstacle, as Siemens cannot deliver the 77 wind turbines on time, Danish media reported. The 4 MW turbine is an upgraded version of Siemens’ bestseller 3.6 MW, which was originally slated to be used at Borkum Riffgrund 1. In the spring, Dong announced […]

  • 3 March 2021
    Contracts & Tenders

    WIKING Helikopter Service has signed a contract extension with Ørsted to continue providing HEMS services for offshore wind projects in Germany. WIKING will provide HEMS (Helicopter Emergency Medical Service) for the Borkum Riffgrund 1 and 2 and Gode Wind 1 and 2 wind farms, as well as for the planned Borkum Riffgrund 3 and Gode […]

  • 23 May 2014
    Wind Farm Update

    DONG Energy is well on its way with the construction of the Borkum Riffgrund 1 offshore wind farm in the North Sea. After nine months of construction work, things are now moving fast. On Friday, 16th May 2014, the team completed the first half of the foundation installation when they installed monopile foundation and transition […]

  • 16 May 2019
    Vessels

    Ørsted’s newly built service operation vessel (SOV) Wind of Change has arrived in Emden, Germany, from where the vessel will soon start servicing offshore wind farms in the German North Sea. Wind of Change is expected to enter full operations and start working on the Borkum Riffgrund 1 & 2 and Gode Wind 1 & 2 […]

  • 25 March 2015
    Vessels

    Last week, DBB Jack-Up’s new purpose-built vessel J/U WIND SERVER commenced a new contract. The vessel has been chartered by Siemens AG to perform offshore installation support and function as accommodation vessel for Siemens’ commissioning teams on the installation of the Borkum Riffgrund 1 project in the German North Sea. The Borkum Riffgrund 1 project […]

  • 2 November 2015
    Vessels

    One of the engine rooms of the Beaumaris Bay wind farm service vessel, deployed at the Borkum Riffgrund 1 offshore wind farm, caught fire on Saturday, 31 October. There is an update on this article. Read it here: No Fire on ‘Beaumaris Bay’ The German Maritime Search and Rescue Association (DGzRS) reported that its rescue boat Bernhard Gruben immediately responded […]

  • 23 May 2014
    Grid Connection, Wind Farm Update

    The construction work at the offshore wind farm Borkum Riffgrund 1 is progressing rapidly. On 21st April 2014, the first cable was connected between the offshore substation and the first foundation. By the end of 2014, approximately 80 kilometers of cables will be installed connecting the foundations to the substation, the heart of the offshore wind […]

  • 2 July 2013
    Business & Finance

    The German energy company RWE has chosen Bladt Industries to design and fabricate the platform for its offshore wind farm Nordsee Ost. With its approximately 2,000 tonnes, this platform is the same size as the platform for the Borkum Riffgrund 1 offshore wind farm, which is currently in the process of constructing at Bladt facilities […]

  • 8 November 2015

    Fire Breaks Out on WFSV at Borkum Riffgrund 1 One of the engine rooms of the Beaumaris Bay wind farm service vessel, deployed at the Borkum Riffgrund 1 offshore wind farm, caught fire on Saturday, 31 October. Scotland Greenlights World’s Largest Floating Wind Project The Scottish Government has granted a marine licence to Statoil for […]

  • 10 January 2014
    Wind Farm Update

    On December 26th the first loadout of the Borkum Riffgrund 1 foundations took place. This week another 4 monopiles, 4 transition pieces and 4 anode cages – four complete foundations – were loaded onto the ship and headed for their destination in Eemshaven, Germany. Next load out is expected to take place next weekend. Bladt […]

  • 6 May 2015
    Wind Farm Update

    TÜV NORD has received an order from Dong Energy to monitor commissioning of the offshore wind farm Borkum Riffgrund 1. Experts will test the function of the wind turbines on site – in particular their safety systems. TÜV NORD will also issue the project certificate at the end of the commissioning process – which is […]

  • 11 December 2014
    Grid Connection, Wind Farm Update

    Last week, CT Offshore completed the installation and burial of 44 inter-array cables at the DONG Energy wind farm Borkum Riffgrund 1. “The valuable experience gained from the West of Duddon Sands and Gwynt y Môr projects earlier this year has played an important role to secure a smooth running project,” Hans Peter Johannsen, Director of […]

  • 22 September 2014
    Operations & Maintenance, Technology, Wind Farm Update

    For CT Offshore, planning Borkum Riffgrund 1 from a cabling installation point of view has required more than a little creativity. For A2SEA, getting to and from DONG Energy’s Borkum Riffgrund 1 wind farm development, located 45 km off the German coast, is pretty much a straight-lined round trip from the port of Esbjerg in Denmark, […]

  • 26 August 2014
    Authorities, R&D, Technology

    The German Federal Maritime and Hydrographic Agency (BSH) has approved the suction bucket jacket foundation, which is installed without noisy pile driving. “We were particularly pleased with this foundation,” stated the President of BSH Monika Breuch-Moritz. “It shows that the authorities, academia and industry are continuously looking for solutions that strike a balance between protection […]

  • 10 December 2013
    Operations & Maintenance

    The turn-key grouting solution was provided to Volker Staal en Funderingen by Densit. The complete grouting package included the supply of UHPC grouting material, grouting equipment, supervisor assistance, as well as the overall planning and coordination at all stages of the project. The installation works were performed on board of Rambiz vessel owned by Scaldis […]

  • 29 July 2014
    Wind Farm Update

    GeoSea has just finalized the installation of 77 foundations on the DONG Energy Borkum Riffgrund 1 offshore wind farm. The installation works, including transport from the fabrication yard to the marshalling harbor, have proceeded in record times and finished ahead of schedule. The 77 units consisted of monopiles, weighing between 495 tonnes and 684 tonnes and measuring a diameter […]

  • 4 May 2016
    Operations & Maintenance

    Specialist Marine Consultants Ltd (SMC) has again been picked to provide offshore Marine Supervision for Siemens on the Borkum Riffgrund 1 Project. SMC’s marine supervisors will be responsible for the daily coordination of vessels for crew transfers and the transportation of supplies. They will be using the ATLAS Marine Coordination System and will be based […]

  • 4 April 2022
    Business & Finance, Wind Farm Update

    Irish investment company Greencoat Renewables PLC has signed an agreement to acquire 50 per cent of the 312 MW Borkum Riffgrund 1 offshore wind farm in Germany. Greencoat Renewables will acquire the stake from Kirkbi A/S (31.5 per cent) and William Demant Invest A/S (18.5 per cent) for a total cash consideration of around EUR […]

  • 17 March 2015
    Wind Farm Update

    The Borkum Riffgrund 1 offshore wind farm has reached halfway with the installation of 39 wind turbines. Due to good weather conditions during the last weeks the team was able to make good progress in installing the turbines about 54 kilometres off the German North Sea coast. At the same time, the cabling work for […]