Foundation Installation Begins at Formosa 1 Phase 2

The installation of foundations has kicked off at the Formosa 1 Phase 2 offshore wind project in Taiwan.

The installation began in early June, a spokesperson from COWI, who designed all the steelwork for the 20 monopiles and transition pieces, told Offshore WIND.

Seaway Yudin is installing the foundations, which comprise monopiles produced by Germany's EEW SPC and transition pieces manufactured by Thailand's CUEL Limited.

Jan De Nul is in charge of the procurement and installation of the foundations, including scour protection and cables. Construction is expected to be completed this year.

Formosa 1 Phase 2, the extension of the existing Formosa Phase 1 wind farm, will feature 20 Siemens Gamesa 6MW turbines located 3 kilometers off the coast of Miaoli.

The 128MW project is being developed by a partnership of Ørsted, JERA, Macquarie Capital and Swancor Renewable Energy.

Related news

List of related news articles

Posted: 3 months ago

Zaratan Geared Up for Formosa 1 Phase 2

Seajacks’ self-propelled jack-up vessel Zaratan has departed for Taiwan ready to begin installation ...

Categories:
  • Wind Farm Update
Posted: 3 months ago
Posted: 3 months ago

SMC Adds SeaPlanner to Formosa 1 Phase 2 Work Kit

SeaRoc has secured a contract to supply its marine management system SeaPlanner to support the const...

Categories:
  • Operations & Maintenance
Posted: 3 months ago
Posted: 1 months ago

Formosa 1 Phase 2 Breaks Ground

The Formosa 1 Phase 2 project has entered the construction phase following a groundbreaking ceremony...

Categories:
  • Wind Farm Update
Posted: 1 months ago
Posted: 2 months ago

Taichung Port Receives Formosa Steel

Transition pieces and monopiles for the Formosa 1 Phase 2 offshore wind farm have started arriving a...

Categories:
  • Wind Farm Update
Posted: 2 months ago