Bladt Starts Building Nobelwind Substation

After the Nobelwind team announced that they have reached financial close for the Nobelwind (Bligh Bank II) offshore wind farm project, Bladt started the construction of the offshore high voltage substation (OHVS).

As the main contractor of the OHVS, Bladt is responsible for the steel construction work of the substation as well as the overall engineering, procurement, construction and installation of the substation.

The company will construct the substation in close cooperation with its partner Semco Maritime, which will undertake the design, onshore construction and offshore commissioning of the high voltage electrical systems and all other technical systems.

The offshore substation is scheduled to be delivered in the fourth quarter of 2016.

Image: Bladt Industries