    Germany’s Federal Maritime and Hydrographic Agency (BSH) has approved the offshore grid connection system for TenneT’s BorWin5 and BorWin epsilon project in the German North Sea. This marks the last project to be implemented based on the specifications of the Federal Offshore Plan 2017 for the North Sea. The area development plan, which has been […]

  • 26 December 2023
    Authorities, Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Planning & Permitting

    The German Federal Maritime and Hydrographic Agency (BSH) has issued a planning approval decision for the DolWin4 offshore grid connection in Germany’s Exclusive Economic Zone (EEZ) in the North Sea. DolWin4, the first offshore grid connection system being implemented by German transmission system operator (TSO) Amprion Offshore, will go into operation in 2028 and connect […]

  • 8 March 2024
    Business & Finance, Vessels

    Fincantieri-owned Vard has signed a contract with Navigare Capital Partners, in close cooperation with Norwind Offshore, for the design and construction of one tailor-made Commissioning Service Operation Vessel (CSOV). The parties have also agreed on new options for two additional vessels. Scheduled for delivery in the first quarter of 2026, the vessel is of VARD […]

  • 22 November 2023
    Contracts & Tenders, Equipment, Grid Connection, Manufacturing, Offshore Platforms, Supply Chain

    German shipbuilding company, Meyer Werft, has been awarded its first contract for steel construction work for four Amprion offshore converter platforms. Amprion Offshore has commissioned Dragados Offshore and Siemens Energy to build the offshore converter platforms. The consortium has now awarded parts of the production to Meyer Werft. Amprion said that the shipyard is to […]

  • 19 March 2024
    Business & Finance, Cables, Fixed-Bottom, Grid Connection

    TenneT and Nexans, which signed framework agreements for three offshore grid connections last year, have now signed a call-off contract for the BalWin3 and LanWin3 projects, each of which will have a capacity of 2 GW and will link offshore wind farms to the German grid. In May 2023, TenneT awarded NKT, Nexans, and a […]

  • 8 January 2024
    Authorities, Grid Connection, Offshore Platforms, Planning & Permitting

    Germany’s Federal Maritime and Hydrographic Agency (BHS) has issued a planning approval decision for 50Hertz’s Ostwind 3 offshore wind grid connection in the Baltic Sea. According to BHS, the new standard for connecting offshore wind farms, the so-called 66 kV direct connection concept, is being implemented, that does not require the construction of additional substation platforms […]

  • 20 March 2024
    Grid Connection, Market Outlooks, Outlook & Strategy

    Great Britain’s electricity system operator (ESO) has proposed a GBP 58 billion (approximately EUR 68 billion) investment in the electricity grid. The proposal outlines a vision for incorporating an additional 21 GW of offshore wind into the grid by 2035, which would bring the country’s total offshore wind capacity to a potential 86 GW. The […]

  • 7 July 2023
    Contracts & Tenders, Grid Connection

    Asso.subsea has signed a contract with Nexans for the transportation, installation and protection of the nearshore section of the BorWin6 offshore cable in Germany, with offshore work scheduled for 2025. The company will be involved in the design and execution of this part of the project in shallow waters and will also assist Nexans in […]

  • 5 July 2023
    Grid Connection

    The construction work has begun on the BorWin6 High-Voltage Direct Current (HVDC) project which will be delivered by TenneT to link 980 MW of offshore wind capacity to the German grid. Through a consortium with Global Energy Interconnection Research Institute and C-EPRI Electric Power Engineering (GEIRI/CEPRI), McDermott is providing engineering, procurement, construction, installation, and commissioning […]

  • 7 October 2016
    Grid Connection

    Transmission systems operator TenneT and Siemens have held a topping-out ceremony for the Emden/Ost converter station, part of the 900MW BorWin3 grid connection project. The land station Emden/Ost is an essential element for the grid connection of offshore wind farms, TenneT said. With the BorWin3 project a high voltage direct current (HVDC) transmission will be realized […]

  • 7 February 2017
    Grid Connection

    The transformer for TenneT’s substation, which will collect and distribute the electricity from the BorWin3 offshore grid connection, has been transported on Saturday from the seaport in Emden to the site at Emden/Ost in the northwest of Germany.

