Cost of CVOW Project Rises to USD 10.7 Billion, Completion on Track for 2026
Share this article On 3 February, Dominion Energy announced that the estimated total costs for the Coastal Virginia Offshore Wind (CVOW) project have increased by nine per cent. In addition, the developer said that the 2.6 GW wind farm is now approximately 50 per cent complete and remains on track for on-time completion at the … Continue reading Cost of CVOW Project Rises to USD 10.7 Billion, Completion on Track for 2026