652 results found for 'Baltica 2 '

652 results found for 'Baltica 2 '
Order results by

A list of search results

  • 11 December 2025
    Cables, Grid Connection, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    ZTT Submarine Cable & System has commenced the production of the export cables for the 1.5 GW Baltica 2 offshore wind farm in Poland, owned by a joint venture between Ørsted and PGE. The project’s export cables will be delivered by the Chinese cable manufacturer and Hellenic Cables, a Greece-based supplier, and installed by Boskalis, under […]

  • 20 March 2026
    Contracts & Tenders, Manufacturing, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Polish offshore wind tower manufacturer Baltic Towers has signed a cooperation agreement with Siemens Gamesa for the supply of the largest batch of wind turbine towers for the Baltica 2 offshore wind project in Poland, jointly developed by PGE Polska Grupa Energetyczna and Ørsted.  Baltic Towers was established in 2023 as a joint venture between […]

  • 27 October 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first high-voltage transformer has been placed on one of four offshore substations that will be installed at the Baltica 2 offshore wind project site in the Polish Baltic Sea. The substations will collect electricity from the 107 Siemens Gamesa 14 MW-222 turbines, stepping up the voltage, and transmitting the electricity to shore. “Installing the transformer […]

  • 22 January 2026
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    EEW SPC has loaded out the first batch of monopiles for the Baltica 2 offshore wind project, being built in Poland by Ørsted and PGE Polska Grupa Energetyczna. “Our operations at Rostock harbor provide a key logistical benefit to the project’s supply chain. As a non-tidal port, it allows us to execute safe, high-precision load-outs […]

  • 19 December 2025
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Four transformers and other high-voltage power equipment necessary for power transfer to the Polish national grid have been delivered to the construction site of the onshore substation for the Baltica 2 offshore wind farm, being built by a joint venture of PGE and Ørsted in the Polish Baltic Sea. The onshore infrastructure for the offshore […]

  • 27 February 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Wind Farm Update

    On 25 February, the President of the Polish Energy Regulatory Office (URE) published a formal update stating that the regulator has granted a “promise of concession” for the Baltica 2 offshore wind farm, which is jointly developed by Polish utility PGE and Danish energy company Ørsted. This is the second official concession promise issued for […]

  • 23 February 2026
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    UK-registered Novastar Energy Holdings, a wholly-owned subsidiary of UAE-based HEA Energy, which bought three Seajacks vessels from Eneti in 2023, has secured a contract for Baltica 2, a 1.5 GW offshore wind farm being built by PGE and Ørsted in Poland. According to a contract award notice published this month on an EU tender website, […]

  • 20 February 2026
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Boskalis has completed the preparation of 150 kilometres of inter-array cable routes at the 1.5 GW Baltica 2 offshore wind farm site in Poland. In 2023, Boskalis was awarded a contract for the transportation and installation of export and inter-array cables for the Polish offshore wind farm, owned by PGE and Ørsted. Under the contract, the Dutch […]

  • 7 January 2026
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Polish state-owned transmission system operator (TSO), Polskie Sieci Elektroenergetyczne (PSE), has confirmed the technical readiness of the transmission infrastructure to accept power from offshore wind farms. “The new Choczewo station and the expanded Żarnowiec station, as well as the 400 kV line connecting them, are ready to transmit energy from wind farms being built in […]

  • 29 October 2025
    Business & Finance, Collaboration, Outlook & Strategy

    UK-headquartered Acteon and Taiwan-based marine solutions provider Wynnergy Marine have signed a strategic Memorandum of Understanding (MoU) to jointly deliver renewable energy projects across the region. The partnership supports offshore wind growth in Taiwan by providing integrated solutions that combine subsea services and local marine vessels. Together, the companies combine Acteon’s knowledge in geophysical and […]

  • 10 December 2025
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    Energy and marine consultancy ABL has been appointed to provide marine warranty survey (MWS) services to support Ocean Winds with the construction of Poland’s BC-Wind offshore wind farm. The BC-Wind offshore wind farm is to be constructed over an area of approximately 90 square kilometres, located within Poland’s Baltic Sea Exclusive Economic Zone, approximately 23 […]

  • 30 September 2025
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    The joint venture between Ørsted and PGE has awarded Acteon’s geo-services business line, UTEC, a structural monitoring contract for the Baltica 2 offshore wind farm, which the joint venture is building in Poland. Under the contract, Acteon is responsible for the design, engineering, procurement, installation and commissioning of measurement and associated data acquisition systems for […]

  • 29 September 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    The first batch of monopile foundations for the 1.5 GW Baltica 2 offshore wind project in Poland has rolled off the factory floor. A total of 111 monopiles are planned to be installed at the Baltica 2 site, 107 for wind turbines and four for the offshore substation. The units are up to 100 metres […]

  • 11 November 2025
    Contracts & Tenders, Equipment, Grid Connection, Offshore Platforms, Supply Chain, Wind Farm Update