  • 16 February 2015
    Business & Finance, Grid Connection, R&D, Wind Farm Update

    DC Netz BorWin3 GmbH has awarded a contract to N-Sea Offshore Wind BV to undertake unexploded ordnance (UXO) surveys at BorWin3 site.  Specifically, the work covers surveying of the seabed to help the identification and removal of undiscovered ordnance along the cable route of BorWin3. The planned BorWin3 submarine cable connection is a DC power transmission link with a […]

  • 14 May 2019
    Grid Connection

    Corrosion Protection Consult GmbH has signed a contract to provide corrosion protection inspection on the BorWin gamma converter station in the German North Sea. The contract started recently and is expected to be completed by the end of June. The scope of work includes monitoring and inspection of the coating works at the newly installed converter […]

  • 8 October 2018
    Grid Connection

    The BorWin gamma topside has completed its journey from Dubai to the installation site in the German North Sea, TenneT reports.

  • 11 September 2018
    Grid Connection, Ports & Logistics

    The BorWin gamma topside has started its journey from the Drydocks World – Dubai to the German North Sea.

  • 20 May 2016
    Grid Connection

    A foundation stone for the land-based converter station, which is part of the BorWin3 grid connection project, was laid yesterday. At the converter station’s Emden / East site, a time capsule with coins, national newspaper and building plans was taken into the ground and thus marked the groundbreaking ceremony. With the BorWin3 project a high voltage direct current (HVDC) […]

  • 20 August 2018
    Contracts & Tenders

    Petrofac has hired SeaRenergy to support the hook-up and commissioning of TenneT’s 900MW BorWin3 HVDC platform (BorWin Gamma), once the topside is installed on top of its foundation already in place at the site off Germany.

  • 12 July 2017
    Grid Connection, Wind Farm Update

    Chinese power cable manufacturer ZTT has contracted SeaRenergy to provide QHSE management & support for the HVAC export cable connection between the BorWin gamma platform and the 497MW EnBW Hohe See wind farm in the German North Sea.

  • 15 April 2014
    Grid Connection

    Siemens has received an order from TenneT for an offshore wind farm grid connection in the North Sea. In a consortium with Petrofac Siemens will supply the complete technology for efficient direct-current transmission for the BorWin3 grid connection as the consortium leader. The consortium partner Petrofac, with over 30 years of experience as a leading […]

  • 4 April 2013
    Contracts & Tenders, Grid Connection

    DC Netz BorWin3 GmbH is inviting tenders for offshore electrical distribution related to BorWin3. The invited tenders are for transmission system of electric power (approximately 900 MW) between the offshore wind farms in the cluster BorWin and a grid connection point on land. In particular, the transmission power, the losses, the availability and compliance with […]

  • 9 May 2018
    Grid Connection, Ports & Logistics

    Heerema Fabrication Group (HFG) has shipped out the jacket foundation for TenneT’s 900MW BorWin3 HVDC platform.

  • 29 August 2014
    Environment, Grid Connection

    Grid operator in Germany, TenneT, is seeking contractor to conduct an unexploded explosive ordnance (UXO) survey, identification and removal on the cable route BorWin3 in the German sector of the North Sea. The planned BorWin3 submarine cable connection is a DC power transmission link with a length of 130 km. Landfall is at Hamswehrum in […]

  • 7 July 2023
    Authorities, Wind Farm Update

    Skyborn Sweden (Skyborn) has submitted a permit application to the Swedish government to build the 2,800 MW Fyrskeppet offshore wind farm north of Örskar in Uppsala County, about 50 kilometres off the coast. The Fyrskeppet offshore wind farm is expected to generate up to 11 TWh fossil-free electricity when completed, which could be enough to […]

  • 13 October 2014
    Grid Connection

    Drydocks World has signed an agreement with Petrofac to build the BorWin3 high voltage direct current (HVDC) converter platform in the North Sea, named BorWin gamma. When completed, this will provide an essential renewable offshore resource to meet increasing energy demands. Drydocks World has successfully secured the contract for the fabrication, commissioning and load out […]

  • 15 May 2018
    Grid Connection

    The jacket foundation for TenneT’s 900MW BorWin3 HVDC platform has been installed in the German North Sea.

  • 29 August 2018
    Grid Connection

    Drydocks World – Dubai has completed the topside for the 900MW BorWin gamma HVDC platform, which will soon sail to its offshore site in the German part of the North Sea, where it is expected to arrive mid-September.