ABB to Deliver Kriegers Flak HVDC Converter Station

ABB has received an order worth around $140 million from Energinet.dk in Denmark and 50Hertz Transmission in Germany to design, supply and install an HVDC converter station in Bentwisch, Northern Germany.

Image: HVDC light valve hall

The company will provide the complete HVDC station including transformers, converter valves, cooling systems, control and protection and other related equipment at the converter station.

The HVDC Light “back-to-back” converter station will allow the connection of the asynchronous AC power grids of Eastern Denmark and Germany.

This is a part of the “Kriegers Flak combined grid solution” project, which establishes the world’s first offshore interconnection by using the national grid connections to the future Danish Kriegers Flak and operating German Baltic 1 and 2 offshore wind farms.

Image: ABB
Image: ABB

The interconnector will have a capacity of 400 megawatts (MW), equivalent to the energy requirement of more than 400,000 households.

ABB was also previously awarded a $100 million AC subsea cable system order for connecting the Danish Kriegers Flak wind farm in 2015.

“ABB has an unparalleled track record of HVDC interconnections and is playing a key role in enabling the vision of a European grid,” said Claudio Facchin, president of ABB’s Power Grids division. “The integration of renewable energy and the development of interconnections are key elements of ABB’s Next Level Strategy, addressing the growing need for electricity with minimum environmental impact.”