All Formosa 1 Phase 2 Turbines In Place

All 20 Siemens Gamesa 6MW turbines have been installed at the Formosa 1 Phase 2 offshore wind project in Taiwan.

All Formosa 1 Phase 2 Turbines In Place
Source: Swancor

To remind, jack-up vessel Seajacks Zaratan installed the first turbine at the project site 6km off the west coast of the Miaoli district in the Taiwan Strait in July.

Prior to commercial operation, each turbine goes through a power generation test which takes 10 to 14 days to complete.

Formosa 1 Phase 2, which is an extension of the existing two-turbine Formosa 1 Phase 1 project, generated first power in September. Full commissioning is expected by the end of the year.

The 120MW project is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%).

All Formosa 1 Phase 2 Turbines In Place
Source: Swancor
Related news

List of related news articles

Posted: 2 months ago

First Formosa 1 Phase 2 Turbine Stands

[…]

Categories:
  • Wind Farm Update
Posted: 2 months ago
Posted: about 1 month ago

Formosa 1 Phase 2 Produces First Power

[…]

Categories:
  • Wind Farm Update
Posted: about 1 month ago
Posted: 2 months ago

Tekmar to Protect Formosa 1 Phase 2 Cables

[…]

Categories:
  • Grid Connection
Posted: 2 months ago
Posted: 2 months ago

Jan De Nul Installs Formosa 1 Phase 2 Export Cables

[…]

Categories:
  • Wind Farm Update
Posted: 2 months ago