    Palfinger has been contracted by Iemants, a subsidiary of Smulders, to deliver two fully electric jib cranes for the Bałtyk 2 and Bałtyk 3 offshore wind farms in Poland, where the cranes will be installed on the projects’ two offshore substations. According to Palfinger, this the first time that its fully electric DKJ500e offshore cranes […]

  • 15 September 2025
    Business & Finance, Contracts & Tenders, Ports & Logistics, Supply Chain

    ORLEN Neptun and Smulders have signed a contract for the lease of the Świnoujście Offshore Terminal in Poland. The terminal will serve as a service and logistics base for Smulders, where the company will store and assemble internal platforms for the Baltica 2 offshore wind project. The agreement involves the lease of the terminal space, […]

  • 19 September 2025
    Equipment, Manufacturing, Supply Chain, Wind Turbines

    The first offshore wind tower section has been produced at the new Baltic Towers facility in Gdańsk, Poland. The event was attended by Minister of Climate and Environment Paulina Hennig-Kloska, Pomeranian Voivode Beata Rutkiewicz, Marshal of the Pomeranian Voivodeship Mieczysław Struk, Mayor of the City of Gdańsk Aleksandra Dulkiewicz, and representatives of the Government of […]

  • 25 February 2026
    Grid Connection

    Lithuania, Latvia, and Germany are planning a joint offshore interconnector that would enable electricity trading between the Baltic countries and Germany and allow for the integration of up to 2 GW of offshore wind capacity in Lithuania and Latvia. The energy ministers of the three countries signed a joint declaration of intent on 18 February, […]

  • 24 March 2026
    Cables, Contracts & Tenders, Offshore Platforms, Supply Chain, Wind Turbines

    Bilfinger has been selected to provide supervision services for the Bałtyk 2 and Bałtyk 3 offshore wind farms in the Polish Baltic Sea, developed by Equinor and Polenergia. The company’s scope covers supervision of the installation of offshore substations, wind turbines and more than 120 kilometres of export cables, including landfall connections to the onshore […]

  • 27 January 2026
    Fixed-Bottom, Operations & Maintenance, Ports & Logistics, Project Updates, Wind Farm Update

    Orlen Neptun has entered into a land reservation agreement with the Kołobrzeg Sea Port Authority for a site that will later house an operations and maintenance (O&M) base for its Baltic West offshore wind farm. The Kołobrzeg Sea Port is closest to the project location among all ports available in this part of the Baltic […]

  • 11 February 2026
    Fixed-Bottom, Grid Connection, Wind Farm Update

    Germany’s total offshore wind power generation in 2025 amounted to 26.1 TWh, of which 20.8 TWh came from the North Sea and 5.38 TWh from the Baltic Sea, according to TenneT Germany, the transmission system operator (TSO) in charge of the country’s North Sea grid. In this article: With onshore wind farms contributing 106.5 TWh […]

  • 14 January 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates

    HSI, a joint venture between HSM Offshore Energy, Smulders and Iv, has installed the Jasmund offshore substation (OSS), which will connect the Windanker offshore wind farm to the German electricity grid, at its designated location in the Baltic Sea. The Jasmund platform is part of the Ostwind 3 grid connection project, which will collect 300 MW […]

  • 18 February 2026
    Fixed-Bottom, Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Offshore construction has begun on the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, developed by Equinor and Polenergia, which will together have 100 wind turbines and an installed capacity of 1.4 GW. The 2026 offshore construction campaign will see the installation of 100 monopiles, transition pieces (TPs), offshore substation components, subsea cables […]

  • 27 February 2026
    Vessels

    Heerema Marine Contractors has put its semi-submersible crane vessel (SSCV) Thialf, the second-largest SSCV in the world, through a lifetime extension programme, with the vessel currently undergoing the first stage of the work in Rotterdam, ahead of its mobilisation for a Polish offshore wind project next month. Thialf will undergo what Heerema Marine Contractors says is […]

  • 20 November 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    [NOTE: The article title was updated on 3 February 2026. The previous title was “TotalEnergies Submits Permits for 3 GW German Offshore Wind Projects”.] TotalEnergies has submitted permit applications for two of its offshore wind farms in Germany, totalling approximately 3 GW, to the Federal Maritime and Hydrographic Agency (BSH). The projects are the NordseeEnergies […]

  • 1 December 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ocean Winds, a 50-50 joint venture between EDP Renewables and ENGIE, has secured around EUR 2 billion in project finance and reached financial close for the 390 MW BC-Wind offshore wind farm in the Polish Exclusive Economic Zone (EEZ) of the Baltic Sea, moving the project into the construction phase. The project finance is supported […]

  • 2 December 2025
    Business development, Energy Islands, Grid Connection, Power-to-X, Research & Development, Vessels

    Stillstrom and Port of Roenne have teamed up on a study looking into integrating offshore wind energy with maritime electrification. Maersk’s offshore power and charging solutions developer and the Danish port have initiated a joint white paper to explore how Energy Island Bornholm could serve as a blueprint for this kind of integration. The study, […]