Damen Fits New Feet to MPI Resolution

Damen Fits New Feet to MPI Resolution

Damen ARNO Dunkerque, part of the Damen Shiprepair & Conversion Group, has given a new set of ‘feet’ to the world’s first purpose-built offshore wind turbine installation and maintenance vessel, the 2003-built MPI Resolution.

The yard has carried out upgrades on the feet or ‘spudcans’ of all the jack-up vessel’s six legs to give them the additional strength they need to withstand the huge loads to which they are subjected when spudding on rocky seabeds.

Damen ARNO Dunkerque carried out the steel work in collaboration with Intelligent Engineering in an operation which was carried out in conjunction with the vessel’s 10-year survey and drydocking, as well as extensive refitting operations. The whole operation was completed within a month, allowing the vessel to leave Dunkirk on April 3, a day ahead of its scheduled delivery date, despite its having arrived at the French port two weeks later than expected. 

Damen ARNO Dunkerque managing director Bob Derks said that the yard worked 24 hours a day and seven days a week to ensure that the work was completed on time. With outside personnel, the yard’s 165-strong permanent workforce was doubled.

Damen Fits New Feet to MPI Resolution (2)Intelligent Engineering SPS shipbuilding director Martin Brooking said that this would not have been possible if the existing steel plate had been replaced with 100 mm steel plate, which would have involved much more time and work.“We were able to maximise the available resources of the shipyard because we were using 40 mm plate and we created this composite sandwich using the polyurethane core. Basically, what we bring to the design in that way is that we essentially make a new composite plate which is 120 mm thick.” 

This solution also allowed the vessel’s operator, MPI Offshore, part of the Netherlands’ Vroon shipping group, to strengthen the spudcans without exceeding the 25 tonne per leg additional weight limit it had set itself for the work.

MPI Offshore fleet manager Dave Galloway said that the upgrade of the spudcans had become necessary to enable the MPI Resolution to work on the Humber Gateway wind farm project currently under construction off the east coast of England. “The Intelligent Engineering upgrade gives a significant increase to the load-bearing capacity of the spudcan without too much increase in weight,” he said.

Press Release, April 10, 2014; Image: mpi-offshore/ damen